Project 13 -7516 <br />Request for Approval of Change Order No. 2 <br />Page 2 of 3 <br />3. At Madison Park, the plans show the proposed chain link fence in the same location <br />as the proposed basketball court light poles. Change Order #1 added custom <br />brackets to attach the fence to the light poles; however the pole manufacturer <br />recommended that additional fence posts be installed to support the weight of the <br />fence. (PCO #13) <br />AGREED COST $ 1,770.00 <br />4. After completion of the work at Madison Park, Parks, Recreation and Community <br />Services Agency requested that the construction fence be maintained in place until <br />the ribbon cutting ceremony on January 21, 2014. (PCO #16) <br />AGREED COST $ 750.00 <br />ACCOUNTING UNIT COST ANALYSIS: <br />CCO Item <br />Number <br />Accounting Units <br />Accounting <br />Unit Costs <br />Total Amount <br />1 <br />13518783- 66220- 13751601028 <br />$440.00 <br />$440.00 <br />2 <br />13518783-66220-13751201028 <br />$2,472.00 <br />$2,472.00 <br />3 <br />13518783 - 66220 - 13751601028 <br />$1,770.00 <br />$1,770.00 <br />4 <br />13518783- 66220 - 13751601028 <br />$750.001 <br />$750.00 <br />Total 1 <br />$5,432.00 <br />CONTRACT COST SUMMARY: <br />Original Contract Total $554,306 <br />% of Contract <br />Previous Change Orders $32,715 <br />Change OrderjQ $5,432 Increase 0.98% <br />Total CCO to date $38,147 Increase 6.88% <br />Adjusted Contract Total $592,453 <br />