EXHIBIT A of EXHIBIT 1
<br />SANTA ANA (ORANGE)
<br />RECOGNIZED OBLIGATION PAYMENT SCHEDULE (ROPS 13-14A) - Notes (Optional)
<br />Juhi 1. 2013 through December 31. 2013
<br />DRAFT
<br />Item # Project Name / Debt Obligation Notes/Comments
<br />116 Audited Financial Statements Actual amount spent in ROPS 2 period. This item was denied on ROPS 2 (line item 091), so it was included again on ROPS 3 (line item #116). RODS 3 Meet and
<br /> Confer Final Determination letter dated December 18, 2012 stated that "although Finance agrees that these items may be enforceable obligations outside of the
<br /> administrative cost cap, the Agency did not provide documentation to demonstrate its position." Successor Agency staff provided additional documentation on
<br /> January 14, 2013, and is awaiting an official response from DOF. Therefore, without a formal resolution on this item, it is included on ROPS 13-14A as suggested in
<br /> DOF's December 18, 2012 letter. Total amount spent also includes expenditures for the Due Diligence Review (line Item #62 on ROPS 3) that was approved by
<br /> DOF.
<br />117 SA Venture Partnership & Other MainPlace No longer applicable. See comments for Item #35.
<br /> Agreements
<br />_ 118 Litigation for Item #15, 17, 22 See comments for item #18.
<br />119 Employee Layoff/Termination Payment Estimated amount per Section 34171 (d)(1)(C).
<br /> Obligations
<br />120 Employee Obligations Estimated amount per Section 34171 (d)(1)(C).
<br />121 Project Costs for Item #13 Estimated amount.
<br />122 Project Costs for Item #19 Estimated amount.
<br />123 Settlement Agreements - Housing Zero amount requested this ROPS six-month period, as DOF has denied this item on previous ROPS. However, as the Successor Agency believes these five
<br /> settlement agreements are continuing enforceable obligations and there are lawsuit(s) pending that have yet to be determined by the courts, this item is again
<br /> included on ROPS 13-14A. Total Due During FY 13-14 Column amount of $26,332,573 is an estimated amount of former tax increment that should have
<br /> been/should be allocated to the Successor Agency for the period of February 1, 2012 through December 31, 2013 (ROPS 1, 2, 3 & 13-14A periods).
<br />124 Settlement Agreement - S. Main Zero amount requested this POPS six-month period, as DOF has denied this item on previous ROPS. However, as the Successor Agency believes this settlement
<br /> Commercial Corridor agreement is a continuing enforceable obligation and there is a lawsuit pending that has yet to be determined by the courts, this item is again included on ROPS 13-
<br /> 14A. Total Due During FY 13-14 Column amount of $3,850,000 is an estimated amount of former tax increment that should have been/should be allocated to the
<br />_ Successor Agency for the period of February 1, 2012 through December 31, 2013 (BOPS 1, 2, 3 & 13-14A periods).
<br />125 Settlement Agreements - Housing Zero amount requested this ROPS sin-month period, as DOF has denied this item on previous ROPS. However, as the Successor Agency believes these five
<br /> Obligation settlement agreements are continuing enforceable obligations and there are lawsuit(s) pending that have yet to be determined by the courts, this item is again
<br /> included on ROPS 13-14A. Total Oustanding Debt or Obligation column amount of $30,593,530 is the amount of former tax increment that is encumbered by
<br /> these settlement agreements and is part of the $54,241,958 amount demanded DOF in its LMIHF DOR Meet and Confer Final Determination letter dated December
<br /> 26, 2012. DOF has indicated a revised letter will be issued to the Succesor Agency by early February 2013, but no such letter has been received as of this POPS 13-
<br /> 14A submission date.
