HomeMy WebLinkAbout2022-014 - Washington Ave Well ProjectRESOLUTION NO. 2022-014
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA ADOPTING THE MITIGATED NEGATIVE
DECLARATION AND MITIGATION MONITORING AND
REPORTING PROGRAM FOR THE WASHINGTON AVENUE
WELL PROJECT AND APPROVING THE PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines,
and declares as follows:
A. The 2017 Santa Ana Water Master Plan water system analysis identified low
pressures along the border of the Low and High Zones adjacent to Interstate 5
Freeway. To resolve these low-pressure deficiencies, the City is proposing to
install a new water supply well and construct ancillary facilities in the vacant lot
at the northwest corner of East Washington Avenue and Penn Way (`Proposed
Project').
B. The expected production capacity of the Proposed Project will range from 2,500
to 3,000 gallons per minute.
C. Construction of the Proposed Project is anticipated to begin in 2022 and continue
until the third quarter of 2023.
D. The Proposed Project is required to undergo an environmental review pursuant
to the California Environmental Quality Act (CEQA) and the state CEQA
Guidelines. Through its consultant, the City prepared an Initial Study/Mitigated
Negative Declaration ("IS/MND") for the Proposed Project. There was no
potential for adverse impacts on agricultural and forest resources, mineral
resources, public services, or recreation associated with the Proposed Project.
Potential adverse impacts resulting from the Proposed Project were found to be
less than significant in the following areas: aesthetics, air quality, energy,
greenhouse gas emissions, hazards and hazardous materials, hydrology and
water quality, land use and planning, population and housing, transportation,
utilities and service systems, and wildfire. Full implementation of the proposed
mitigation measures included in the IS/MND would reduce potential project -
related adverse impact on biological resources, cultural resources, geology and
soils, noise, and tribal cultural resources to a less than significant level.
E. In accordance with California Pubic Resources Code section 21091 and State
CEQA Guidelines Section 15073, the Initial Study/Mitigated Negative
Declaration for the Proposed Project was circulated for a 30-day public review
and comment period from November 9, 2021 to December 8, 2021. Any public
comments that were received have been incorporated as part of the Final Initial
Resolution No. 2022-014
Page 1 of 3
Study/Mitigated Negative Declaration ("Final IS/MND") and are incorporated
herein by reference.
F. The mitigation measures set forth in the Mitigated Negative Declaration are fully
enforceable and will be implemented using the related Mitigation Monitoring and
Reporting Program accompanying the Final IS/MND in order to avoid or
minimize adverse environmental impacts identified therein.
G. On February 1, 2022, the City Council of the City of Santa Ana held a duly
noticed public hearing to consider all testimony, written and oral, related to the
Final IS/MND and the related Mitigation Monitoring and Reporting Program for
the Proposed Project, at which time all persons wishing to testify were heard, the
project was fully considered, and all other legal prerequisites to the adoption of
this Resolution occurred.
Section 2. The City Council has independently reviewed and analyzed the
information contained in the Final Initial Study/Mitigated Negative Declaration prepared for
the Proposed Project. The City Council has, as a result of its consideration and the
evidence presented at the hearing on this matter, determined that, as required pursuant to
the California Environmental Quality Act and the State CEQA Guidelines, the Final IS/MND
adequately addresses the expected environmental impacts of the Proposed Project. On
the basis of this review, the City Council finds that there is no substantial evidence from
which it can be fairly argued that the Proposed Project will have a significant impact on the
environment.
Section 3. The City Council hereby adopts the Final IS/MND and the related
Mitigation Monitoring and Reporting Program, a copy of which is attached as Exhibit A, and
directs that a Notice of Determination be prepared and filed with the Clerk of the County of
Orange in the manner required by law. This decision is based upon the evidence submitted
at the above said hearing, including but not limited to: the Request for Council Action dated
February 1, 2022, and exhibits attached hereto, and any public testimony, written and oral,
all of which are incorporated herein by this reference. The Final IS/MND is available for
viewing at the City's Public Works Agency at 20 Civic Center Plaza, Santa Ana, CA 92702.
Section 4. The City Council hereby approves the Proposed Project, based upon
the entire record before it and all written and oral evidence presented.
Section 5. Pursuant to Title XIV, California Code of Regulations, section
753.5(c)(1), the City Council has determined that, after considering the record as a whole,
there is no evidence that the Proposed Project will have the potential for any significant
adverse effect on fish and wildlife. However, the payment of Fish and Game Department
filing fees in conjunction with this project is at the ultimate determination of the California
Department of Fish and Wildlife.
Section 6. This Resolution shall take effect immediately upon its adoption by the
City Council, and the Clerk of the Council shall attest to and certify the vote adopting this
Resolution.
Resolution No. 2022-014
Page 2 of 3
ADOPTED this 15t day of February, 2022.
"46(4
Vicente Sarmiento
Mayor
APPROVED AS TO FORM:
Sonia R. Carvalho, City Attorney
By: &'L ,
John Funk
Sr. Assistant City Attorney
AYES: Councilmembers Hernandez, Lopez, Mendoza, Penaloza.
Phan, Bacerra, Sarmiento (7)
NOES: Councilmembers None (0)
ABSTAIN: Councilmembers None (0)
NOT PRESENT: Councilmembers None (0)
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, DAISY GOMEZ, Clerk of the Council
Resolution No 2022-014 to be the original
City of Santa Ana on February 1, 2022.