HomeMy WebLinkAboutItem 19 - Project W-Bus ShelterPublic Works Agency www.santa-ana.org/public-works Item # 19 City of Santa Ana 20 Civic Center Plaza, Santa Ana, CA 92701 Staff Report July 18, 2023 TOPIC: Project W-Bus Shelter AGENDA TITLE Approve an Appropriation Adjustment and Award a Construction Contract to M.S. Construction Management Group in the Amount of $428,420 for the Project W-Bus Shelter, with an Estimated Project Delivery Cost of $535,525 (Project No. 22-6999) (General Fund) RECOMMENDED ACTION 1. Approve an amendment to the FY 2023-24 Capital Improvement Program to include $282,053 in construction funds for the Project W-Bus Shelter (Project No. 22-6999). 2. Approve an appropriation adjustment recognizing $114,000 in FY 2023-24 in Senate Bill 1, Solutions for Congested Corridors Program (SCCP) grant funds in the Selected Street Construction, State Grants -Indirect revenue account, and appropriate the same amount to Select Street Construction, Improvements Other Than Building expense account. (Requires five affirmative votes) 3. Award a construction contract to M.S. Construction Management Group, the lowest responsible bidder, in accordance with the base bid in the amount of $428,420, subject to change orders (not -to -exceed 25% of the base bid) in accordance with the Greenbook: Standard Specifications for Public Works Construction, for the construction of the Project W-Bus Shelter, for a term beginning July 18, 2023, and ending upon project completion, and authorize the City Manager to execute the contract subject to non -substantive changes approved by the City Manager and the City Attorney. 4. Approve the Project Cost Analysis for a total estimated construction delivery cost of $535,525, which includes $428,420 for the construction contract, $42,842 for contract administration, inspection, and testing, and a $64,263 project contingency for unanticipated or unforeseen work. 5. Determine the recommended actions are exempt from further review in accordance with the California Environmental Quality Act as Categorical Exemption Environmental Review No. ER-2021-182 was filed for the project. Award Construction Contract with M.S. Construction Management Group July 18, 2023 Page 2 DISCUSSION The City has identified the need to undertake the installation of new bus shelters throughout all Santa Ana Neighborhoods (Exhibit 1). The scope of work includes excavation, grading, removal, and replacement of Portland cement concrete, and installation of new bus shelters. After completion, the newly installed bus shelters will provide protection from various weather conditions for citizens as they wait for the bus at any bus stop location throughout Santa Ana. Public Outreach and Contractor Participation To provide an opportunity for local vendors to submit bids, the City notified a total of 900 regional vendors via PlanetBids, many of which are Santa Ana based. Five vendors requested bidding documents and a total of two bids were received. Bids were not received from any Santa Ana contractors. As legally required, a Notice Inviting Bids was advertised in the Orange County Register newspaper on April 21, 2023 and April 28, 2023. The project was also advertised in PlanetBids from April 21, 2023 through May 107 2023. Bids were received electronically via PlanetBids on May 10, 2023. Bid Results Summary Rank Bidder's Name Location Base Bid 1 M.S. Construction Management Group Dana Point, CA $428,420 2 ND Construction Co., Inc. Long Beach, CA $523, 183 A total of two bids were received, and both were deemed responsive. M.S. Construction Management Group submitted the lowest responsive base bid in the amount of $428,420 (Exhibit 2). As specified in the bid documents, the lowest bid shall be determined on the basis of the Base Bid. Based on the bid analysis and a contractor's reference check, staff recommends awarding the construction contract to M.S. Construction Management Group, in the amount of the base bid totaling $428,420 (Exhibit 3). M.S. Construction Management Group has not performed as a prime contractor in the City of Santa Ana within the past five years. A reference check was made and good reviews were from other public agencies regarding the quality of work performed by M.S. Construction Management Group. Project Delivery To deliver a complete project, in addition to the construction