<br />126 South Main Settlement Agreement - Zero amount requested this POPS six-month period, as DOF has denied this item on previous ROPS. However, as the Successor Agency believes this settlement
<br /> Current Obligation agreement is a continuing enforceable obligation and there is a lawsuit pending that has yet to be determined by the courts, this item is again included on ROPS 13-
<br /> 14A. Total Oustanding Debt or Obligation column amount of $11,080,747 is the amount of the former tax increment that is encumbered by this settlement
<br /> agreement after deducting the $75,000 for line Item #18, and identified in the All Other Funds and Accounts DDR (Exhibit I).
<br />127 South Main Commercial Corridor Loan for $500,000 requested this POPS six-month period (repayment schedule to be approved by Oversight Board at the same meeting). The Successor Agency believes the
<br /> SERAF FY 09-30 repayment of this loan to pay the FY 09/10 SERAF payment is a continuing enforceable obligation, as the monies were borrowed from a fund created to track and
<br /> utilize the funds from the South Main Commerical Corridor component of the South Main Settlement Agreement. There is a lawsuit pending that has yet to be
<br /> determined by the courts.
<br />128 DDA -Vista Del Rio Hsg Partners LP This is the amount paid/to be paid to the developer as stipulated in the Disposition and Development Agreement (DDA) from February 1, 2012 through the
<br /> completion of the project. Expenditures from February 1, 2012 through June 30, 2012 for this DDA are part of the $8,467,780 in LMIHF expenditures identified in
<br /> the LMIHF DDR and at the LMIHF DDR Meet and Confer. The remaining amount to complete the project was identified and is part of the $17,613,146 amount in
<br /> the Housing Asset Transfer (HAT) Form approved by DOF. However, DOF is demanding $54,241,958 in its LMIHF DDR Meet and Confer Final Determination letter
<br /> dated December 26, 2012 which includes the expenditures spent from February 1, 2012 through June 30, 2012 and the amount identified in the HAT. DOF has
<br /> indicated a revised letter will be issued to the Succesor Agency by early February 2013, but no such letter has been received as of this POPS 13-14A submission
<br /> date. Therefore, if DOF continues to demand the $54,241,958 from the Successor Agency, then the amount shown under the RPTTF is required to complete the
<br /> project and be in compliance with the DOA. Otherwise, the amount under Reserve Balance is appropriate.
<br />129 Project Costs for Item #128 This is the amount of the project and construction management related costs from February 1, 2012 through the completion of the project. Expenditures from
<br /> February 1, 2012 through June 30, 2012 for this item are part of the $8,467,780 in LMIHF expenditures identified in the LMIHF DDR and at the LMIHF DOR Meet
<br /> and Confer. The remaining amount to complete the project was identified and is part of the $17,613,146 amount in the Housing Asset Transfer (HAT) Form
<br /> approved by DOF. However, DOF is demanding $54,241,958 in its LMIHF DDR Meet and Confer Final Determination letter dated December 26, 2012 which
<br /> includes the expenditures spent from February 1, 2012 through June 30, 2012 and the amount identified in the HAT. DOF has indicated a revised letter will be
<br /> issued to the Succesor Agency by early February 2013, but no such letter has been received as of this ROPS 13-14A submission date. Therefore, if DOF continues to
<br /> demand the $54,241,958 from the Successor Agency, then the amount shown under the RPTTF is required to complete the
<br />project. Otherwise, the amount under
<br /> Reserve Balance is appropriate.
<br />130 DDA - Habitat for Humanity This is the amount paid/to be paid to the developer as stipulated in the Disposition and Development Agreement (DDA) from February 1, 2012 through the
<br /> completion of the project. Expenditures from February 1, 2012 through June 30, 2012 for this DDA are part of the $8,467,780 in LMIHF expenditures identified in
<br /> the LMIHF DDR and at the LMIHF DDR Meet and Confer. The remaining amount to complete the project was identified and is part of the $17,613,146 amount in
<br /> the Housing Asset Transfer (HAT) Form approved by DOF. However, DOF is demanding $54,241,958 in its LMIHF DDR Meet and Confer Final Determination letter
<br /> dated December 26, 2012 which includes the expenditures spent from February 1, 2012 through June 30, 2012 and the amount identified in the HAT. DOF has
<br /> indicated a revised letter will be issued to the Succesor Agency by early February 2013, but no such letter has been received as of this ROPS 13-14A submission
<br /> date. Therefore, if DOF continues to demand the $54,241,958 from the Successor Agency, then the amount shown under the RPTTF is required to complete the
<br /> project and be in compliance with the DDA. Otherwise, the amount under Reserve Balance is appropriate.
