Schedule <br />Our Critical Path Method (CPM) project schedule shows each major task identified in our scope <br />of work, as well as quality control milestones and meetings. <br />See key milestone dates from the project schedule below: <br />• Project Kickoff — December 4, 2015 <br />• Survey Completion — March 4, 2016 <br />• Delivery of draft PMP — March 21, 2016 <br />• City comments returned to Consultant— April, 2016 <br />• Delivery of City CIP Final Report — April, 2016 <br />o Santa Ana CIP data /Final Report & OCTA Compliant report, revenue projections <br />will be submitted by April, 2016 <br />• Implementation of MicroPAVER v.7.0 PMP software /database — Any time after <br />acceptance of Final PMP <br />• All pavement and GIS data pertinent to the project deliverables will be submitted with <br />the Final PMP report, May, 2016 <br />5 -1 <br />25D -22 <br />