HomeMy WebLinkAbout20A - AA PARK LIGHTINGREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
JULY 2, 2019
TITLE:
APPROVE AN APPROPRIATION ADJUSTMENT
AND AWARD A CONSTRUCTION CONTRACT
TO FODDRILL CONSTRUCTION CORPORATION
FOR NEW LIGHTING AT SIX PARKS
ESTIMATED DELIVERY COST: $724,000
(PROJECT NOS. 18-2683, 18-2684, 18-2685,
18-2686, 18-2687, 18-2689)
(STRATEGIC PLAN NO. 6, 1131; 1G)
���%fiM; AFA r,or CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 1B1 Reading
❑ Ordinance on 2nd Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
Approve an appropriation adjustment recognizing $195,476 from Residential Development District 1
prior year fund balance and appropriating the same amount into the Residential Development District
1 Acquisition & Development expenditure account. These funds will be added to the existing budget
for this project.
2. Approve an appropriation adjustment recognizing $171,604 from Residential Development District 2
prior year fund balance and appropriating $90,604 into the Residential Development District 2
Acquisition & Development expenditure account and $81,000 into the Residential Development
District 2 In -Lieu expenditure account. These funds will be added to the existing budget for this
project.
3. Award a contract to Foddrill Construction Corporation, the lowest responsible bidder, in accordance
with the base bid in the amount of $579,378, for the term beginning upon execution of the contract
and ending upon project completion, for construction of the New Lighting at Six Parks Project, and
authorize the City Manager and the Clerk of the Council to execute the contract, subject to non -
substantive changes approved by the City Manager and the City Attorney.
4. Approve the Project Cost Analysis for a total estimated construction delivery cost of $724,000, which
includes $579,378 for the construction contract, $86,906 for contract administration, inspection and
testing, and a $57,716 project contingency, to be funded with District 1 and District 2 Acquisition &
Development funding and District 2 in -lieu funds.
The New Lighting at Six Parks Project will enhance lighting at the following park locations: Angels Park,
Cabrillo Park, Cesar Chavez Park, Portola Park, Riverview Park, and Rosita Park (Exhibit 1). The existing
20A-1
Award a Construction Contract to Foddrill Construction Corporation
New Lighting at Six Parks
July 2, 2019
Page 2
wooden lighting poles at these parks have deteriorated with age. Replacement is required for safety,
modernization, and to update existing lighting to adequate levels at these parks.
The Scope of Work includes new light pole assemblies, foundations, electrical conduit, wiring, removal of
deteriorated wooden light poles, and replacement with new concrete poles with energy efficient LED
fixtures. Once completed, these improvements will enhance lighting levels and safety for these parks.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was advertised in the
Orange County Register newspaper on April 27 and May 4, 2019, and bids were received electronically
via the City's web -based electronic bidding system, PlanetBids, on May 22, 2019. Through the PlanetBids
online portal, vendors may register to receive notifications on all current and future City projects, as well
as download contract documents, receive project updates, and submit bids electronically.
A total of 577 vendors, including 31 located in the City of Santa Ana, were notified of the project via
PlanetBids. 56 vendors requested bidding documents and 6 bids were received; none from Santa Ana
contractors.
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
Foddrill Construction Corporation
Chino
$579,378
2
California Professional Engineering, Inc.
La Puente
$670,265
3
VT Electric Inc.
Ontario
$757,907
4
International Line Builders, Inc.
Riverside
$764,840
5
M. Brey Electric, Inc.
Beaumont
$834,957
6
YAKAR
Covina
$875,750
All 6 bids received were deemed responsive. Foddrill Construction Corporation submitted the lowest
responsive bid in the amount of $579,378 (Exhibit 2). Based on the bid analysis and a contractor's
reference check, staff recommends awarding the construction contract to Foddrill Construction
Corporation in the amount of $579,378 (Exhibit 3).
