HomeMy WebLinkAboutItem 15 - Downtown Flood Reduction and Stormwater Infiltration ProjectPublic Works Agency
www.santa-ana.org/public-works
Item # 15
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
March 21, 2023
TOPIC: Downtown Flood Reduction and Stormwater Infiltration Project
AGENDA TITLE
Approve Appropriation Adjustments and Award a Construction Contract to GMZ
Engineering, Inc. in the Amount of $4,642,644 for the Downtown Flood Reduction and
Stormwater Infiltration Project with an Estimated Construction Delivery Cost of
$5,640,000 (Non -General Fund)
RECOMMENDED ACTION
1. Approve an appropriation adjustment to recognize an additional $1.25 million in
Proposition 68 Urban Flood Protection (UFP) grant funding from the California
Natural Resources Agency into the Public Works Agency Enterprise Capital
Grants, Direct Revenue Account and appropriate the same amount into the
California Natural Resources Agency Urban Flood Protection, Improvements
Other Than Building expenditure account. (Requires five affirmative votes)
2. Approve an appropriation adjustment to recognize $900,000 of prior year fund
balance in the Federal Clean Water Protection fund, Prior Year Carryforward
revenue account and appropriate the same amount into the Federal Clean Water
Protection Enterprise, Improvements Other Than Building expenditure account.
(Requires five affirmative votes)
3. Approve an amendment to the Fiscal Year 2022-23 Capital Improvement
Program to add $1.25 million of Proposition 68 Urban Flood Protection Grant
Program funding and $900,000 of Federal Clean Water Protection Enterprise
funding for the Downtown Flood Reduction and Stormwater Infiltration Project
(22-6622).
4. Award a construction contract to GMZ Engineering Inc., the lowest responsible
bidder, in accordance with the base bid plus bid alternate in the amount of
$4,642,644, for construction of the Downtown Flood Reduction and Stormwater
Infiltration Project, for the term beginning March 21, 2023 and ending upon
project completion, and authorize the City Manager to execute the contract
subject to non -substantive changes approved by the City Manager and the City
Attorney.
Downtown Flood Reduction and Stormwater Infiltration Project
March 21, 2023
Page 2
5. Approve the Project Cost Analysis for a total estimated construction delivery cost
of $5,640,000, which includes $4,642,644 for the construction contract, $552,356
for contract administration, inspection and testing, and a $445,000 project
contingency for unanticipated or unforeseen work.
DISCUSSION
This Downtown Flood Reduction and Stormwater Infiltration Project features the
upgrade of storm drain infrastructure along East 3rd Street, between Main Street and
French Street, and the construction of a subsurface stormwater infiltration system
underneath the City -owned parking lot at 3rd Street and Bush Street (Exhibit 1). The
project also includes drought -tolerant landscaping, reconstruction of the City -owned
parking lot, paving, and interpretive signage to promote stormwater management. This
project will help reduce flooding Downtown, increase local water supplies, and improve
water quality in the Newport Bay watershed.
Public Outreach and Contractor Participation
This project was originally advertised for bid on November 8, 2022, with bids due on
December 6, 2022. To provide an opportunity for local vendors to submit bids, the City
notified 1,494 regional vendors via PlanetBids, many of which are Santa Ana based. Six
vendors requested bidding documents, and a total of six bids were received. Bids were
not received from any Santa Ana contractors.
As legally required, a Notice Inviting Bids was advertised in the Orange County Register
newspaper on November 14, 2022 and November 23, 2022. The project was also
advertised in PlanetBids from November 8, 2022 through December 6, 2022. Bids were
received electronically via PlanetBids on December 6, 2022.
Bid Results Summary
Rank
Bidder's Name
Location
Base Bid
1
GMZ Engineering, Inc.
Westlake Village, CA
$4,458,844
2
Big Ben Inc.
Irvine, CA
$4,763,888
3
Boudreau Pipeline Corporation
Corona, CA
$5,039,548
4
Excel Paving Co
Long Beach, CA
$5,179,765
5
mmc, inc
La Palma, CA
$5,594,943
6
Access Pacific, Inc.
Pasadena, CA
$6,180,861.78
A total of six bids were received, all of which were deemed responsive. GMZ
Engineering, Inc. submitted the lowest responsive base bid in the amount of $4,642,644
Downtown Flood Reduction and Stormwater Infiltration Project
March 21, 2023
Page 3
(Exhibit 2). As specified in the bid documents, the lowest bid shall be determined by the
Base Bid. Alternate bid items were also included for additional paving and striping work.
