HomeMy WebLinkAbout25D - AGMT CUSTODIAL SERVICESREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
AUGUST 21, 2018
TITLE:
APPROVE AN AGREEMENT AMENDMENT
WITH VALLEY MAINTENANCE CORPORATION
FOR EXPANDED CUSTODIAL SERVICES AT
PARK RESTROOMS AND INCLUDE THE
ROOSEVELTIWALKER COMMUNITY CENTER
{STRATEGIC PLAN NO. 6, 113}
ta�
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 151 Reading
❑ Ordinance on 2nd Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
Authorize the City Manager and Clerk of the Council to execute an amendment to the agreement
with Valley Maintenance Corporation to provide expanded custodial services at park restrooms
and include the Roosevelt/Walker Community Center into the base agreement by increasing the
annual agreement amount by $186,200 (prorated at $139,650 for the remaining portion of current
term), which includes a 10% contingency, from September 1, 2018 through May 31, 2019, with
two, one-year renewal options, for a total cost (original and amendments) of $1,653,536 over the
term of the contract, including renewals, subject to non -substantive changes approved by the City
Manager and City Attorney.
DISCUSSION
On May 16, 2017, the City of Santa Ana awarded an agreement to Valley Maintenance
Corporation for custodial services at park restrooms and park facilities. Due to the heavy use of
city parks, the City wishes to increase services at park restrooms from once per day to twice per
day service. The annual cost for custodial services at park restrooms is $141,072, annually, for
once per day service. Increasing the service to twice per day will increase the annual price by
$141,072. In order to address the urgent need, City staff has already directed the custodial
company, through contingency available in the agreement, to begin twice per day service at
various parks in the City with a focus on those with sports fields, which started on August 1, 2018.
All the park restrooms will receive increased service starting September 1, 2018. Additionally, in
June 2018, the City opened a new community center, Roosevelt/Walker Community Center.
Valley Maintenance Corporation has been maintaining this facility as authorized extra work with
the use of contingency funds included the original agreement. The cost of providing custodial
services at the Roosevelt/Walker Community Center will be $28,200, annually. Included the
agreement will also be an additional $16,928, annually, as a contingency for unforeseen
circumstances.
25D-1
Agreement Amendment with Valley Maintenance Corporation
August 21, 2018
Page 2
STRATEGIC PLAN ALIGNMENT
Approval of this item allows the City to meet Goal #6 - Community Facilities & Infrastructure,
Objective #1 (Establish and maintain a Community Investment Plan for all City assets), Strategy
B (Equitably maintain existing streets and associated assets in a state of good repair so they are
clean, safe and aesthetically pleasing for all users).
FISCAL IMPACT
Funds are available in the following accounts for the specified fiscal year of the initial term:
Accounting Unit
Maintenance (no. 0111
FY18/19
139,650
Funds are available and will be budgeted in the following accounts for the specified years of the
two, one-year renewal terms:
Unit
PRCSA-Park Maintenance (no. 01113250-62320)
`Bark§, Recreation and Community Services
Agency
Exhibit: 1. Agreement Amendment
FY 18/19 FY19/20 FY20121
$15,517 $186,200 $170,683
APPROVED AS TO FUNDS AND ACCOUNT:
Sergio Vidal FQ (25D)
Assistant Director
Finance and Management Services Agency
25D-2
SECOND AMENDMENT TO AGREEMENT WITH VALLEY MAINTENANCE
CORPORATION FOR JANITORIAL SERVICES AT PARK RESTROOMS AND PARK
BUILDINGS
THIS SECOND AMENDMENT effective as of the 21 st day of August, 2018, by and
between-VdlleyMaintenance Corporation (hereinafter "Valley") and the City of Santa Ana
("City"), a charter city and municipal corporation organized and existing under the Constitution
and laws of the State of California.
RECITALS
1. On June 1, 2017, City and Valley entered into Agreement No. A-2017-125
("Agreement') for janitorial services for park restrooms and park buildings. The
Agreement was from June 1, 2017 to May 31, 2019 with two (2) one-year options for
renewal.