20A-2
Award a Construction Contract to Foddrill Construction Corporation
New Lighting at Six Parks
July 2, 2019
Page 3
Proiect Delivery
To deliver a complete project, in addition to the construction contract awarded to the lowest responsible
bidder, the estimated total construction delivery cost of the project includes construction administration,
inspection and testing, along with an allowance for contingencies to account for unexpected or unforeseen
conditions. Construction administration and inspection includes construction management; implementation
of the City's Community Workforce Agreement requirements; inspection of the Contractor's work to
ensure contract compliance, workmanship, and quality; and material testing. As summarized in the table
below, the estimated total construction delivery cost of the project is $724,000.
Construction Contract
$579,378
Construction Administration, Inspection and Testing
$86,906
Contingencies
$57,716
ESTIMATED CONSTRUCTION DELIVERY COST
$724.000
Project funds will cover all staffing costs for delivery of this capital project. No additional or separate
funding will be used.
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's efforts to meet Goal #6 Community Facilities & Infrastructure,
Objective #1 (establish and maintain a Community Investment Plan for all City assets), Strategy C (invest
resources and technology to extend the service life of existing infrastructure to protect the City's
investment and support a high quality of life standard) and Strategy G (develop and implement the City's
Capital Improvement Program in coordination with the Community Investment Plan — e.g., neighborhood
streets, traffic improvements, etc.)
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions are exempt from
further review. Categorical Exemption Environmental Review No. ER-2019-43 was filed for the project.
FISCAL IMPACT
Approval of the requested appropriation adjustment will increase the expenditure budget in the following
funds for a total of $367,080:
• Residential Development District 1 fund $195,476 (account no. 31113260-66220); and
• Residential Development District 2 fund $171,604 ($90,604 in account no. 31213260-66220 and
$81,000 in account no. 31213261-66220).
As indicated in the Cost Analysis (Exhibit 4), the estimated total construction delivery cost of the project is
$724,000, which includes the construction contract, contract administration, inspection, testing, and
project contingency. The following table summarizes the expenditure budget by account number and
project number to deliver construction of this project:
20A-3
Award,a Construction Contract to Foddrill Construction Corporation
New Lighting at Six Parks
July 2, 2019
Page 4
Accounting Unit—
Accounting Unit, Account No.
Fiscal Year
Account No.
Fund Description
Description
Amount
Project No.
FY 2019-20
31113260-66220
Acquisition &
A&D District 1, Improvements
$140,934
July -June
18-2683
Development Fund
Other Than Building
FY 2019-20
31113260-66220
Acquisition &
A&D District 1, Improvements
$149,199
July -June
18-2684
Development Fund
Other Than Building
FY 2019-20
31113260-66220
Acquisition &
A&D District 1, Improvements
$101,773
July -June
18-2685
Development Fund
Other Than Building
FY 2019-20
31213260-66220
Acquisition &
A&D District 2, Improvements
$56,051
July -June
18-2686
Development Fund
Other Than Building
FY 2019-20
31213260-66220
Acquisition &
A&D District 2, Improvements
$98 421
Jul -June
18-2687
Develo ment Fund
Other Than Building
FY 2019-20
31213260-66220
Acquisition &
A&D District 2, Improvements
$96,622
July -June
18-2689
Development Fund
. Other Than Building
FY 2019-20
31213261-66220
District 2 in Lieu
A&D District 2, Improvements
$81,000
July -June
18-2689
Other Than Building
Total
1 $724,000
All Funds are scheduled for expenditure in Fiscal Year 2019-20.
12
Fuad Sweiss, PE, PLS
ExecutiAt Director
Public Mrks Agency
Parks, Recreation, and Community Services
FSS/EWG/TC/MO
Exhibits: 1. Location Map
2. Bid proposal
3. Construction Contract
4. Cost Analysis
APPROVED AS TO FUNDS AND ACCOUNTS:
Kathryn Downs, CPA
Executive Director
Finance & Management Services Agency
20A-4
JECT LOCATION
ROSITA PARK
PROJECT LOCATION
CHAVEZ PARK
PROJECT LOCATION 1
CABRLLO PARK
SANTA ANAANA
p■ W A ■ PROJECT TING 3 T SIX PARKS
NEW LIGHTING AT SIX PARKS
n.. c ic.
