City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
July 18, 2023
TOPIC: New Water Well Drilling at Washington Site
AGENDA TITLE
Award a Construction Contract to Best Drilling and Pump, Inc. in the Amount of
$2,978,524 for the Washington Well Improvements: Well Drilling (Phase 1), with an
Estimated Project Delivery Cost of $3,432,274 (Project No. 19-6423) (Non -General
Fund)
RECOMMENDED ACTION
1. Award a construction contract to Best Drilling and Pump Inc., the lowest responsible
bidder, in accordance with the base bid in the amount of $2,978,524, subject to
change orders (not -to -exceed 25% of the base bid) in accordance with the
Greenbook: Standard Specifications for Public works Construction, for construction
of the Washington Well Improvements: Well Drilling (Phase 1) Project, for the term
beginning July 18, 2023, and ending upon project completion, and authorize the
City Manager to execute the contract subject to non -substantive changes approved
by the City Manager and the City Attorney.
2. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$3,432,274 which includes $2,978,524 for the construction contract, $100,000 for
contract administration, inspection, and testing, and a $353,750 project contingency
for unanticipated or unforeseen work.
DISCUSSION
The ultimate Washington Well Site Improvements Project includes the construction of a
new groundwater well, including piping and electrical equipment, a well building, and a
chemical storage building located at the intersection of Washington Avenue and Penn
Way (Exhibit 1). The project creates an additional local water supply, which improves
the City' s long-term resilience, and closes the projected gap between future demand
and available supply by adding over 4,000 acre-feet per year to the City's pumping
capacity. This promotes less reliance on imported water, which, in turn, reduces
wholesale water costs. The project will also address low-pressure deficiencies, improve
reliability, and increase flexibility within the City' s water system.
Washington Well Improvements: Well Drilling
July 18, 2023
Page 2
Phase 1 of the project includes drilling of the well bore hole to a depth of 1,300 feet
below ground surface, installation of 18-inch stainless steel well casing and screen, filter
packs, geophysical surveys, water quality testing, installation of construction sound
walls, and all other incidental work as specified in the construction plans and contract
documents.
Project Funding
As part of a continual effort to maintain fiscal responsibility, staff has sought additional
funding sources to complete the project. In 2021, the City was awarded $750,000 in
federal Bureau of Reclamation grant funds, $740,000 of which is available for project
construction costs. Additional grant funds in the amount of $3,394,743 are anticipated to
be awarded to the project during the current calendar year via the State of California
Department of Water Resources Proposition 1 Implementation Grant Program.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was
advertised in the Orange County Register newspaper on March 17 and March 24, 2023.
The project was also advertised on PlanetBids, and bids were received electronically via
PlanetBids on April 27, 2023.
The City notified a total of 940 regional vendors via PlanetBids, 42 of which are Santa
Ana based. Twenty-eight vendors requested bidding documents. A total of four bids
were received. However, no bids were received from Santa Ana contractors.
Bid Results Summ
Rank
Bidder's Name
Location
Base Bid
1
Best Drilling and Pump, Inc.
Colton, CA
$2,978,524
2
Nor -Cal Pump & Well Drilling, Inc.
Yuba City, CA
$3,197,304
3
Layne Christensen Company, Inc.
Redlands, CA
$3,500,998
NR
South West Pump & Drilling, Inc.
Coachella, CA
$2,774,283
Of the four bids received, one was deemed not responsive. Best Drilling and Pump,
Inc. submitted the lowest responsive base bid, in the amount of $2,978,524 (Exhibit 2)
As specified in the bid documents, the lowest bid shall be determined on the basis of
the Base Bid. Based on the bid analysis and a contractor's reference check, staff
recommends awarding the construction contract to Best Drilling and Pump, Inc., in the
amount of the base bid totaling $2,978,524 (Exhibit 3).
Best Drilling and Pump, Inc. has not performed as a prime contractor in the City of
Santa Ana within the past five years. A reference check was made and received good
Washington Well Improvements: Well Drilling
July 18, 2023
Page 3
reviews from other public agencies regarding quality of work performed by Best Drilling
and Pump, Inc.
