Laserfiche WebLink
Project 10.7557 <br />Request for Approval of Change Order No. 1 <br />April 15, 2014 <br />Page 3 of 3 <br />Change Order #1 $16,048 Increase 6.05% <br />Total Change Orders to Date <br />Adjusted Contract Total <br />SCHEDULEIMPACT <br />$16,048 Increase 6.05% <br />$281,307 <br />Increase contract time by 50 calendar days for added work and to cover the <br />landscape maintenance period for the added landscaping work. <br />William Galvez, Interi xecutive Director <br />Public Works Agency <br />GerarV o Mouet, Executive Director <br />Parks, Recreation, and Community <br />Services Agency <br />APPROVED AS TO FUNDS AND <br />ACCOUNTS: <br />Francisco Gutierrez, Executive Director <br />Finance & Management Services Agency <br />K: Construction /Projects /10- 7557 /8.Change Orders /B /CO #01/10 -7557 MEM RFA CC0#01 <br />