PROJECT LOCATION
RIVERVEW PARK
PROJECT LOCATM
PORTOLA PARK
(SCALE . NTS)
PAGE 1 OF 1
2OA-5
20A-6
City of Santa Ana Page t
New Lighting at 6 Parks (1 B-2683 thru 18-2689), bidding on May 22, 2019 2:00 PM (Pacific) Printed t1W=019
Bid Results EXHIBIT 2
Bidder Details
Vendor Name
Foddrill Construction Corporation
Address
P.O. Box 826
Chino, CA 91708.0826
United States
Respondee
Oscar Sevilla
Respondee Title
Estimator/Project Manager
Phone
909591-4095 Ext
Email
csevllla@foddrllfbonsbuctlon.com
Vendor Type
License 9
CA DIR
Bid Detail
Bid Format
Electronic
Submitted
May 22, 2019 1:40:34 PM (Pacific)
Delivery Method
Bid Responsive
Bid Status
Submitted
Confirmation #
179030
Ranking
0
Respondee Comment
Buyer Comment
Attachments
File Title
File Name
File Type
Fodddll General Forms
Foddrlll_General Forms_Slgned.pdf
General Forms
Fodddll Ownership Affidavit
Fcdddll_Ownershlp Affidavit.pdf
Ownership Affidavit (Notary
Public) - REQ Original
Hard Copy Submittal In
Addition
Fodddll Bid Bond
Fadddll_Bid Bcnd.pdf
Bid Bond Guaranty (Notary
Public) - REQ Original
Hard Copy Submittal in
Addition
Foddrill Non Collusion Affidavit
Foddrill_Non-Colluslon Affidavlt.pdf
Non -Collusion Affidavit
(Notary Public) - REO
Original Hard Copy
Submittal in Addition
Line Items
Type Item Code
UCM City Unit Price
Line Total Comment
Base Bid Items
1 NEW LIGHTING AT ANGELS PARK
LS 1 $38,368.37
$36,368.37
2 NEW LIGHTING AT CABRILLO PARK
LS 1 $70,263.84
$70.263.64
PlanstBids, Inc.
20A-7
City of Santa Ana
Page 2
New Lighting at 8 Parks (18-2683 thru 18-2689), bidding on May 22, 2019 2:00 PM (Paciflc)
Printed 05/22/2019
Bid Results
Type
Item Code UCM aty
Unit Price
Line Total Comment
3
NEW LIGHTING AT CHAVEZ PARK
LS 1
$72,945.62
$72.945.62
4
NEW LIGHTING AT PORTOLA PARK
LS 1
$133,803.92
$133,803.92
5
NEW LIGHTING AT RIVERVIEW PARK
LS 1
$110,886.75
$110,886.75
6
NEW LIGHTING AT ROSITA PARK
LS 1
$104,274.27
$104,274.27
7
ADDITIONAL LIGHT POLE"
FA 5
$3.316.02
$18,660.10
8
ADDITIONAL LIGHT POLE ASSEMBLY'
EA 5
$2,222.58
$11,112.80
9
ADDITIONAL WIRING*
LF 300
$16.10
$4,830.00
10
ADDITIONAL CONDUIT*
LF 300
$15.75
$4,725.00
11
AS -BUILT DRAWINGS
LS 1
$3,687.50
$3,587.50
12
LABOR AGREEMENT OVERSIGHT
Ls 1
$10.000.00
$10,666.00
Subtotal
$579,378.17
Asterisk Notes (Per Section 3.2 of Standard Specifications) -NOT part of Total
Bid Calculation
13
' = The quantity for this bid Item Is shown forbid comparison only. This bid Item shall
not be subject to the "25%" limit as stated In Section 3-2 of
the Standard Specifications. The actual amount for this Item will be dictated by the actual quantitiy used, and the Agency reserves the right to
Increase or decrease the quanflty of this Item accordingly.
EA 0
$16.10
0
14
t = This bid Rem is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
EA 0
$15.75
0
Subtotal
0
Total
$579,378.17
PlanotBids, Inc.
