Proposed Development Schedule: <br />EVENT <br />DATE <br />Community Redevelopment <br />and Housing Commission <br />3/28/2016 <br />City Council <br />4/19/16 <br />Site Acquired <br />8/30/2015 <br />Begin Entitlements <br />8/3/2015 <br />City Staff Approval of <br />Entitlements <br />3/28/2016 <br />9% Tax Credit Application <br />3/1/2017 <br />9% Tax Credit Award <br />6/30/2017 <br />Begin Construction <br />Documents <br />7/1/2017 <br />Construction Financing <br />Secured <br />8/1/2017 <br />Tax Credit Investor <br />Secured <br />8/1/2017 <br />Begin Construction /Building <br />Permit Issued <br />11/1/2017 <br />Construction Complete <br />5/1/2019 <br />Leasing Process Begins <br />5/1/2019 <br />Project Fully Leased <br />8/1/2019 <br />. M <br />