In the past five years, GMZ Engineering, Inc. has not performed any work for the City.
Based on the bid analysis and a contractor reference check, staff recommends
awarding the construction contract to GMZ Engineering, Inc. in the amount of the Base
Bid + Bid Alternatives, totaling $4,642,644 (Exhibit 3).
Proiect Delive
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes construction administration, inspection, and testing, along
with an allowance for contingencies to account for unexpected or unforeseen
conditions. Construction administration and inspection includes the following:
construction management; inspection of the Contractor's work to ensure contract
compliance, workmanship, and quality; and materials testing. As indicated in the Cost
Analysis (Exhibit 4) and as summarized in the table below, the estimated total
construction delivery cost of the project is $5,640,000.
The original grant agreement for this project with the California Natural Resources
Agency (CNRA) included $3.8 million of Prop 68 Urban Flood Protection (UFP) grant
funding. Due to elevated construction costs, staff was successful at obtaining an
additional $1.25 million from CNRA to deliver the project.
Project Item
Total
Construction Contract
$4,642,644
Construction Administration, Inspection, Testing
$552,356
Contingencies
$445,000
TOTAL CONSTRUCTION DELIVERY COST
$5,640,000
Approval of the amendment to the FY 2022-23 Capital Improvement Program (Exhibit 5)
will officially incorporate the additional funding for the project into the CIP program.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions
are exempt from further review. Categorical Exemption Environmental Review No. ER-
2022-95 was filed for the project.
FISCAL IMPACT
This project was originally authorized on January 18, 2022 in the FY 2021-22 CIP as
Project No. 22-6622, with a total project budget of $3,800,000. With approval of the
$1.25 million and $900,000 Appropriation Adjustments, the new total project budget will
be $5,950,000. As indicated in the Cost Analysis, the estimated total construction
delivery cost of the project is $5,640,000, which includes construction, contract
administration, inspection, testing, and an authorized contingency.
Downtown Flood Reduction and Stormwater Infiltration Project
March 21, 2023
Page 4
The current fiscal year funding is available in the FY 2022-23 budget and future fiscal
year funding will be included in the proposed budgets for City Council consideration.
Fiscal
Accounting Unit -
Fund
Accounting Unit -Account
Year
Account No.
Description
No. Description
Amount
(Project No.)
Prior Authorized Funds
16417644-66220
PWA
CNRA Urban Flood
2021-22
(22 6622)
Enterprise
Protection, Improvements
$3,800,000
Capital Grants
Other Than Building
Appropriation Adjustments
16417644-66220
PWA
CNRA Urban Flood
2022-23
(22 6622)
Enterprise
Protection, Improvements
$1,250,000
Capital Grants
Other Than Building
Federal Clean
Federal Clean Water
2022-23
05717640-66220
Water
Protection Enterprise,
$900,000
(22-6622)
Protection
Improvements Other Than
Enterprise
Building
Total
$5,950,000
EXHIBIT(S)
1.
Location Map
2.
Bid Proposal
3.
Construction Contract
4.
Cost Analysis
5.
FY 2021-22 C I P Sheet
Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency
Approved By: Kristine Ridge, City Manager
Exhibit 1
SANTAANA Project No. 22-6622.
