HomeMy WebLinkAboutItem 15 - Santa Ana Zoo Goat TrailPublic Works Agency www.santa-ana.org/pw Item # 15 City of Santa Ana 20 Civic Center Plaza, Santa Ana, CA 92701 Staff Report June 21, 2022 TOPIC: Santa Ana Zoo Goat Trail AGENDA TITLE Approve and Appropriation Adjustment and Award a Construction Contract to Harrison Building Inc., in the amount of $400,000 for the Santa Ana Zoo Goat Trail FY 2021-22 Project, with an Estimated Project Delivery Cost of $560,000 (Project No. 21-2744) (Non - General Fund) RECOMMENDED ACTION 1. Approve an appropriation adjustment to recognize $180,000 in donations from Friends of the Santa Ana Zoo into the PRCSA Fee & Donation, Gifts & Donations revenue account and appropriate the same amount into the PRCSA Fee & Donation, Improvements Other than Building expenditure account for the Santa Ana Zoo Goat Trail project. (Requires five affirmative votes) 2. Award a construction contract to Harrison Building Inc., the lowest responsible bidder, in accordance with the base bid in the amount of $400,000, for construction of the Santa Ana Zoo Goat Trail FY 2021-22, for the term beginning June 21, 2022 and ending upon project completion, and authorize the City Manager to execute the contract subject to non -substantive changes approved by the City Manager and the City Attorney. 3. Approve the Project Cost Analysis for a total estimated construction delivery cost of $560,000, which includes $400,000 for the construction contract, $80,000 for contract administration, inspection and testing, and $80,000 project contingency for unanticipated or unforeseen work. 4. Approve an amendment to the Fiscal Year 2021-22 Capital Improvement Program to include the Santa Ana Zoo Goat Trial project. DISCUSSION The scope of work for the Santa Ana Zoo Goat Trail FY 2021-22 project includes excavation, grading to improve accessibility, a freestanding steel goat trail structure, a new theme element at the goat interaction yard, expanded animal interaction yards, new and rehabilitated landscape at area of work, trees, irrigation, relocation of existing Award Construction Contract to Harrison Building, Inc. June 21, 2022 Page 2 signage, and replacement of existing and new storm drain basins to improve drainage (existing storm drain system to remain). The project design expands opportunities for goats to express natural behaviors via elevated structural elements that encourage and display their climbing skills; at the same time, it creates an immersive farm environment for human participants. Pathway and drainage improvements, area grading, and signage relocation will increase overall farm accessibility; expanded habitats will improve animal welfare; and new landscaping and irrigation will beautify the space. The Goat Trail project will contribute to the Zoo's revitalization and enhance the Zoo's ability to empower its community to save wildlife and wild spaces through fun, adventure, and learning. Public Outreach and Contractor Participation To provide an opportunity for local vendors to submit bids, the City notified a total of 27 regional vendors via PlanetBids, many of which are Santa Ana based. Three vendors requested bidding documents, and a total of three bids were received. Bids were not received from any Santa Ana contractors. As legally required, a Notice Inviting Bids was advertised in the Orange County Register newspaper on March 24 and March 31, of 2022. The project was also advertised in PlanetBids from March 22, 2022 through April 12, 2022. Bids were received electronically via PlanetBids on April 12, 2022. Bid Results Summary RANK BIDDER'S NAME LOCATION BASE BID 1 Harrison Building, Inc. Newport Beach $400,000 2 G.B. Cooke, Inc. Fullerton $721,531 3 C.S. Legacy Construction, Inc. Walnut $1,015,985 Three bids were received, and all were deemed responsive. Harrison Building Inc., submitted the lowest responsive base bid in the amount of $400,000 (Exhibit 2). As specified in the bid documents, the lowest bid shall be determined on the basis of the Base Bid. Based on the bid analysis and a contractor reference check, staff recommends awarding the construction contract to Harrison Building Inc. in the amount of the Base Bid, totaling $400,000 (Exhibit 3). In the past year, Harrison Building Inc. has performed fence installation work at two fire stations for the Building Maintenance Division and the Public Works Agency. Project Delivery To deliver a complete project, in addition to the construction contract, the estimated total project delivery cost includes construction administration, inspection, and testing, along Award Construction Contract to Harrison Building, Inc. June 21, 2022 Page 3 with an allowance for contingencies to account for unexpected or unforeseen conditions. Construction administration and inspection includes construction management; implementation of the City's Community Workforce Agreement requirements; inspection of the Contractor's work to ensure contract compliance, workmanship, and quality; and materials testing. As indicated in the Cost Analysis (Exhibit 4) and as summarized in the table below, the estimated total construction delivery cost of the project is $560,000.00. Project Item Total Construction Contract $400,000 Construction Administration, Inspection, Testing $80,000 Contingencies $80,000 TOTAL CONSTRUCTION DELIVERY COST $560,000 Approval of the amendment to the FY 2021-22 Capital Improvement Program (Exhibit 5) will officially incorporate this funding for the project into the program. ENVIRONMENTAL IMPACT In accordance with the California Environmental Quality Act, the recommended actions are exempt from further review. Categorical Exemption Environmental Review No. ER- 2022-31 was filed for the project. FISCAL IMPACT As indicated in the Cost Analysis, the estimated total construction delivery cost of the project is $560,000.00, which includes construction, contract administration, inspection, testing, and an authorized contingency. With the approval of the requested appropriation adjustment to recognize $180,000 in donations from Friends of the Santa Ana Zoo into the PRCSA Fee & Donation, Gifts & Donations revenue account (No. 02213002-57081) and appropriate the same amount into the PRCSA Fee & Donation, Improvements Other than Building expenditure account (No. 02213200-66220) to sufficiently complete the delivery of this project. The following table summarizes the funds budgeted (after the appropriation adjustment) and available for expenditure to deliver the construction of this project. Accounting Unit Fund Accounting Unit - Fiscal Year - Account No. Description Account No. Amount (Project No.) Description Existing Project Budget Cannabis PRCSA Youth 2021-22 01213020-66220 Public Benefit Services- $380,000 (21-2744) Fund Improvements Other Than building Award Construction