ENVIRONMENTAL IMPACT REPORTADDENDUM <br />Bristol Street Widening Proiect Warner Ave to Saint Andrew Place (Phase IV) <br />1.4.3 Changes as Compared to the Approved Project <br />It should be noted that project phasing has been revised from the original three phases identified in thel990 <br />Final EIS /EIR. Construction phasing of the entire project segment has been further subdivided as follows: <br />• St. Andrew Place to McFadden Avenue (Constructed in 2002) <br />• Elm Street to Memory Lane (Constructed in 2003) <br />• Pine Street to 3`d Street (Constructed in 2009) <br />• Phase I: McFadden Avenue to Pine Street (Constructed in 2011)' <br />• Phase IL• 3`d Street to Civic Center Drive (Construction to be completed in 2014) <br />• Phase IIIA: Civic Center Drive to Washington Avenue <br />• Phase IIIB: Washington Avenue to 17 "' Street <br />• Phase IV: Warner Avenue to St. Andrew Place <br />• Phase V: 17`1i Street to Elm Street <br />The proposed street widening design configuration for the current Phase IV segment differs from the <br />original configuration of the 1990 Final EIS /EIR, as follows: <br />• The proposed Project increases the total right -of -way width from 120 feet to 128 feet. The proposed <br />Project right -of -way cross - section would maintain a curb -to -curb width of 100 feet, would <br />accommodate a 7 -foot wide bike lane on each side of the roadway, and would not affect the number <br />or width of vehicular travel lanes as compared to the right -of -way cross - section addressed in the <br />1990 FEIS /EIR. However, the proposed Project right -of -way cross section, as compared to the right - <br />of -way cross section addressed in the 1990 FEIS /EIR, would reduce the width of the sidewalks from <br />10 to 8 feet and also accommodate a 6 -foot wide parkway on each side of Bristol Street to separate <br />pedestrian and vehicular travel; a parkway was not included as part of the roadway cross section <br />addressed in the 1990 FEIS /EIR. Acquisition of property resulting from the proposed Project right - <br />of -way is accounted for in this analysis. <br />• The centerline alignment has been shifted to the west starting at St. Gertrude instead of starting at <br />Glenwood Place with the addition of 4 -feet to the original 20 -foot shift. The street centerline then <br />shifted back 4 -feet to the east at St. Andrew in order to match the existing centerline north of St. <br />Andrew. By shifting the centerline at St. Gertrude, the Phase IV Project saved eight parcels from full <br />take by reducing these parcels to partial acquisitions. <br />• A bus turnout would be located at the Warner Avenue. <br />• Change right -of -way requirement from full take to partial take of the following single - family <br />residential parcels: 015 - 215 -10 (150 square feet), 015- 215 -11 (50 square feet), 015- 214 -10 (50 <br />square feet), 015- 234 -10 (50 square feet), 015- 233 -11 (50 square feet), 015- 233 -10 (50 square feet), <br />015- 232 -11 (50 square feet), and (015- 232 -10 (50 square feet). <br />I Phase numbers were assigned to the Bristol Street Widening Project subsequent to cancelation of the CenterLine <br />Light Rail Transit Project and associated reallocation of funding from that canceled project to the Bristol Street <br />ANA 305494 (PER 02) CSA (AUGUST 2014) 133867 YU 15 <br />