Pi Downtown Flood Reduction & Stormwater
PUBLICWO- Infiltration
CITY OF SANTA ANA
PRO Pa SAL
PROJECT NO.: 22-5422
DOWNTOWN FLOOD REDUCTION! AND STORMWATER INFILTRATIONI
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: GMZ Enaineerinci. Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Remove Bollard
5
EA
$ 250.00
$ 1,250.00
2
Remove, Salvage/Replace, and Reinstall
54
EA
$ 100.00
$ 5,400.00
Wheel Stop
3
Remove, Salvage, and Reinstall Parking
26
EA
$ 100.00
$ 2.600-00
Meter Post
4
Remove, Salvage, and Reinstall Swing
I
EA
$
$
Gate
2,500.00
2,500.00
5
Remove, Salvage, and Reinstall Waste
I
EA
S 250.00
$ 250.00
Receptacle
6
Remove, Salvage/Replace, and Reinstall
4
EA
$
1,500.00
$
13,000.00
Electric Pullbox
7
Remove, Salvage, and Reinstall Light Pole
2
EA
$
$
10,000.00
20,000.00
8
Remove, Salvage, and Reinstall Electric
1
EA
$
S
Vehicle Charging Station
10,000.00
10,000.00
9
Remove, Salvage, and Reinstall
I
EA
$
S
Emergency Phone Pole
10,000.00
10 000.00
10
Remove and Replace Electrical Conduit
I
LS
$
$
25,000.00
and Wiring In Kind
25,000-00
11
Remove Storm Drain Maintenance Hole
3
EA
$
5,000.00
$
15,000.00
12
Clearing and Grubbing
1,780
Si'
S
5.00
$
$,900.00
I3
Remove Tree
2
EA
$ 1,500,00
S 3,000.00
14
Unclassified Excavation and Export
2,590
CY
$ 85.00
$
220,150.0D
(Parking Lot)*
IS 1Unclassified
Excavation, Stockpile, and
4,500
CY
$ 25,00
$ 112,500.00
Reuse as Backfill (Parking Lot)*
P-1 ofP-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6622
DOWNTOWN FLOOD REDUCTION AND STORMWATER INFILTR-ATION
Item
Description
Qty
Unit
Unit Price
Amount
16
Install Shoring for Underground Storage
7,865
SF
$
$
Reservoir*
50 00
393,250 00
17
Install 8" 5DR35 PVC Pipe Incl.
151
LF
$
$
Trenching, Removals, Bedding, and
355.00
55,115.00
Backfill
18
Install 18" DIP (CL.250) Incl. Trenching,
47
LF
$
S
Removals, Bedding, [Backfill, and
535.00
25,145.00
Pavement Re lacement
19
Install 18" RCP (2500-D) Incl. Trenching,
367
LF
$
S
Removals, Bedding, Backfill, and
450.00
1 G8 820 00
Pavement Replacement
20
Install 21" RCP (2000-D) Incl. Trenching,
IO
LF
$
S
Removals, Bedding, Backfill, and
490.00
4,900.00
Pavement Re lacement
21
Install 24" RCP (2000-D) Incl. Trenching,
102
LF
$
S
Removals, Bedding, Backfill, and
520,00
53,040.00
Pavement Replacement
22
Install 30" RCP (2000-D) Incl. Trenching,
310
LF
$
$
Removals, Bedding, Back Fill, and
590.00
1$2,900.00
Pavement Replacement
23
Install 36" RCP (2000-D) Incl. Trenching,
295
LF
$
$
Removals, Bedding, Backfill, and
675.00
199,125,00
Pavement Replacement
24
Install 39" RCP (2000-D) Incl. Trenching,
10
LF
$
$
Removals, Bedding, Backfill, and.
540.00
5,400.00
Pavement Replacement
25
Construct Concrete Collar
8
EA
$
3,000.00
$
24,000_00
26
Construct Junction Structure Per SPPWC
t
EA
$
$
Sid. Plan 331-3
5.000.00
5,000.00
27
Construct Type A Junction Chamber Incl.
5
EA
$
$
Excavation, Removals, Backfill, and
22 500 00
112,500.00
Pavement Replacement
28
Construct Type B Junction Chamber Incl.
I
EA
$
$
Excavation, Removals, Backfill, and
25.000.00
25,000.00
Pavement Replacement
29
Construct Low Flow Diversion Vault Incl.
1
EA
$
S
Excavation, Removals, Backfill, and
21,500.00
21,500.00
Pavement Replacement
30
Construct Low Flow Diversion lvll-1 Incl.
I
EA
$
S
Excavation, Removals, Backfill, and
22,500.00
22.500.00
Pavement Replacement
31
Install 18"X 13" Grated Catch Basin with
2
EA
S
S
Catch Basin Filter Insert (Qldcastle
7,500.00
15,000.00
FloGard or approved equal) Incl.
Excavation, Removals, and Backfill
32
Install 18"xl8" Grated Catch Basin Air
2
EA
$
S
Vent with Catch Basin Filter Insert
7,500.00
15,000.00
(01dcastle F1oGard or approved equal)
Incl. Incl. Excavation, Removals, and
Backfill
P-2 of P- 19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6622
DOWNTOWN FLOOD REDUCTION AND STORMWATER INFILTRATION
Item
Description
Qty
Unit
Unit Price
Amount
33
Install Manual Spill Isolation Valve Incl.