20A-8
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.:18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Foddrill Construction Corporation
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
NEW LIGHTING AT
1
LS
$
$
ANGELS PARK
36,368.37
36,368.37
2
NEW LIGHTING AT
1
LS
$
$
CABRILLO PARK
70,263.84
70,263.84
3
NEW LIGHTING AT
1
LS
$
$
CHAVEZ PARK
72,945.62
72,945.62
4
NEW LIGHTING AT
1
LS
$
$
PORTOLA PARK
133,803.92
1 133,803.92
5
NEW LIGHTING AT
1
LS
$
$
RIVERVIEW PARK
110,886.75
110,886.75
6
NEW LIGHTING AT
1
LS
$
$
ROSITA PARK
104,274.27
104,274.27
7
ADDITIONAL LIGHT POLE*
5*
EA
$
3,316.02
$
16,580.02
8
ADDITIONAL LIGHT POLE
5*
EA
$
$ 11,112.80
ASSEMBLY*
2,222.56
9
ADDITIONAL WIRING*
300*
LF
$
$
16.10
4,880.00
10
ADDITIONAL CONDUIT*
300*
LF
$
$
15.75
4,725.00
11
AS -BUILT DRAWINGS
1
LS
$
$
3587.50
3587.50
12 1
LABOR AGREEMENT OVERSIGHT
1
LS
$10,000
$10,000
TOTAL BASE BID
$ 579,378.17
201X-9
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
TOTAL BASE BID $ 579,378.17
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add-altemate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within ONE -HUNDRED TWENTY (120) working days after the commencement date
stated in the Notice to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $500 per calendar day.
Name of Firm
Signature of DI
Title Owner/CEO
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-2 ofP-16
20A-10
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
17 I► 9 : M_ ul_11�11
BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent
Construction Contract Agreement shall constitute the entire agreement between BIDDER and the
AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the Council
with her signature and official seal noting hereon the action of approval of the Council, signed by
the Public Works Agency Executive Director or his/her duly authorized agent, and signed by the
City Attorney, denoting his approval of the form of this document, and its execution, and when it
or an exact copy of it has been either delivered to BIDDER or deposited with the United States
Postal Service properly addressed to the BIDDER with the correct postage affixed thereto.
BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he/she
will furnish AGENCY all required bonds and certificate of liability insurance within ten (10)
business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof
accompanying this proposal shall become the property of the AGENCY and shall be considered
as payment of damages due to the delay and other causes suffered by AGENCY because of the
failure to furnish the necessary bonds and because it is distinctly agreed that the proof of damages
actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or BIDDER'S bond
substituted in lieu thereof shall be returned to the undersigned.
BIDDER understands that a bid is required for the entire work, the estimated quantities set forth
in the bid schedule are solely for the purpose of comparing bids, and that final compensation under
the contract will be based upon the actual quantities of work satisfactorily completed. The
BIDDER also certifies that the bid is a balanced bid.
In accordance with Section 7028.15 of the California Business and Professions Code, the
undersigned certifies under penalty of perjury that the foregoing is true and correct.
Name of Firm
Signature of BE
Title Owner/CEO
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-3 ofP-16
20A-11
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
CONTRACTOR'S LICENSING AND REGISTRATION STATEMENT
The undersigned contractor, or corporate officer, declares under penalty of perjury that he/she and
all his/her subcontractors are registered with the State of California Department of Industrial
Relations (DIR), and that the following is true and correct.
Contractor's Name: Foddrill Construction Corporation
Business Address: P.O. Box 826 Chino, CA 91708-0826
Business E-Mail Address: Leonora()foddrillconstruction or osevilla(a foddrillconstruction.com
Telephone: (909) 5914095
State Contractor's License No. and Class: 946999, Class A and C-10
License Expiration Date: 05/31/2020
State Dept. of Industrial Relations (DIR)
Registration No.: 1000025525
State Dept. of Industrial Relations (DIR)
Registrat
Signed:
Title: Owner/CEO
P-4 ofP-16
20A-12
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
PREVAILING WAGE COMPLIANCE AND MONITORING STATEMENT
Contractor is aware of the requirements of California Labor Code Section 1720, et seq., as well as
California Code of Regulations, Title 8, Section 16,000, et seq., ("Prevailing Wage Laws"), which
require the payment of prevailing wage rates and the performance of other requirements on "public
works" and "maintenance" projects. Since the services are being performed as part of an applicable
"public works" or "maintenance" project, as defined by the Prevailing Wage Laws, and since the
total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing
Wage Laws.
