Schedule <br />kvA� <br />Our Critical Path Method (CPM) project schedule shows each major task identified in our scope <br />of work, as well as quality control milestones and meetings. <br />See key milestone dates from the project schedule below: <br />• Project Kickoff — January, 2014 <br />• Survey Completion —April, 2014 <br />• Delivery of draft PMP — May, 2014 <br />• City comments returned to Consultant — May, 2014 <br />• Delivery of City CIP Final Report— May, 2014 <br />o Santa Ana CIP data /Final Report, reporting and revenue projections will be <br />submitted by May, 2014 <br />• Implementation of MicroPAVER PMP software /database — Any time after acceptance of <br />Final PMP <br />• All pavement and GIS data pertinent to the project deliverables will be submitted with <br />the Final PMP report, May, 2014 <br />4 -1 <br />25G -34 <br />