I
EA
S
S
Valve Box and Signage
20,000.00
20,000.DD
34
Install Pipe Connection to Storage
I
EA
$ 1 Q,aa0.ao
$ 10,000.00
Reservoir Incl. Energy Dissipator
35
Remove and Reconstruct Type C Catch
I
EA
$
S
Basin (W=14') Inci. Excavation,
31,000.00
31,000.00
Removals, and Backfill
36
Remove and Reconstruct Type C Catch
2
EA
$
S
Basin (W=21') Incl. Excavation,
!
37,500.00
75,000,00
Removals, and Backfill
37
Install Underground Storage Reservoir
l
LS
$
1,150,000.00
$
1,150,000.00
Incl. Access Frames, Covers, and Shafts
38
Install Cartridge Media Filter (Kraken KF-
l
FA
$
$
10-16 or approved equal) Incl. Excavation,
320,000.00
320,000.00
Removals, and Backfill
39
InstaIl Drywell {Torrent Maxwell or
] 3
EA
$
53,00Q.QD
$
889,000.0D
Approved Equal}
40
Construct Asphalt Concrete Pavement
607
TONS
$ 150,00
$ 91,050.00
41
Construct Abgregate Base (Class 2)
582
CY
$ 100 00
$ 58,200M
42
Construct PCC Driveway Approach
566
SF
$ 30.00
$ 16,980,00
(Commercial = 8")
43
Construct 8" Thick PCC Cross Gutter
108
SF
$ 30.00
$ 3,240.00
44
Construct 4" Thick PCC Sidewalk
656
SF
$ 20.00
$ 13,120.00
45
Construct PCC Curb
981
LF
$ 50 00
$
49,050.00
46
Construct PCC Curb & Gutter
177
LF
$ 100,00
$ 17,700.00
47
Install Detectable Warning Surface
50
SF
$ 100.00
S 5,000.00
48
Install Traffic Signal Loop Detector (Type
2
EA
$ 5,000.00
$ 10,000 00
D Loop)
49
Install Traffic Signal Loop Detector (Type
2
EA
$
5,000.QQ
$ 1 Q,QQO.OD
E Loop)
50
Signing and Striping
I
LS
$ 15,000.00
$ 15,Q00.0D
51
Prop 68 Funding Acknowledgement Sign
1
EA
$ 5 QQQ 00
$ 5 000 Q0
52
Interpretive Signage
l
LS
$
7,500.00
$
7,500.00
53
Construction Permit
]
LS
$16,500
$16,500
54
1 Gallon Shrub (Furnish Material Only)"*
209
EA
$ 15.00
$ 3,135.00
P-3 of P-19
W11h21:1a19111%Nicoll
CITY 4F SANTA ANA
PROPOSAL
PROJECT NO.: 22-6622
DOWNTOWN FLOOD REDUCTION AND STORMWATER INFILTRATION
Item
Description
Qty
Unit
[snit Price
Amount
55
5 Gallon Shrub (Furnish Material Only)**
7
EA
$ 35.00
S 245.00
56
15 Gallon Shrub (Furnish Material
2
EA
$
110.00
$
220.00
Only)**
57
15 Gallon Tree Including Tree Staking and
2
EA
$
S
Protection
250.00
500.00
58
Remove, Temporarily Box, and Reinstall
3
EA
$
S
Palm Tree
7,500.D0
22,500.00
59
OCCC Planting"
I
LS
$2, l 46
$2,146
60
Install 2.5" Deep Decomposed Granite
1,780
SF
$
$
Mulch ('California Gold') or Match
5.00
8,900.00
Existing
61
Install 4" Deep Decomposed Granite Path
95
SF
$
0.00
$
950.00
('California Gold') or Match Existing
62
Soil Conditioning & Topsoil Placement
1,730
SF
$ 3.00
$
5,340.00
63
Fertilizer Tablets 21 Gram
i
LS
$ 250.00
$ 250.00
64
Non -woven Geotextile Fabric Including
1,780
SF
S 2 85
$ 5,a73.aa
Pins
65
Relocate Landscape Boulder
2
EA
$ 300.00
$ 60000
66
Install TxTxT Landscape Boulder
5
EA
$ 400.00
$
z;oaD.aO
67
Tnstail TxTxT Landscape Boulder
4
EA
$
350.00
$
1,40a.a0
68
Plant Establishment (90 Days)
1
LS
$ 3,500.00
S 3,500.00
69
Protection and Modification of Drip
I
LS
S 8 0017 00
$ 18 000 OD
Tubing Irrigation System
Bid Alternates
1
Remove and Replace 8" Thick Colored
1,070
SF
$ 40 Q0
$ 42,800.00
Concrete Pavement In Kind
2
Adjust Water Valve Frame and Cover to
13
EA
$ 1,000.00
$ 13,000.00
Grade
3
Adjust Sanitary Sewer Maintenance Hole
2
EA
$ 1,000.00
$ 2,400.00
Frame and Cover to Grade
4
2" Cold Mill
4,200
SY
$
5.00
$
21,000.00
5
2" ARHM Overlay
473
TONS
S 200.00
$ 94,600.00
6
Si-ning and Stripinb
I
L5
S 25,000.00
25,000.00
{ Replaces Bid Item 54}
Bid lien] 50 (subtract)
-S
15,000.00
P-4 of P-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6622
