CITY OF SANTA ANA
<br />CAPITAL IMPROVEMENT PROGRAM (CIP)
<br />FY 13 -14 CIP PROJECTS BY CATEGORY
<br />PROJECTS
<br />NEIGHBORHOOD IMPROVEMENTS
<br />TOTAL
<br />Curb, Gutter, Sidewalk
<br />Omnibus Concrete 350,000
<br />Pedestrian Safety Project Development 50,000
<br />Subtotal Curb, Gutter, Sidewalk 400,000
<br />Neighborhood Street Improvements
<br />Local Street Preventative Maintenance 1,400,000
<br />Residential Street Repair Program 788,692
<br />Alley Improvement Program
<br />Alleys
<br />Subtotal Neighborhood Street Improvements 2,188,692
<br />95,850
<br />Subtotal Alley Improvements 95,850
<br />TOTAL NEIGHBORHOOD IMPROVEMENTS 2,684,542
<br />H. ARTERIAL IMPROVEMENTS
<br />Arterial Widenin
<br />Bristol Street Widening: Phase IIIA - Civic Center to Washington 594,000
<br />Bristol Street Widening: Phase 11113 - Washington to Seventeenth 11,482,701
<br />Bristol Street Widening: Phase IV - Warner to St. Andrew 737,946
<br />Grand Avenue Widening: First to Fourth 2,790,262
<br />Project Development 100,000
<br />Right -of -Way Management 100,000
<br />Warner Avenue Widening: Main to Grand 5,411,121
<br />Warner Avenue Widening: Main to Oak 5,831,700
<br />Subtotal Arterial Widening 27,047,730
<br />Street Reconstruction/Resurfacin
<br />Arterial Street Preventative Maintenance 1,400,000
<br />Chestnut Avenue Rehabilitation: Broadway to Main 287,000
<br />Civic Center Drive Rehabilitation: Main to Spurgeon 440,000
<br />McFadden Avenue Rehabilitation: Newhope to Harbor 646,000
<br />Memory Lane Rehabilitation: Main to North City Limit 829,000
<br />Pavement Management 100,000
<br />Subtotal Street Reconstruction/Resurfacing 3,702,000
<br />TOTAL ARTERIAL IMPROVEMENTS 30,749,730
<br />III. TRAFFIC IMPROVEMENTS
<br />Traffic Improvements
<br />Fixed Guideway 194,000
<br />Grand/Glassel/Kraemer Corridor Traffic Signal Synchronization 850,000
<br />Main Street Corridor Traffic Signal Synchronization 1,212,000
<br />Newhope Street at Camille Street - New Traffic Signal 330,000
<br />Santa Ana Safe Street Crossers (SRTS) 338,940
<br />Segerstrom Avenue at Bear Street - Traffic Signal Modification 210,600
<br />Traffic Control Devices Inventory 100,000
<br />Traffic Management Plans 30,000
<br />Traffic Safety Project Development 124,115
<br />Traffic Signal Equipment Replacement 100,000
<br />Subtotal Traffic Improvements 3,489,655
<br />TOTAL TRAFFIC IMPROVEMENTS 3,489,655
<br />20
<br />
|