General Plan Timeline
2014-Santa Ana Strategic Plan Adopted
2015-General Plan Kickoff
2016-Community Outreach Phase I
2017-General Plan Advisory Group
SCAG Grant Awarded
2018-Draft Policy Framework
Second Community Outreach Effort
2019-Draft General Plan and EIR
2020-General Plan Adopted
City of
Santa Ana
6.5.18
2018: Current Work Effort
Preparation of draft policy framework
•
HEALTH
Second Community Outreach Effort
•
EQUITY
Policy document to include:
•
Vision Statement
SUSTAINABILITY
Goals/Policies
Land Use Map Alternatives
CULTURE
The principles that guide our decision-making
EDUCATION
City of
Santa Ana
6.5.18
Critical Milestones
•Secure funding for General Plan
Environmental (EIR)/Technical Studies
(Spring 2018)
•Vision, Core Values and Land Use Study Areas
Council Study Session (Summer 2018)
•Kick off Community Outreach Program
Phase 2 (Summer 2018)
City of
Santa Ana
6.5.18
Critical Milestones
•RFP for EIR/Technical studies consultant –
(Fall 2018)
•Draft General Plan Policy Framework
completed (December 2018)
•EIR Complete (February 2020)
•Adoption of General Plan Update
(March 2020)
City of
Santa Ana
6.5.18
Fiscal Impact
GENERAL PLAN PROJECTED EXPENDITURES
FUNDFY2017-18FY2018-19FY2019-20TOTAL
AMES$ 850,000 $ 1,000,000 $ 650,000 $ 2,500,000
AQMD$ -$ 75,000 $ 75,000 $ 150,000
SCAG$ -$ 325,000 $ -$ 325,000
G.F.$ -$ 30,570 $ -$ 30,570
$ 850,000 $ 1,430,570 $ 725,000 $ 3,005,570
City of
Santa Ana
6.5.18
Next Steps
THANK YOU!