DOWNTOWN FLOOD REDUCTION AND STORMWATER INFILTRATION
TOTAL BASE BID S 4,458,844.00
TOTAL ADD ALTERNATE BID S `€83,800.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (If any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "251/o" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
Labor for planting all 1-gallon, 5-gallon, and 15-gallon Shrubs, Ornamental Grasses, and
Ground Covers as shown per plan shall be performed by the OCCC. The Contactor shall be
responsible for planting all Trees as shown per plan. For the landscaping bid items, only the
price to furnish the materials for the installation of the 1-gallon, 5-gallon, and 15-gallon
planting shall be included. The labor for the OCCC installation work for 1-, 5-, and 15-galIon
plants is included in Bid Item 59.
f This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within 200 working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $4,800 per calendar day_
Name ofFirm GMZ Engineering, Inc.
Signature of BIDDER
Title Ghazi Mubarak - President. Vice President, Secretary, Treasurer
(If an individual, so state. If firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If corporation, state legal name ofcorporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-5 of P-19
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 22-6622
DOWNTOWN FLOOD REDUCTION AND STORMWATER INFILTRATION
This CONSTRUCTION CONTRACT is made and entered into this 21" day of March, 2023 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and existing
under the Constitution and laws of the State of California (hereinafter "CITY'), and GMZ Engineering,
Inc. (hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the Downtown Flood. Reduction and Stormwater Infiltration Project
(hereinafter referred to as the "WORD OF IMPROVEMENT") identified in and in accordance with
the Contract Documents prepared by the City's Public Works Agency and approved by the City
Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF
IMPROVEMENT the sum total amount not to exceed Four Million, Six Hundred Forty -Two
Thousand, Six Hundred Forty -Four Dollars and No Cents ($4,642,644.00), as set forth and identified
in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A"
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of work
will correspond therewith, but reserves the right to increase or decrease the amount of any class or
portion of the work or to omit portions of the work as may be deemed necessary or advisable.
Page 1 of 3
4. CONTRACTOR agrees to complete the WORD OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORD
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
5. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at: http:llwww.santa-ana.orglpwa/documents/CWA.pdf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
S. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars (S500,000), the Warranty Bond amount shall be the greaterof Ton Thousand Dollars ($10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. fNDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemni tee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By:42'g�
JOHN FUNK
Chief Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
GMZ Engineering, Inc.
NAME:TITLE:
d "
Page
Page 3 of 3
EXHIBIT A
CITY OF ,S TA ANA
PROPOSAL
PROJECT NO.: 22-662-1
DOWNTOWN FLOOD REDUCTION AND STORMWATER INFILTRATION
DID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: GMZ Engineering, Inc.