2. On May 15, 2018, City and Valley entered into the First Amendment No. A-2018-124 to
add additional services to the Agreement for Pacific Electric Park and the Zoo Animal
Hospital effective June 1, 2018 at an additional cost of $26,823 per year and an annual
agreement not to exceed amount for each year of $290,508.
3. The parties now wish to amend the Agreement to add additional services at the
Roosevelt -Walker Community Center and to increase the daily cleanings at designated
City park restrooms to twice a day and increase the compensation to pay for those
services.
NOW THEREFORE, in consideration of the mutual and respective promises, and subject
to the terms and conditions hereinafter set forth, the parties agree as follows:
1. Section 1, SCOPE OF SERVICES, of the Agreement will be amended to add Exhibit
C attached hereto detailing the new services to be provided at the Roosevelt -Walker
Community Center and increasing daily cleaning of restrooms at all listed City Parks
under the Agreement starting September 1, 2018.
2. Section 2, COMPENSATION, of the Agreement will be amended to add the
following:
a. An additional $126,954 plus a 10% contingency of $12,696 for September -1,
2018 to May 31, 2019 for a total annual not to exceed amount of $430,158;
b. (Optional fust year renewal) An additional $169,272 plus a 10% contingency
of $16,928 for June 1, 2019 to May 31, 2020 for a total annual not to exceed
amount of $476,708;
c. (Optional second year renewal) An additional $169,272 plus a 10%
contingency of $16,928 for June 1, 2020 to May 31, 2021 for a total annual
not to exceed amount of $476,708; and
d. Total agreement not to exceed amount of$1,653,536 including all optional
renewals.
EfiBT 1
Except as modified by this Second Amendment, the terms and conditions of the
Agreement remain unchanged and in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this Second Amendment to the
Agreement the date and year first written above.
ATTEST:
Maria D. Huizar
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By: &w'ta- /A,.�19/�t )1 l
Laura A. Rossini
Senior Assistant City Attorney
RECOMMENDED FOR APPROVAL:
Ralph J. Nufiez
Interim Executive Director,
Parks, Recreation and Community Services Agency
CITY OF SANTA ANA
Raul Godinez, II.
City Manager
VALLEY MAINTENANCE CORP.
By:
Title:
EXHIBIT 1
25D-4
am"
VALLEY MAINTENANCE CORP
Exhibit C
VALLEY MAINTENANCE CORP.
10002 Pioneer Blvd. Suite 101 Ca. 90670
TEL: (562) 948-3020 Fax: (562) 948-3081
SERVICE AGREEMENT
Janitorial Services
1. WORK SCHEDULE Listed City Park Restrooms 2ntl cleanings services 7 days a week Monday through
Sunday
2. TIME OF SERVICE Between 12:00 A.M. to 3:00 P.M. or Time the management requests
LOCATION
3. JOB LOCATIONS Listed City of Santa Ana Park Restrooms
4. WORK SPECIFICATIONS Per existing service contract work specification
5. SUPPLIES Cleaning supplies will be supplied by: VMC
Restroom supplies & trash liners will be supplied by: VMC
6. SERVICE CHARGE
THE SERVICE CHARGE(S) FOR ABOVE DESCRIBED SERVICES
$ 141,072.00 Per Annual ( $11,756 Per Month)
7. GUARANTEE
You are respectfully requested to examine the results of our work and if you find our
workmanship and finished results to be less satisfactory, please call
VMC immediately so we will correct the matters within 1 hour.
9. ACCEPTANCE
Please indicate your approval by signing the acceptance line below.
DATE OF SUBMISSION
July 9, 2018
OF SERVICE AGREEMENT
Valley Maintenance Corp.