contract bid amount, the estimated total project delivery cost includes construction administration, inspection, and testing, as well as an allowance for contingencies to account for unexpected or unforeseen conditions. Construction administration and inspection includes construction Award Construction Contract with M.S. Construction Management Group July 18, 2023 Page 3 management, workmanship, and quality; and materials testing. As indicated in the Cost Analysis (Exhibit 4) and as summarized in the table below, the estimated total construction delivery cost of the project is $535,525. Project Item Total Construction Contract Bid Amount $4281420 Construction Administration, Inspection, Testing 1$42,842 Contract Contingencies $64,263 TOTAL ESTIMATED CONSTRUCTION DELIVERY COST $5351525 Approval of this item will amend the FY 2023/24 Capital Improvement Program (CIP) to include the Project W-Bus Shelter (Exhibit 5). ENVIRONMENTAL IMPACT In accordance with the California Environmental Quality Act, the recommended actions are exempt from further review. Categorical Exemption Environmental Review No. ER- 2021-82 was filed for the project. FISCAL IMPACT Project No. 22-6999 is the number assigned to the funding for tracking of all expenditures to deliver the construction of this project. As indicated in the Cost Analysis, the total construction delivery cost of the project is $535,525 which includes construction, contract administration, inspection, testing, and contingency. During construction, if necessary, funds may be reallocated between construction administration, inspection, testing, and/or contingencies. The proposed contract enables staff to authorize change orders (not -to -exceed 25% of the base bid) in accordance with Greenbook: Standard Specifications for Public Works Construction, if necessary, for contingencies. Staff expects to utilize other available Public Works appropriations if a contingency becomes necessary to complete the project. If there are no other available appropriations, then staff will return to City Council with a project update and recommendations. The following table summarizes the funds budgeted and available in current FY 2023-24 for expenditure to deliver construction of this project. Existing funding will be available in the FY 2023-24 budget through the Carry Forward (CF) process. The additional budget is available in FY 2023-24 approved budget and will be assigned to the project upon approval of the amendment to the FY 2023-24 CIP. Any unspent budget in FY24 will be included in future year CF for City Council consideration. Award Construction Contract with M.S. Construction Management Group July 18, 2023 Page 4 Fiscal Accounting Unit Fund Accounting Unit - Year _Account No. Description Account No. Amount project No.) Description Existing Budget (Excluding Design Engineering) Measure M- Measure M2 2023-24 03217663-66220 Street Competitive Street, $2531472 (CF) (22-6999) Construction Improvements Other Than Buildings Additional Budget 01117622-66220 PWA Right -of -Way, 2023-24 (22-6999) General Fund Improvements Other $1685053 Than Building Appropriation Adjustment Select Street 2023-24 05917660-66220 Select Street Construction, $1141000 (22-6999) Construction Improvements Other Than Buildings Additional Budget/Appropriation Adjustment Total $282,053 Complete Total T$535,525 EXHIBITS) 1. Location Map 2. Bid Proposal 3. Construction Contract 4. Cost Analysis 5. CIP Project Sheet Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency Approved By: Kristine Ridge, City Manager Exhibit 1 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6999 PROJECT W —BUS SHELTER BID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: M.S. Construction Management Group REQUIREMENT: Exhibit 2 The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or lump surn(s) set forth in the following schedule: Item Description TQty 31 Unit EA Unit Price $ 3500 Amount $ 108 500 1 . Install Transit Advertising Shelter (Furnished by City of Santa Ana ' Vendor) 2 Install Transit Non -Advertising 17 EA $ 3500 $ 59 500 Shelter ' (Furnished by City of Santa Ana Vendor) 3 Install Solar Power for Transit 31 EA $ 400 $ 12 400 ' Advertising Shelter (Furnished by Ci of Santa Ana Vendor) 4 Install Solar Power for Transit Non- 17 EA $ 400 $ 6 800 ' Advertising Shelter (Furnished by City