<br />131 Project Costs for Item #130 This is the a unt of the project and construction management related costs from February 1, 2012 through the completion of the project Expenditures from
<br /> February 1, 2012 through June 30, 2012 for this item are part of the $8,467,780 in LMIHF expenditures identified in the LMIHF DDR and at the LMIHF DDR Meet
<br /> and Confer. The remaining amount to complete the project was identified and is part of the $17,613,146 amount in the Housing Asset Transfer (HAT) Form
<br /> approved by DOF. However, DOF is demanding $54,241,958 in its LMIHF DOR Meet and Confer Final Determination letter dated December 26, 2012 which
<br /> includes the expenditures spent from February 1, 2012 through June 30, 2012 and the amount identified in the HAT. DOF has indicated a revised letter will be
<br /> issued to the Succesor Agency by early February 2013, but no such letter has been received as of this ROPS 13-14A submission date. Therefore, if DOF continues to
<br /> demand the $54,241,958 from the Successor Agency, then the amount shown under the RPTTF is required to complete the project. Otherwise, the amount under
<br /> Reserve Balance is appropriate.
<br />132 DDA - Station District New Construction This is the amount paid/to be paid to the developer as stipulated in the Disposition and Development Agreement (DDA) from February 1, 2012 through the
<br /> completion of the project. Expenditures from February 1, 2012 through June 30, 2012 for this DDA are part of the $8,467,780 in LMIHF expenditures identified in
<br /> the LMIHF DDR and at the LMIHF DDR Meet and Confer. The remaining amount to complete the project was identified and is part of the $17,613,146 amount in
<br /> the Housing Asset Transfer (HAT) Form approved by DOF. However, DOF is demanding $54,241,958 in its LMIHF DDR Meet and Confer Final Determination letter
<br /> dated December 26, 2012 which includes the expenditures spent from February 1, 2012 through June 30, 2012 and the amount identified in the HAT. DOF has
<br /> indicated a revised letter will be issued to the Succesor Agency by early February 2013, but no such letter has been received as of this POPS 13-14A submission
<br /> date. Therefore, if DOF continues to demand the $54,241,958 from the Successor Agency, then the amount shown under the RPTTF is required to complete the
<br /> project and be in compliance with the DDA. Otherwise, the amount under Reserve Balance is appropriate.
<br />133 Project Costs for Item #132 This is the amount of the project and construction management related costs from February 1, 2012 through the completion of the project Expenditures from
<br /> February 1, 2012 through June 30, 2012 for this item are part of the $8,467,780 in LMIHF expenditures identified in the LMIHF DDR and at the LMIHF DDR Meet
<br /> and Confer. The remaining amount to complete the project was identified and is part of the 517,613,146 amount in the Housing Asset Transfer (HAT) Form
<br /> approved by DOF. However, DOF is demanding $54,241,958 in its LMIHF DDR Meet and Confer Final Determination letter dated December 26, 2012 which
<br /> includes the expenditures spent from February 1, 2012 through June 30, 2012 and the amount identified in the HAT. DOF has indicated a revised letter will be
<br /> sued to the Succesor Agency by early February 2013, but no such letter has been received as of this ROPS 13-14A submission date. Therefore, if DOF continues to
<br /> demand the $54,241,958 from the Successor Agency, then the amount shown under the RPTTF is required to complete the project. Otherwise, the amount under
<br /> Reserve Balance is appropriate.
<br />3-17
|