City of Santa Ana
Exhibit C CITY OF SANTA ANA PARK RESTROOMS
District 1
Address
Contract Price
2nd Clean Price
Campesino
3311 W. 5th St.
$
352.00
$
352.00
Edna
2140 W. Edna Dr.
$
352.00
$
352.00
EI Salvador
1825 W. Civic Center Dr.
$
352.00
$
352.00
Riverview
1823 W. 19th St.
$
352.00
$
352.00
Rosita
706 N. Newhope St.
$
352.00
$
352.00
District 2
Angels
914 W. 3rd St.
$
352.00
$
352.00
Cabrillo
1820 E. Fruit St.
$
352.00
$
352.00
Fisher Restroom
2501 N. Flower St.
$
352.00
$
352.00
Fisher Cabin
2501 N. Flower St.
$
352.00
$
352.00
Logan/Chepa's
1009 N. Custer St.
$
352.00
$
352.00
Portcla
1750 E. Santa Clara Ave.
$
352.00
$
352.00
Santiago RR "A"
510 E. Memory Lane
$
230.00
$
230.00
Santiago RR "B"
510 E. Memory Lane
$
230.00
$
230.00
Santiago Cabin
510 E. Memory Lane
$
200.00
$
200.00
District 3
Delhi
2314 S. Halladay St.
$
432.00
$
432.00
Madison
1434 S. Standard Ave.
$
432.00
$
432.00
Memorial
2102 S. Flower St.
$
432.00
$
432.00
Sandpointe
3700 S. Birch St.
$
432.00
$
432.00
Pacific Electric
400 E. MaHaden
$
432.00
$
432.00
District 4
Adams
2101 W. Warner Ave.
$
432.00
$
432.00
Centennial "A"
3000 W. Edinger Ave.
$
400.00
$
400.00
Centennial "B"
3000 W. Edinger Ave.
$
400.00
$
400.00
Centennial "C..3000
W. Edinger Ave.
$
400.00
$
400.00
Centennial HGHS
3000 W. Edinger Ave.
$
432.00
$
432.00
DYSC "A"
3000 W. Edinger Ave.
$
540.00
$
540.00
DYSC "B"
3000 W. Edinger Ave.
$
300.00
$
300.00
Heritage
4812 W. Camille St.
$
432.00
$
432.00
Jerome
2101 W. Mcfadden St.
$
432.00
$
432.00
Santa Anita
300 S. Figueroa Sl.
$
432.00
$
432.00
Thornton
1801 W. Segerstrom
$
432.00
$
432.00
Windsor
2915 W. La Verne Ave.$
432.00
$
432.00
Total
0$,�.;Al-756?003 1
$
11,756.00
EXHIBIT 1
25D-6
Exhibit C
VALLEY MAINTENANCE CORP
VALLEY MAINTENANCE CORP.
10002 Pioneer Blvd. Suite 101 Ca. 90670
TEL: (562) 948-3020 Fax: (562) 948-3081
SERVICE AGREEMENT
Janitorial Services
1. WORK SCHEDULE Janitorial services.da a on.a throu h'Sat r a
2. TIME OF SERVICE After 10 PM between 10:00 P.M. to 5:00 A.M.
LOCATION
816 East Chestnut Ave. Santa Ana,
3. JOB LOCATIONS Roosevelt -Walker Community Center
4. WORK SPECIFICATIONS Per existing service contract work specification
5. SUPPLIES Cleaning supplies will be supplied by: VMC
Restroom supplies & trash liners will be supplied by: VMC
6. SERVICE CHARGE THE SERVICE CHARGE(S) FOR ABOVE DESCRIBED SERVICES
2139Q1Per Ifllintti
7. GUARANTEE You are respectfully requested to examine the results of our work and If you find our
Workmanship and finished results to be less satisfactory, please call
VMC immediately so the we will correct the maters within 1 hour.
9. ACCEPTANCE Please indicate your approval by signing the acceptance line below.
EFFECTIVE STARTING DATE
APPROVED DATE
Valley Maintenance Corp.
City of Santa Ana
EZCI BIJ
25D-8