City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the
commencement of this Agreement. Contractor shall make copies of the prevailing rates of per
diem wages for each craft, classification or type of worker needed to execute the services available
to interested parties upon request, and shall post copies at the Contractor's principal place of
business and at the project site.
Cohtractor shall defend, indemnify and hold the City, its elected officials, officers, employees and
agents free and harmless from any claim or liability arising out of any failure or alleged failure to
comply with the Prevailing Wage Laws.
The undersigned certifies that the foregoing is true and correct.
Name of Firm
Signature of BI]
Title Owner/CEO
(if an individual, so state)
P-5 ofP-16
20A-13
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.:18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
LIST OF SUB -CONTRACTORS
Section 4100 et seq. of the Public Contract Code requires listing of all subcontractors with the bid for all
subcontract work exceeding the following amount:
o Streets, highways including bridge projects: %m% of the bid or $10,000, whichever is greater
o Buildings, parks, or other projects: '/z% of the bid
Section 1725.5 of the Public Contract Code requires all Subcontractors be registered with the State
Department of Industrial Relations (DIR).
BIDDER proposes to subcontract certain portions of the work to the firms listed below:
Name Bithell, Inc
License #/Exp.
C-13 225174 exp 06/10/2020
DIR Reg. #/Exp.
1000001155 exp 06/30/2021
Location
Covina. CA
Phone (626) 33 1 -2292
Type Of Work
_Apply Vitrocem Anti -Graffiti
Amount $
$8,800.00
Name V&E Tree Service
License #/Exp. C-27,C61/D49 654506exp 9/30/20
DIR Reg. #/Exp. 1000001936 exp 6/30/2019
License # 654506
Location Orange, CA
Phone (714)997-0903
Type Of Work Tree Pruning Service
Amount $ $9,800.00
Name
License #/Exp.
DIR Reg. #/Exp.
License #
Location
Phone
Type Of Work
Amount $
Signature of Bidder
Name
License #/Exp.
DIR Reg. #/Exp.
Location
Phone
Type Of Work
Amount $
Name
License #/Exp.
DIR Reg. #/Exp.
License #
Location
Phone
Type Of Work
Amount $
Name
License #/Exp:
DIR Reg. #/Exp.
License #
Location
Phone
Type Of Work
Amount $
P-8 ofP-16
20A-14
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.:18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER has performed similar work within the past three years.
1. Ameron/NOV, 1020 B Street
Name and Address of Owner.
Name and Telephone Number of person familiar with project.
$4,000,000.00 Streetlight maintenance and replacement 11/93 to present
Contract Amount Type of Work Date Completed
2. City of Santa Ana
Name and Address of owner.
Name and Telephone Nun
$720,499.33
Contract Amount
City of Palmdale
Name and Address of owner.
of person familiar with project.
Security Lighting at 8 Parks
Type of Work
Arista Hennessey, (661) 267-5458
Name and Telephone Number of person familiar with project.
$1,465,206.20
Contract Amount
LED Conversion
Type of Work
July 2017
Date Completed
06/2018-Present
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
Insurance & Surety, LLC, Agent Gabriel Hill, 4195 Chino Hills Parkway #403, Chino Hills, CA 91709
Lie. 0167797, (909) 703-9396 Cell
w i�
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.:18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
ADDITIONAL REFERENCES
The following are the names, addresses, and telephone numbers for THREE public agencies for
which the BIDDER or Subcontractor has performed similar work in the past five years.
1. City of Rancho Cucamonga
Name and Address of Owner.
Fred Lyn, (909) 774-4035
Name and
$613 235.02
Contract Amount
2• City of Yorba Linda
Name and Address of owner.
Armando Jahr
Name and Telephone Number
$20,258.75
Contract Amount
3. _ City of Corona
Name and Address of owner.
person tamiliar with project.