of Santa Ana Vendor) EA _ 300 $ 17,400 ' 5 Install Steel Bench (Furnished by 58 City of Santa Ana Vendor) $ 20' 100 6 Install 32 Gallon Trash Receptacle 67 EA $ 300 (Furnished by City of Santa Ana Vendor) 7 PCC Sidewalk (T=6")* 6,000 SF = $ 21 $ 126,000 $ 600 8 Adjust Water Meter to Finished 1 EA $ 600 Grade 9 Furnish and install New #6 Pullbox 3 EA $ 550 $ 1,650 10 Construction Permit I LS $6,130 $6,130 I I Master Padlock 67 EA $20 $1,340 12 Removal of Existing Bus Shelter, 34 EA Bench, and Trash Receptacle at bus $2,000 $68,000 Stop locations P-1 of P-16 CITY OF SANTA ANA Exhibit 2 PROPOSAL PROJECT NO.: 22-6999 PROJECT W —BUS SHELTER TOTAL BASE BID 1 $ 4283420.00 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. j' This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications. TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within number f8O) working days after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $1,500 per calenar day. Name of Firm M.S. Construction ManWemer�(Group Signature of BIDDER Title President /I (If an individual, so state. If a firm or co-partnershtV state the firm name and give the names of all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-2 of P-16 EXHIBIT 3 CITY OF SANTA ANA CONSTRUCTION CONTRACT PROJECT 22-6999 PROJECT W-BUS SHELTER This CONSTRUCTION CONTRACT is made and entered into this 18th day of July, 2023 by and between the City of Santa Ana, California, a charter city and municipal corporation organized and existing under the Constitution and laws of the State of California (hereinafter "CITY"), and M.S. Construction Management Group (hereinafter "CONTRACTOR"). WITNESSETH: The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows: 1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction of the City Engineer of the CITY, the Project W Bus Shelter (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contract Documents prepared by the City's Public Works Agency and approved by the City Council. 2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard Specifications for Public Works Construction and which include the following: • Notice Inviting Bids • Information to Bidders • Bid Proposal • Bid Bond • Contract Form • Contract Bonds • General Provisions • Special Provisions • Technical Provisions and Project Plans • Community Workforce Agreement • Appendices In case of conflict between the Contract Documents, the precedence of documents shall be as established in the Standard Specifications for Public Works Construction. 3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF IMPROVEMENT the sum total amount not to exceed Four Hundred Twenty -Eight Thousand Four Hundred Twenty Dollars and No Cents ($428,420.00), as set forth and identified in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A." The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate quantities only, and the City does not expressly or by implication agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work or to omit portions of the work as maybe deemed necessary or advisable. rev. 09/01/2017 Page 1 of 3 4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including commencing construction within the timeframe therein specified after issuance of a Notice to Proceed. 5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for such work as set forth in the wage determinations for this work in accordance with applicable State and Federal law. 6. If applicable, the CONTRACTOR shall adhere to the CITY' S Community Workforce Agreement (CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website at: http://www.santa-ana.org/pwa/documents/CWA.pdf 7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY, one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%) of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment Bond). This Contract shall not become effective until such bonds are supplied to and approved by the CITY. 8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price. 