Project Delivery
To deliver a complete project, in addition to the construction contract bid amount, the
estimated total project delivery cost includes construction administration, inspection,
and testing, along with an allowance for contingencies to account for unexpected or
unforeseen conditions. Construction administration and inspection includes the
following: construction management and materials testing. As indicated in the Cost
Analysis (Exhibit 4) and as summarized in the table below, the estimated total
construction delivery cost of the project is $3,432,274.
Project Item
Total
Construction Contract Bid Amount
$2,978,524
Construction Administration, Inspection, Testing
$100,000
Contract Contingencies
$353,750
TOTAL ESTIMATED CONSTRUCTION DELIVERY COST
$3,432,274
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, a Mitigated Negative
Declaration was prepared for the project and was filed with the document number
2021110169.
FISCAL IMPACT
Project No. 19-6423 is the number assigned to the funding for tracking of all
expenditures to deliver the construction of this project. As indicated in the Cost Analysis,
the estimated total construction delivery cost of the project is $3,432,274 which includes
the construction contract, contract administration, inspection, testing, and project
contingency.
Funds for this project have been transferred from previously appropriated funds for the
East Pump Station Security Fencing Project (19-6433) to the Washington Well
Improvements: Well Drilling (Phase 1) Rebid Project (19-6423).
The proposed contract enables Staff to authorize a change order (not -to -exceed 25% of
the base bid) in accordance with the Greenbook: Standard Specifications for Public
Works Construction, if necessary, for contingencies. Staff expects to utilize other
available Public Works appropriations if a contingency becomes necessary to complete
the project. If there are no other available appropriations, then Staff will return to the
City Council with a project update and recommendations.
The following table summarizes the funds budgeted and available in current FY 23-24
for expenditure to deliver construction of this project. Any remaining balances not
Washington Well Improvements: Well Drilling
July 18, 2023
Page 4
expended at the end of the fiscal year will be presented to City Council for approval of
carrvovers to FY 24-25.
Accounting Unit
Fund
Accounting Unit -
r
Year ea
- Account No.
Description
Account No.
Amount
(Project No.)
Description
Prior Authorized Funds Transfers
06617647-66301
Acquisition &
Water Utility Capital
2023-24
(From 19-6433
Construction
Projects, Water Capital
$600,034
To 19-6423)
Project
ExistingProject Budget
06617647-66301
Acquisition &
Water Utility Capital
2023-24
(19-6423)
Construction
Projects, Water Capital
$2,092,240
Project
PWA
WaterSMART-
2023-24
16417641-66220
Enterprise
Watershed Mgmt Prog,
$740,000
(19-6423)
Capital
Improvements Other
Grants
Than Buildings
Total
$3,432,274
EXHIBIT(S)
1. Location Map
2. Bid Proposal
3. Construction Contract
4. Cost Analysis
5. CIP Project Sheet
Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency
Approved By: Kristine Ridge, City Manager
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Best Drilling and Pump, Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Unit
Unit Price
Amount
I
Mobilization & Demobilization
including Noise Attenuation Panels
1
LS
$ 400,000.00
$ 400,000.00
2
NPDES Discharge Compliance
1
LS
$ 300,000.00
$ 300,000.00
3
Conductor (Surface) Casing
52
FT
$ 1,300.00