LED Conversion
Type of Work
Type of Work
Name and Telephone Number of person familiar with project.
$500.647.60
Contract Amount
LED Conversion
Type of Work
01/2019
Date Completed
11/2018
Date Completed
01/2018
Date Completed
The following are the names, addresses, and telephone numbers of all brokers and sureties from
whom BIDDER intends to procure insurance and bonds.
Insurance & Surety, LLC, Agent Gabriel Hill, 4195 Chino Hills Parkway #403, Chino Hills, CA 91709
Lic. 0167797, (909) 703-9396 Cell
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.:18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
NON-DISCRIMINATION CERTIFICATE
The undersigned contractor or corporate officer, during the performance of this contract, certifies
as follows:
The Contractor shall not discriminate against any employee or applicant for employment
because of race, color, religion, sex, or national origin. The Contractor shall take affirmative
action to ensure that applicants are employed, and that employees are treated during
employment without, regard to their race, color, religion, sex, or national origin. Such action
shall include, but not be limited to, the following: employment, upgrading, demotion, or
transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship. The Contractor
agrees to post in conspicuous places, available to employees and applicants for employment,
notices to be provided setting forth the provisions of this nondiscrimination clause.
2. The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf
of the Contractor, state that all qualified applicants will receive consideration for employment
without regard to race, color, religion, sex, or national origin.
The Contractor shall send to each labor union or representative of workers with which he/she
has a collective bargaining agreement or other contract or understanding, a notice to be
provided advising the said labor union or workers' representatives of the Contractor's
commitments under this section, and shall post copies of the notice in conspicuous places
available to employees and applicants for employment.
4. The Contractor shall comply with all provisions of Executive Order 11246 of September 24,
1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
The Contractor shall furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant
thereto, and will permit access to his/her books, records, and accounts by the administering
agency and the Secretary of Labor for purposes of investigation, to ascertain compliance with
such rules, regulations, and orders.
6. In the event of the Contractor's non-compliance with the nondiscrimination clauses of this
contract or with any of the said rules, regulations, or orders, the contract may be canceled,
terminated, or suspended in whole or in part and the Contractor may be declared ineligible for
further Government contracts or federally assisted construction contracts in accordance with
procedures authorized in Execution Order 11246 of September 24, 1965, and such other
sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of
September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as otherwise
provided by law.
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
The Contractor shall include the portion of the sentence immediately preceding paragraph (1)
and the provisions of paragraphs (1) through (7) in every subcontract or purchase order unless
exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section
204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding
upon each subcontract or purchase order as the administering agency may direct as means of
enforcing such provisions, including sanctions for noncompliance; provided, however, that in
the event the Contractor becomes involved in, or is threatened with, litigation with a
subcontractor or vendor as a result of such direction by the administering agency, the
Contractor may request that the United States enter into such litigation to protect the interests
of the United States.
8. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as
amended, no discrimination shall be made in the employment of persons upon public works
because of race, religious creed, color, national origin, ancestry, physical handicaps, mental
condition, marital status, or sex of such persons, except as provided in Section 1420, and any
contractor of public works violating this Section is subject to all the penalties imposed for a
violation of the hh jpter.
Signed:
Title: Owner/CEO
Firm: Foddrill Construction Corporation
Date: 05/20/2019
P-13 ofP-16
20A-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
STATEMENT REGARDING APPRENTICESHIP REQUIREMENTS
The undersigned BIDDER is familiar with the requirements of Section 1777.5 of the State Labor
Code regarding employment of apprentices, and understands that contractors on contracts
exceeding $30,000 or 20 working days shall:
1. Apply to the joint apprenticeship committee administering the apprenticeship standards of the
craft or trade in the area of the site of the public work for a certificate approving the contractor
under the apprenticeship standards for the employment and training of apprentices in the area
or industry affected.
2. Employ the number of apprentices or the ratio of apprentices to journeymen stipulated in the
apprenticeship standards.
3. Contribute to the fund or funds in each craft or trade in which he/she employs journeymen or
apprentices on the public work, in the same amount or upon the same basis and in the same
manner as the other contractors, except contractors not signatory to the trust agreement shall
pay a like uut to the Ca ' mia irenticeship Council.