REQUIREMENT:
The undersigned bidder declares that Lhey have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and lierehy proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lurnp sum(s) set forth in the
following schedule:
Item
Description
Qt}
Unit
Unit Price
Amount
I
Remove Ballard
5
EA
$ 250.00
$ 1,250.00
2
Remove, Salvage/Replace. and Reinstall
54
EA
$ iD0.00
$ 5,400.00
Wheel Stop
3
Remove, Salvage, and Reinstall Parking
26
EA
$ 100.00
$ 2'000'00
Meter Post
4
Remove, Salvage, and Reinstall Swing
1
EA
$
$
Gate
?,500.00
2,500,DO
5
I Remove, Salvage, and Reinstall Waste
1
EA
S 250.00
$ 250.00
Receptacle
G
j Remove, Salvage/Rcpiace, and Reinstall
4
EA
� S
1,500.00
$ 5 p04.00
Elrcaic Pullbox
7
Remove. Salvage, and ItclastaII LighL Pole
2
CA
S
S
10,000.00
20,000.00
8
Remove. Salvage, and Reinstall Electric
1
EA
S
S
Vehicle Chareina Station
10,000.00
10,000.00
9
Remove, Salvage, and Reinstall
1
Eel
$
S
Emergency Phone Pole
10,000.0010,000.00
10
Remove and Replacc Electrical Conduit
1
L5
$
25,000.00
S
25,000.00
and Wiring In Kind
t ]
Remove Storm Drain Maintenance Hole
3
E,A
S 5.000,00
S 15,000.00
12
Clearing and Grubbing
1,730
SF
S
5.00
S
8,9001)0
13
Remove Tree
2
EA
S 1,500.00
i $ 3,000.00
14
Unclassilied Exc a e, ation and Export
7,59U
Cy
S 85.00
$ 220,150,00
fiParkiil� Lot]*
15
Unclassified Excavation. Stockpile, land
4,566
Cy
$ 25.00
S 112,500.00
Reuse as Backfill (Parking Lot)*
P-1 ofP-l9
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6622
DOWNTOWN FLOOD REDUCT[ON AND STORMWATI R INFILTRATION
Item
Description
Qty
Chit
Unit Price
Amount
15
Install Shoring for Underground Storage
7,865
5F
5
Reservoir*
uO.OD
3'93,250.00
17
Install 8" 5DR35 PVC Pipe Inc[.
151
LF
$
5
Trenching, Renick,als, Bedding, and
355.00
65,115.00
Backfill
18
Instal 18" DIP [CL250] Incl. Trenching,
47
LF
S
$
Removals, Bedding, Backfill, and
535.00
26,145.00
Pavement Re luuemcnt
19
Install 18" RCP (2500-D) Incl. Trenching,
367
LF
S
S
Removals, Bedding, Backfill, and
460.00
168,820.00
Pavement Replacement
20
Install 21" RCP (2000-13) Inal, Trenching,
10
LF
S
S
Removals, Bedding, Back -fill, and
490.00
4,900.00
Pavement Replacement
21
Install 24" RCP (2000-D) Incl, Trenching.
102
LF
S
S
Removals, Bedding, Backfill, and
520.00
5.3,040.00
Pavement Rc lacement
22
Install 30" RCP (2000-D) Tncl. Trenching,
310
LF
$
$
Removals, Bedding, Backfill, and
590.00
182,900 00
Pavement R❑ lacement
23
Install 3G" RCP (2000-D) Incl. Trenching,
295
LF
$
$
Removals, Bedding, Backfill, and
675.0C
'199,125,00
Pavement Replacement
24
Install 39" RCP (2000-D)1ncl. Trenching,
10
LF
$
$
Removals, Bedding, BackGll, and
540,00
5,400,t70
Pavement Replacement
25
Construct Concrete Collar
8
EA
$
3.afa0.ao
$
24.000.I)0
26
Construct Junction Structure Per SPPWC
l
EA
$
$
Std. Plan 331-3
5,000•00
5,000.00
27
Construct Type A Junction Chamber IncL
5
EA
S
$
Excavation, Removals, Backfill, and
22 50C C0
112.500.00
Pavement Replacement
28
Construct Type B Junction Chamber Incl.
I
EA
$
S
Excavation, Removals, Backfill, and
25,000_00
25,000.00
Pavement Replacement
29
Construct Low Flow Diversion Vault Inc].
1
EA
S
S
Excavation. Removals, Backfill. and
21,500.90
21 500.00
Pavement Replacement
30
Construct Low Flow Diversion iv1H Incl.
1
EA
$
S
Excavation. Removals. Backfill, and
�
22, 500.00
22, 500.00
Pavement Replacement
31
Install 15"X 18" Grated Catch Basin n ith
2
EA
S
S
Catch Basin Filler Insert (DEdcastle
500 00
15 000.00
FloGard or approved equal) Incl,
Excavatian. Removals, and Backfill
32
Install 18"x18" Grated Catch Basin :fir
?
EA
S
S
Vent with Catch Basin Filter Insert
(dldcastle FloGard or approved equal)
�.500.00
15,000.00
Incl. Incl. Excavation, Removals, and
Backfill
P-2 o l' P-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-5622
DOWNTOWN FLOOD REDUCTION AND STORM WATER INFILTRATION
Item
Description
Qty
Unit
Unit Price
Amount
33
Install Manual Spill Isolation Valve Incl.