9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY. 10. INDEMNIFICATION. To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend, indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents, employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"), through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs, damages or losses, including reasonable costs and attorney's fees, for injury, including death to any person or damage to any property, arising directly or indirectly from, or in any manner relating to, any of the following: (1) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its Subcontractors of any lower tier; (ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, of any of the obligations under the Contract Documents; Page 2 of 3 �( ii The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either on the project site or on other properties,, (1v) The payment or nonpayment by CONTRACTOR of any of its SUbcontractors of any lower tier, for Work of Improvement performed on or off the project site; and (v) Any personal injury, property damage or economic loss to third persons related to and arising from the performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, of the Work of Improvement. (vi) The indemnity obligations of Subcontractors provided by this Section shall be inctuded in all subcontract doUlments issued by CONTRACTOR. Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity ill favor of CON'I-R.AcrOR against CITY or any other Indemnitee. IN WITNESS WHEREOF., the parties hereto have executed this Construction Contract on the day and year first above written. ATTEST: JENNIFER L. HALL City Clerk APPROVED AS TO FORM: SONIA R. CARVALHO City Attorney 00 JOSS MONTOYA Assistant City Attorney RECOMMENDED FORAPPROVAL: NABIL BABA, PE Executive Director Public Works Agency CITY OF SA TA ANA KRISTINE RIDGE City Manager CONTRACTOR: M.S. Construction Mp`ag'ement Group /Z --, ' 4 NAME: Mike S of TITLE: Preside Page 3 of 3 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6999 PROJECT W —BUS SHELTER BID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: M.S. Construction Management Group REQUIREMENT: Exhibit A The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or lump surn(s) set forth in the following schedule: Item Description TQty 31 Unit EA Unit Price $ 3500 Amount $ 108 500 1 . Install Transit Advertising Shelter (Furnished by City of Santa Ana ' Vendor) 2 Install Transit Non -Advertising 17 EA $ 3500 $ 59 500 Shelter ' (Furnished by City of Santa Ana Vendor) 3 Install Solar Power for Transit 31 EA $ 400 $ 12 400 ' Advertising Shelter (Furnished by Ci of Santa Ana Vendor) 4 Install Solar Power for Transit Non- 17 EA $ 400 $ 6 800 ' Advertising Shelter (Furnished by City of Santa Ana Vendor) EA _ 300 $ 17,400 ' 5 Install Steel Bench (Furnished by 58 City of Santa Ana Vendor) $ 20' 100 6 Install 32 Gallon Trash Receptacle 67 EA $ 300 (Furnished by City of Santa Ana Vendor) 7 PCC Sidewalk (T=6")* 6,000 SF = $ 21 $ 126,000 $ 600 8 Adjust Water Meter to Finished 1 EA $ 600 Grade 9 Furnish and install New #6 Pullbox 3 EA $ 550 $ 1,650 10 Construction Permit I LS $6,130 $6,130 I I Master Padlock 67 EA $20 $1,340 12 Removal of Existing Bus Shelter, 34 EA Bench, and Trash Receptacle at bus $2,000 $68,000 Stop locations P-1 of P-16 CITY OF SANTA ANA Exhibit A PROPOSAL PROJECT NO.: 22-6999 PROJECT W —BUS SHELTER TOTAL BASE BID 1 $ 4283420.00 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. j' This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications. TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within number f8O) working days after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $1,500 per calenar day. Name of Firm M.S. Construction ManWemer�(Group Signature of BIDDER Title President /I (If an individual, so state. If a firm or co-partnershtV state the firm name and give the names of all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-2 of P-16 EXHIBIT 4 COST ANALYSIS CONSTRUCTION OF PROJECT NO. 22-6999: Project W- Bus Shelter Construction Contract $ 4287420.00 Contract Administration, Inspection and Testing $ 427842.00 Contingencies $ 647263.00 TOTAL ESTIMATED CONSTRUCTION COSTS $ 5357525.00 I W W I = UO N r �V V W LL QO as IQ z F-w ZM Qw ILL Ow � a H � V J Q F- L) 4- �3 Q 6 Cd q � C O O O � W c) LU Z a H 4- C) �, o Oo a co C3 cx c� U CL � O � W Lu H C� Q) H F- L) W zz 0.0 O , a � � a U- 0 a Q z _O H Q C.� O J 00 00 i N N N N U- U- I., r N N N N LUL LPL to to Ul Ul (N N U- LPL LO UlCN , N N U- U- N N N N LUL LPL M ' ' M N N N N U- U- N O CA N O O N (D TC) o o � O co O 01 O LPL LPL J J Q Q O O H Q H Cl) Z H Cl) � O ILL C) ILL c O ~ oI.- v w W � L v O M w � O a U) W 0 H C.� CN 04 W H a V Z W aCL LO