$ 67,600.00
4
Pilot Hole Drilling
1,250
FT
$ 200.00
$ 250,000.00
5
Downhole Geophysical Surveying
1
LS
$ 8,000.00
$ 8,000.00
6A
Isolated Aquifer Zone Testing
6
EA
$ 30,000.00
$ 180,000.00
6B
Collect, Deliver and Testing of
Zone Tests
6
EA
$ 8,000.00
$ 48,000.00
7A
38-inch Dia. Upper Pilot Hole
Ream
450
FT
$ 180.00
$ 81,000.00
7B
28-inch Dia. Lower Pilot Hole
Ream
800
FT
$ 170.00
$ 136,000.00
1
1
502
8A
Caliper Survey
Magnetic Deviation Survey
LS
LS
LF
$ 4,000.00
$ 4,000.00
$ 4,000.00
$ 352,906.00
8B
i
$ 4,000.00
$ 703.00
9A
18-inch ID Blank Casing
9B
18-inch ID Blank Well Casing,
Cellar Pipe & End Cap
170
LF
$ 587.00
$ 99,790.00
P-1 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
Item
Description
Qty
Unit
Unit Price
Amount
9C
18-inch ID Louvered Well Casing
600
FT
$ 686.00
$ 411,600.00
9D
3-inch Dia. Gravel Feed Tube
422
FT
$ 79.00
$ 33,338.00
9F
2-inch Dia. Pressure Transducer
Tube
452
FT
$ 65.00
$ 29,380.00
9G
4-inch Dia. Camera Tube
440
FT
$ 160.00
$ 70,400.00
9H
3-inch ID Air Vent Tube
4
FT
$ 200.00
$ 800.00
10A
Pilot Hole Bottom Bentonite Seal
(Optional)
10
FT
$ 55.00
$ 550.00
10B
Intra-Annular Seal (Optional)
20
FT
$ 55.00
$ 1,100.00
11
Gravel Pack
890
FT
$ 100.00
$ 89,000.00
12
Annular Grout Seal
395
FT
$ 130.00
$ 51,350.00
13
Well Casing Alignment Testing
1
LS
$ 5,000.00
$ 5,000.00
14
Standby Time
24
HR
$ 400.00
$ 9,600.00
15
Mechanical Well Development
120
HR
$ 800.00
$ 96,000.00
16A
Chemical Development (12.5%
Chlorine Solution)
257
GAL
$ 30.00
$ 7,710.00
16B
Chemical Development (Polymer
Dispersant)
32
GAL
$ 200.00
$ 6,400.00
17
Color Video Surveys
3
EA
$ 2,000.00
$ 6,000.00
18A
Temporary Test Pump
I
LS
$ 30,000.00
$ 30,000.00
18B
Flow Meter Device
I
LS
$ 5,000.00
$ 5,000.00
18C
Water Quality Meter
1
LS
$ 15,000.00
$ 15,000.00
19
Pumping Development
60
HR
$ 600.00
$ 36,000.00
P-2 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
Item
Description
Qty
Unit
Unit Price
Amount
20A
Step Drawdown Test
12
HR
$ 600.00
$ 7,200.00
20B
Constant Rate Pumping Test
48
HR
$ 600.00
$ 28,800.00
21
Dynamic Flow Meter Survey
1
LS
$ 5,000.00
$ 5,000.00
22A
Depth Specific Sampling
7
EA
$ 1,000.00
$ 7,000.00
22B
Collect, Deliver and Testing of
Discrete Sampling
7
EA
$ 5,000.00
$ 35,000.00
23
Static Flowmeter Survey
1
LS
$ 5,000.00
$ 5,000.00
24
Well Disinfection and Capping
1
LS
$ 10,000.00
$ 10,000.00
25A
Abandonment of Borehole at City's
Request (This bid item not to be
used in totaling of base bid)
1300
LF
$ 23.00
$ 29,900.00
25B
Destruction of Well at City's
Request (This bid item not to be
used in totaling of base bid)
1
LS
$ 30 000.00
$ 30,000.00
26
Erosion Control and BMP Measures
1
LS
$ 30,000.00
$ 30,000.00
27
City Construction Permit
(Allowance)
1
LS
$ 15,000
$ 15,000
P-3 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
TOTAL BASE BID $ 2,978,524.00
(Items 1 to 27 excluding Item 25A and 25B)
The lowest responsible bidder shall be selected based on the total base bid (Items 1 to 27 excluding
Item 25A and 25B). The City reserves the right to award the Base Bid, and any, all, or none of the
add -alternate bid items (if any).
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within one hundred and thi 130 working days after the commencement date stated
in the Notice to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $1,500 per calendar day.
Name of Firm Best Drilling and ?ump, Inc.
Signature of BIDDER
Title Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-4 of P-18
EXHIBIT 3
UNANIMOUS WRMEN CONSENT
OF DIRECTORS OF
BEST DRILLING AND PUMP, #4C.
A Califon'a Cosporation.