1
EA
5
S
Valve Box and 5ignage
20,0(70.00
20,000.00
34
[nstall Pipe Connection to Storage
i
Eel
5 10,000.00
S 10,000.00
Reservoir Incl. Erergy Dissipator
35
Reniove and Reconstruct Type C Catch
I
EA
S
S
Basin (W=14) Inc[. Excavation,
31,000.00
31,000.00
Removals, and Backfill
36
Reniove and Reconstruct Type C Catch
2
EA
S
S
Basin (W=21) Incl. Excavation,
37 500.00
75,000.00
Removals, and Backfill
37
lnsta[l Uriderground Storage Reservoir
I
LS
S f50,gQ0 00
Incl. Access Frames, Covers, and Shafts
,150,000.00
38
Install C3r1ridgc Media Filter (Kraken KF-
[
EA
S
S
10-1 G or approved equal) Incl. Excavation,
320.000.00
320,000.00
Removals, and Backfill
39
1nsiall Drywell (Torrent Maxwell or
[3
EA
S
53,fl00.00
$
689,000.0C
Approved Equal)
40
Construct Asphalt Concrete Pavement
607
TONS
$ 150 d0
S 91,050,00
41
Construct Aggregate Base (Class 7)
582
CY
S 100.00
5s,2ao.00
42
Construct PCC Driveway Approach
566
5F
S
3D.DD
S
s,9�a.aa
{Commercial = 8" j
=43
Construcl 8" Thick PCC Cross Civaer
108
SF
S 30.00
S 3,240.00
44
Construct 4" Thick PCC Sidewalk
656
SF
S 20.00
S 13 120.00
45
Construct PCC Curb
981
LF
S 50.00
$
49,050.00
46
Construcl PCC Curb & Gutter
177
LF
$
100.00
17,700.00
47
Install Detectablc Warring Surface
50
SF
$ 100.00
$ 5,000.00
48
Install TraMic Signal Loop Detector (Type
?
I -EA
$ 5,000.00
S 10,000.00
D Loop)
49
1astal1 Trali'ic Signal Loop Detector (Type
2
EA
$ 5,000.00
$ 10.000.00
E Loop)
50
Signing- and Striping
1
LS
$ .
I5,000.00
$
15,000.00
51
Prop 58 Funding Acknowledgement Sign
I
EA
$ 5.000.00
$ 5,000.00
52
lnterpretive Signage
I
LS
S
7.500.00
�
7,500.00
53
Construction Pcrmit
I
I_S
$16,500
$16,500
54
1 Gallon Shrub (Furnish Material Only)**
209
EA
S 15.00
$ 3,135.00
P-3 of P-19
ADDENDUM NO. -I
CITY OF SAN'TA A NA
PROPOSAL
PROJECT NO.: 22-6622
DOWNTOWN FLOOD REDUCTION AND STORMWATER INFILTRATION
Item
Description
Qty
Unit
unit Price
Amount
55
a Gallon Shrub (Fumisli Material Only)**
7
EA
S 35.00
S 245,00
56
15 Gallon Shrub (Furnish Material
2
EA
$ 110.00
S 220.00
Only)*"
57
15 Gallon Tree Including7ree Staking and
2
EA
$
S
Protection
250.00
500.00
58
Rcmove, Temporarily Box, and Reinstall
3
EA
$
S
Palm Tree
7,500.00
22,500.00
39
❑CCC Planting"*
!
LS
$2,146
S2,146
60
install 2.5" Deep Decomposed Granite
1,780
SF
$
S
Mulch ('California Gold') or Match
5.00
8,9C0.00
Existing
61
Install 4" Deep Decomposed Granite Path
95
SF
$ 0 00
5 950.00
('California Gold'j or Match Existing
62
Soil Conditioning & Topsail Placement
1,730
SF
$ 3.00
$
5,340.00
63
F: rtilixerTablets 21 Gram
1
LS
S 250.00
$ 250.00
64
Non -woven Geotextile Fabric Including
1,780
SF
$ 2.85
S 5,073.00
Pins
65
Relocate Landscape Boulder
?