Signed:
Title: Owner/CEO
Firm: Foddrill Construction Comoration
Date: 05/20/2019
P-14 ofP-16
20A-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
STATEMENT REGARDING "ANTI -KICKBACK" REQUIREMENTS
The undersigned is submitting this proposal for performing by contract the work required by these
bid documents, agrees to comply with the Copeland "Anti -Kickback" Act (18 USC 74) as
supplemented in the Department of Labor regulations (29 CFR, Part 3). This act provides that
each contractor or subcontractor shall be prohibited from inducing, by any means, any person
employed in the construction or repair of public work, to give up any part of the compensation to
which he/she is 3ise entitled. `'��j
Signed:
Title: Owner/CEO
Firm: Foddrill Construction Corporation
Date: 05/20/2019
P-15 ofP-16
20A-20
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.:18-2683 THRU 18-2689
NEW LIGHTING AT 6 PARKS
PUBLIC CONTRACT CODE SECTION 10162 OUESTIONNAIRE
In conformance with Public Contract Code Section 10162, the BIDDER shall complete,
under penalty of perjury, the following questionnaire:
Has the BIDDER, any officer of the BIDDER, or any employee of the BIDDER who has a
proprietary interest in the BIDDER ever been disqualified, removed, or otherwise prevented from
bidding on, or completing a federal, state, or local government project because of a violation of
law or a safety regulation?
Yes No X
If the answer is yes, explain the circumstances in the following space.
2��P21
WORKERS' COMPENSATION INSURANCE CERTIFICATION
As required by California Labor Code Section 1860 and 1861, the Contractor certifies as follows:
I am aware of the provisions of Section J700 of the Labor Code, which requires every employer to be
insured against liability for worker's compensation or to undertake self-insurance in accordance with the
provisions of the Code, and I will comply with such provisions before commencing the performance of
the work of this c t tract.
Signed:
Title: Owner/CEO
Firm: Foddrill Construction Corporation
Date: 05/20/2019
20A-22
CITY OF SANTA ANA EXHIBIT 3
CONSTRUCTION CONTRACT
PROJECT 18-2683, 18-2684, 18-2685, 18-2686, 18-2687, AND 18-2689
NEW LIGHTING AT SIX PARKS PROJECT
This CONSTRUCTION CONTRACT is made and entered into this 2nd day of July, 2019 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and
existing under the Constitution and laws of the State of California (hereinafter "CITY"), and Foddrill
Construction Corporation (hereinafter "CONTRACTOR').
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the
satisfaction of the City Engineer of the CITY, the New Lighting at Six Parks Project (hereinafter
referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contract
Documents prepared by the City's Public Works Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the
Standard Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed Five Hundred Seventy -Nine Thousand
Three Hundred Seventy -Eight Dollars and Seventeen Cents ($57%378:17), as set forth and identified
in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
rev. 09/01/2017 20 A -23 Page 1 of
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeftame therein specified after issuance of a Notice to
Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the
WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage
established for such work as set forth in the wage determinations for this work in accordance with
applicable State and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's
website at:
hqp://www.santa-ana.org/pwa/documents/CWA.pdf
CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent
(100%) of the Contract price to guarantee payment of all claims for labor and materials furnished
(Payment Bond). This Contract shall not become effective until such bonds are supplied to and
approved by the CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred
Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand
Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five
Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One
Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, famish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the
CITY.
//
20 A -24 Page 2 of 3
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
NORMA MITRE-RAMIREZ
Acting Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By:. ��
J FUNK
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
FUAD SWEISS, PE, PLS
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
Foddrill Construction Corporation
NAME:
TITLE:
20A-25
Page 3 of 3
20A-26
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 1�Z683--THRU,18=2689: NEW LIGHTING AT
SIX PARKS '
Construction Contract
$
- `579,378.00
Contract Administration, Inspection and Testing
$
-86,906.00_
Contingencies
$
57,716.00
TOTAL ESTIMATED CONSTRUCTION COSTS
$
724;000.00-
1Wl:ll iffil
20A-27
20A-28