The undersigned, constitutingI directors of the above
. -named all' the & e x -bov -narried corporation.*
actin pursuant to the authority of Corporations.Code Section 3-07(b), hereby adopt . the
following recitals and effective resolutions, ve on the
s I signed beJow:
WNEREA8. the Board has deernddit to be in thebest in - -c corporation
terests oftlit, o ew.
to competitively bid on public works contracts for t
contracts I . public.projec --
s.,
tt REAS; said corporate officers shall also be authorized to enter: into any
contract arising froin a submitted bid binding, tbe_;orp*or _ationassetlbrthherein;
Nowi _rr�-REFORE, BE 11' RESOLVED, that the JblJov%j3Pg corporate ciffi=s
are hereby auth.6riZed to execute and submit bids on public works
contracts for public
projects and to execute and enter into .any' contracts ariting.frow said `bidss-submitted on
behalf of the corporation:
JOHN KENNEDY, P: re L sident/Seaeuq
MARK BEST, CEO
NII 8 kENWEDY. trice President
DEAN GARCIA., Vice Piesident
CONNOR HARMON, Vice Piesident
DAN WOODARD,Contioller
BE IT FURTHER RESOLVED that the above -named wWrate officers are
Airther authorized to sign any andall documents which may be necessary to final arty
finalize a
contract on behalf of the corporation.
DATED. Septembet 15, 2021
John Kennetty, Presidiht
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 19-6423
WASHINGTON WELL IMPROVEMENTS WELL DRILLING (PHASE 1) RE -BID PROJECT
This CONSTRUCTION CONTRACT is made and entered into this 18th day of July, 2023 by and between
the City of Santa Ana, California, a charter city and municipal corporation organized and existing under
the Constitution and laws of the State of California (hereinafter "CITY"), and Best Drilling and Pump,
Inc. (hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the Washington Well Improvements: Well Drilling (Phase 1) Re -
Bid (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in accordance
with the Contract Documents prepared by the City's Public Works Agency and approved by the City
Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF
IMPROVEMENT the sum total amount not to exceed Two Million Nine Hundred and Seventy -Eight
Thousand Five Hundred Twenty -Four Dollars and No Cents ($2,978,524.00), as set forth and
identified in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of work
will correspond therewith, but reserves the right to increase or decrease the amount of any class or
portion of the work or to omit portions of the work as may be deemed necessary or advisable.
rev. 09/01/2017 Pagel of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at: httl2://www.santa-ana.oriz/pwa/documents/CWA.12d
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
JENNIFER L. HALL
City Clerk
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By: �� ;4.
JOSE MONTOYA
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
Best Drilling and Pump, Inc.
N ME: onnor Harmon
TITLE: Vice -President
Page 3 of 3
CITY OF SANTA ANA Exhibit A
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Best Drilling and Pump, Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Descri tion
Mobilization & Demobilization
including Noise Attenuation Panels
NPDES Discharge Compliance
Conductor (Surface) Casing
Qty
1
1
52
Unit
LS
LS
FT
$
$
$
Unit Price
400,000.00
300,000.00
1,300.00
Amount
$ 400,000.00
$ 300,000.00
$ 67,600.00
1
2
3
4
Pilot Hole Drilling
1,250
FT
$
200.00
$
+ $
250,000.00
8,000.00
5
Downhole Geophysical Surveying 1 LS
$ 8,000.00
6A
Isolated Aquifer Zone Testing
6
EA
$
30,000.00
$
180,000.00
6B
Collect, Deliver and Testing of
Zone Tests
6
EA
$
8,000.00
$
48,000.00
7A
38-inch Dia. Upper Pilot Hole
Ream
450
FT
$
180.00
$
81,000.00
7B
2R8-inch Dia. Lower Pilot Hole
Caliper Survey
g00
1
FT
LS
$
$
170.00
4,000.00
$
136,000.00
$
4,000.00
8A
8B
Magnetic Deviation Survey
1
LS
$
4,000.00
$
4,000.00
9A
9B
18-inch ID Blank Casing
18-inch ID Blank Well Casing,
Cellar Pipe & End Cap
502
170
LF
LF
$
$
703.00
587.00
$
$
