Request for Time Extension of Measure M2 CTFP Funds <br />for Bristol & Warner Street Improvement Projects <br />March 7, 2017 <br />Page 2 <br />utilities, and widening the roadway from the existing four lanes to six lanes. In addition to the on- <br />street, dedicated bike lanes (Class II) and ADA- compliant sidewalks, the proposal also includes a <br />raised landscape median and a landscaped parkway buffer, both with drought tolerant plants. <br />In accordance with Comprehensive Transportation Funding Program (CTFP) guidelines, the <br />construction and right -of -way phases for these projects must be awarded by June 30, 2017. Staff <br />recommends that the City Council authorize the Public Works Agency to request a one -time, two - <br />year extension of Measure M2 CTFP funding for the following projects to avoid the grant awards <br />from lapsing: <br />Project Name <br />Resolution for <br />Funding <br />Board of Directors <br />Extension <br />Application <br />Amount <br />Approval/ <br />Request <br />(Exhibit 4) <br />Programmed Fiscal <br />Year <br />Bristol Street <br />November 18, 2014 <br />$2,485,597 <br />April 27, 2015 <br />Construction <br />Improvements <br />Res. No. 2014 -078 <br />FY 2016 -17 <br />FY 2019 -20 <br />(Phase 3A) <br />Bristol Street <br />November 18, 2014 <br />$5,629,845 <br />April 27, 2015 <br />Construction <br />Improvements <br />Res. No. 2014 -078 <br />FY 2016 -17 <br />FY 2019 -20 <br />Phase 4) <br />Warner Avenue <br />November 17, 2015 <br />$5,200,000 <br />April 11, 2016 <br />Right -of -Way <br />Improvements <br />Res. No. 2015 -063 <br />FY 2016 -17 <br />FY 19 -20 <br />The Bristol Street project involves acquisition of 71 properties along the two segments. The <br />Public Works Agency has made a diligent effort to negotiate and complete these acquisitions to <br />meet the funding timeline. To date, the City has completed the acquisition of 52 of 71 parcels <br />and relocation of 53 of 96 residents. Staff has continued to negotiate in good faith, but an <br />impasse has been reached on numerous properties. The ongoing negotiations now put the <br />schedule for award of a construction contract beyond the June 30, 2017, deadline. <br />The Warner Avenue project received a portion of the right -of -way funding from Measure M2 <br />CTFP for Fiscal Year 2016 -17. On December 6, 2016, the City Council adopted Resolution <br />2016 -090 (Exhibit 5) authorizing the Executive Director of Public Works to submit an application <br />for the remainder of the required funding, in the amount of $12,618,000 for program Fiscal Year <br />2017 -18. The City will begin the right -of -way acquisition process once the necessary funding is <br />secured in full. <br />STRATEGIC PLAN ALIGNMENT <br />Approval of this item supports the City's efforts to meet Goal #6 — Community Facilities & <br />Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City <br />assets), Strategy G (develop and implement the City's Capital Improvement Program in <br />coordination with the Community Investment and Deferred Maintenance Plans). <br />21A-2 <br />