EA
S 300 00
S 6a0 as
66
Install 3'x3'x3' Landscape Boulder
5
EA
$ 400.00
S
2,000.170
67
Install 2'x2'x2' Landscape Boulder
4
EA
$
350.00
S
1,400.00
68
Plant Establishment (90 Days)
1
LS
$ 3,500.00
S 3,500.00
69
Protection and Modification of Drip
1
LS
$
1$,000.00
S
18.000.00
Tubing Irrigation System
Bid Alternates
1
Remove and Replace 8" Thick Colored
1,07D
SF
$ 40.00
$ 42,800.00
Concrete Pavement in Vinci
Adjust Water Valve Frame and Cover to
13
EA
$ 1,000.00
$ 13.000.00
Grade
3
Adjust Sanitary Sewer Maintenance Role
2
EA
$ 1,000.00
$ 2,400.00
Frame and Caper to Grade
4
2"' Cold Mill
4,200
SY
$
5.00
$
21,000.00
5
2" AIMM Overlay
473
'TOWS
S
200.00
$
94,600.oa
G
Signing, and Striping
I
LS
S 25,000.oa
S 25.000.00
I Rep1;lc:cs Bit] lwni 501
Bid Ilem -50 (subtravl)
A 5,�1nn O0�7lJ.00
P-4 of P-19
CITY Or SANTA ANA
PROPOSAL
PROJECT NO.: 22-6627
DOWNTOWN FLOOD REDUCTION AND STORMWnTER INFILTRATION
TOTAL BASE Bill s 4,458,844.00
TOTAL AID❑ ALTE, RNATE BID S 183,800.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to wward the Base Bid, and any, al1, or none of the add -alternate bid items (if any).
The gLiantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the `'25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
ZP
right to increase or decrease the quantity of this item accordingly.
Labor for planting all I -gallon, 5-gallon, and 15-gallon Shrubs, Ornamentaf Grasses, and
Ground Covers as shown per plan shall be performed by the OCCC. The Contactor shall be
responsible for planting all Trees as shown per plan. For the landscaping bid items, only the
price to furnish the materials for the installation of the 1-gallon, 5-gallon, and 15-gallon
planting shall be included. The labor for the OCCC installation work for 1-, 5-, and 15-gallon
plants is included in Bid Item 59.
This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLLTION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to cornpletc talc Work for the total base bid amount
shown above, within 200 working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $4,800 per calendar day.
.Name of Firm GViZ Engineering, Inc.
Signature of BIDDER�'�'
Title Ghazi iylubarak - President. Vice President. Secretary. Treasurer
(I f an individual, so state. I r a Firm ar co -partnership, state the firm name and give the names of
a I I individual co-partners composing the firm. I['a cnrporation, state legal name orcorparation.
and names of President, Secretary, Treasurer and Manager, thereof: j
P-5 of ?-19
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 22-6622: DOWNTOWN FLOOD REDUCTION
AND STORMWATER INFILTRATION PROJECT
Construction Contract
$4,642,644
Contract Administration, Inspection and Testing
$552,356
Contingencies
$445,000
TOTAL ESTIMATED CONSTRUCTION COSTS
$5,640,000
PROJECT TITLE:
Downtown Flood Reduction &
Stormwater Infiltration Project
PROJECT CATEGORY:
Utility/Drainage/Lighting
Improvements
Storm Drain/Water Quality
LOCATION MAP A
N
AGENCY:
Public Works
CITY OF SANTA ANA FY 22/23CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Upgrade existing stormdrain infrastructure along 3rd Street,
installation of a subsurface stormwater infiltration system, and
redevelopment of a City -owned parking lot to include stormwater
Best Management Practices (BMPs), drought tolerant landscaping,
and interpretive signage.
PROJECT NEED:
The City experiences significant flooding during intense rain events,
particularly in the Downtown area. The multi -benefit project will help
alleviate flooding via the reconstruction and upgrade of the existing
stormdrain infrastructure along 3rd Street, and construction of a
subsurface infiltration system that will capture and infiltrate stormwater.
PROJECT COSTS FY 22/23 FY 23/24 FY 24125 FY 25/26 FY 26/27 FY 27/28 FY 28129
Construction 2,150,000 - - - - - -
Engineering -
Planning - -
TOTAL 2,150,000 - - - - -
SOURCE OF FUNDS FY 22/23 FY 23124 FY 24125 FY 25126 FY 26127 FY 27128 FY 28129
CNRA Urban Flood Protection 1,250,000 - - - - - -
FED CLEAN WATER 900,000
TOTAL 2,150,000 - - - -
DIVISION:
C/P Engineering
CONTACT:
Craig Foster, NPDES Manager
DATE:
28-Feb-2023