352,906.00
99,790.00
P-1 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
Item
DesSK! tion
Unit
Unit Price
Amount
9C
18-inch ID Louvered Well Casing
600
FT
$
686.00
$ 411,600.00
9D
3-inch Dia. Gravel Feed Tube
422
FT
$
79.00
$ 33,338.00
9F
2-inch Dia. Pressure Transducer
452
FT
$
65.00
$ 29,380.00
Tube
9G
4-inch Dia. Camera Tube
440
FT
$
160.00 f
$ 70,400.00
9H
3-inch 1D Air Vent Tube
4
FT
$
200.00 7
$ 800.00
10A
Pilot Hole Bottom Bentonite Seal
10
FT
$
55.00
$ 550.00
(Optional)
10B
Intra.-Annular Seal (Optional)
20
FT
$
55.00
$ 1,100.00
11
Gravel Pack
890
FT
$
100.00
$ 89,000.00
12
Annular Grout Seal
395
FT
$
130.00
$ 51,350.00
13
Well Casing Alignment Testing
1
LS
$
5,000.00
$ 5,000.00
14
Standby Time
24
HR
$
400.00
$ 9,600.00
15
Mechanical Well Development
120
HR
$
800.00
$ 96,000.00
16A
Chemical Development (12.5%
257
GAL
$
30.00
$ 7,710.00
Chlorine Solution)
16B
Chemical Development (Polymer
32
GAL $
200.00
$ 6,400.00
Dispersant)
17
Color Video Surveys
3
EA $
2,000.00
$ 6,000.00
18A
Temporary Test Pump
I
LS $
30,000.00
$ 30,000.00
18B
Flow Meter Device
1
LS $
5,000.00 $
5,000.00
18C
Water Quality Meter
I
LS $
15,000.00 $
15,000.00
19
Pumping Development
60
HR $
600.00 $
36,000.00
P-2 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
Item
Descri tion
:UnitTUnit
Price
Amount
20A
Step Drawdown Test
12
HR
600.00
7,200.00
20B
Constant Rate Pumping Test
48
HR
$
600.00
$
28,800.00
21
Dynamic Flow Meter Survey
I
LS
$
$
5,000.00
1,000.00
$
5,000.00
22A
Depth Specific Sampling 7 EA
$
$
$
7,000.00
35,000.00
5,000.00
22B
Collect, Deliver and Testing of 7 EA
Discrete Sampling
$ 5,000.00
23
Static Flowmeter Survey 1 LS
$ 5,000.00
24
Well Disinfection and Capping
1
LS
$
10,000.00
$
10,000.00
25A
Abandonment of Borehole at City's
Request (This bid item not to be
used in totaling of base bid)
1300
LF
$
23.00
$
29,900.00
25B
Destruction of Well at City's
Request (This bid item not to be
1
LS
$
30,000.00
$
30,000.00
used in totaling of base bidi
$
30,000.00
26 Erosion Control and BMP Measures 1 LS $ 30,000.00
I._
27
City Construction Permit (Allowance)
1
LS
$
15,000
$
15,000
P-3 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 19-6423
WASHINGTON WELL IMPROVEMENTS
WELL DRILLING (PHASE 1) RE -BID
TOTAL BASE BID $ 2,978,524.00 —
(Items 1 to 27 excluding Item 25A and 25B)
The lowest responsible bidder shall be selected based on the total base bid (Items 1 to 27 excluding
Item 25A and 25B). The City reserves the right to award the Base Bid, and any, all, or none of the
add -alternate bid items (if any).
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within one hundred and thirty 130 working days after the commencement date stated
in the Notice to Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $1,500 per calendar day.
Name of Firm Best Drilling and �ump, Inc.
Signature of BIDDER 4
Title Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-4 of P-18
EXHIBIT 4
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 19-6423: Washington Well Improvements:
Well Drilling (Phase 1) Rebid
Project Item
Total
Construction Contract
$2,978,524.00
Construction Administration, Inspection, Testing
$100,000.00
Contingencies
$353,750.00
TOTAL CONSTRUCTION DELIVERY COST
$3,432,274.00
EXHIBIT 5
PROJECT TITLE:
Washington Well Site Improvements
PROJECT CATEGORY:
Utility/Drainage/Lighting Improvements
Water
LOCATION MAP
AGENCY:
Public Works
IN
CITY OF SANTA ANA FY22/23CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Drilling a new groundwater well.
PROJECT NEED:
A new well will help increase the reliability, performance and
customer experience.
PROJECT COSTS FY 22/23 FY 23124 FY 24125 FY 25/26 FY 26/27 FY 27128 FY 28129
Construction Progress Pay 600,033.16 - - - - - -
TOTAL 600,033.16
SOURCE OF FUNDS FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29
WTR UTY CAPITAL 600,033.16 - - - - - -
PROJECTS
TOTAL 600,033.16 - - - - -
DIVISION:
Water Resources
CONTACT:
James Burk, Senior Civil Engineer
DATE:
18-July-2023