Contract to Harrison Building, Inc. June 21, 2022 Page 4 Accounting Unit Fund Accounting Unit - Fiscal Year - Account No. Description Account No. Amount (Project No.) Description Appropriation Adjustment PRCSA Fees PRCSA Fees & 2021-22 02213200-66220 & Donations Donations- $180,000 (21-2744) Fund Improvements Other Than Building Total $560,000 EXHIBIT(S) 1. Location Map 2. Bid Proposal 3. Construction Contract 4. Cost Analysis 5. CIP Worksheet Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency and the Parks, Recreation and Community Services Agency Approved By: Kristine Ridge, City Manager SANTA ANA LAA PUBLIC VMS AGENCY PROJECT 21-2744 SANTA ANA ZOO GOAT TRAIL i1 No PAGE 1 OF 1 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 21-2744 SANTA ANA ZOO GOAT TRAIL BID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: Harrison, Building, Inc. REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following schedule: Item Description Qty Unit Unit Price Amount 1 Santa Ana Zoo Goat Trail Project Manual 1 LS $375,000 $375,000 2 Tractor Element 1 LS $10,000 $ 10,000 3 Construction Permit 1 LS $15,000 $15,000 TOTAL BASE BID $400,000 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications. TIME FOR COMPLETION OF IMPROVEMENTS AND LIOUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work fbr the total base bid amount shown above, within number (100) working_ & s after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $820 per calendar day. P-6 of P-22 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 21-2744 SANTA ANA ZOO GOAT TRAIL Name of Firm Harrison Building, Inc. Signature of BIDDER Title CEO (If an individual, so state. If a firm or co -partnership, state the firm name and give the names of all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-7 of P-22 CITY OF SANTA ANA CONSTRUCTION CONTRACT AGREEMENT PROJECT NO.: 21-2744 Santa Ana Zoo Goat Trail This CONSTRUCTION CONTRACT is made and entered into this 21 st day of June, 2022 by and between the City of Santa Ana, California, a charter city and municipal corporation organized and existing under the Constitution and laws of the State of California (hereinafter "CITY"), and Harrison, Building, Inc., (hereinafter "CONTRACTOR"). WITNESSETH: The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows: 1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction of the City Engineer of the CITY, the Santa Ana Zoo Goat Trail (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contracts Documents prepared by the City's Public Works Agency and approved by the City Council. 2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard Specifications for Public Works Construction and which include the following: • Notice Inviting Bids • Information to Bidders • Bid Proposal • Bid Bond • Contract Form • Contract Bonds • General Provisions • Special Provisions • Technical Provisions and Project Plans • Community Workforce Agreement • Appendices In case of conflict between the Contract Documents, the precedence of documents shall be as established in the Standard Specifications for Public Works Construction. 3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF IMPROVEMENT the sum total amount not to exceed Four Hundred Thousand and No Cents ($400,000), as set forth and identified in the BID PROPOSAL, which is attached hereto and incorporated herein as "Exhibit A." The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate quantities only, and the City does not expressly or by implication agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work or to omit portions of the work as may be deemed necessary or advisable. 1 of 3 CITY OF SANTA ANA CONSTRUCTION CONTRACT AGREEMENT PROJECT NO.: 21-2744 Santa Ana Zoo Goat Trail 4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including commencing construction within the timeframe therein specified after issuance of a Notice to Proceed. 5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for such work as set forth in the wage determinations for this work in accordance with applicable State and Federal law. 6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement (CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website at: htt2://www.santa-ana.org/pwa/documents/CWA.pdf 7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY, one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%) of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment Bond). This Contract shall not become effective until such bonds are supplied to and approved by the CITY. 8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price. 9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY. 10. INDEMNIFICATION. To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend, indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents, employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"), through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs, damages or losses, including reasonable costs and attorney's fees, for injury, including death to any person or damage to any property, arising directly or indirectly from, or in any manner relating to, any of the following: (i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its Subcontractors of any lower tier; (ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, 2 of 3 CITY OF SANTA ANA CONSTRUCTION CONTRACT AGREEMENT PROJECT NO.: 21-2744 Santa Ana Zoo Goat Trail of any of the obligations under the Contract Documents; (iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either on the project site or on other properties; (iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower tier, for Work of Improvement performed on or off the project site; and (v) Any personal injury, property damage or economic loss to third persons related to and arising from the performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, of the Work of Improvement. (vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all subcontract documents issued by CONTRACTOR. Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in favor of CONTRACTOR against CITY or any other Indemnitee. IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and year first above written. ATTEST: DAISY GOMEZ Clerk of the Council APPROVED AS TO FORM: SONIA R. CARVALHO City Attorney JOHN FUNK Assistant City Attorney RECOMMENDED FOR APPROVAL: NABIL SABA, PE Executive Director Public Works Agency CITY OF SANTA ANA KRISTINE RIDGE City Manager CONTRACTOR Company: Harrison, Building, Inc. NAME: PATRICK AUDENIS Title: CEO 3 of 3 EXHIBIT CITY OF SANTA ANA PROPOSAL PROJECT NO.: 21-2744 SANTA ANA ZOO GOAT TRAIL BID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: Harrison, Building, Inc. REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following schedule: Item Description Qty Unit Unit Price Amount 1 Santa Ana Zoo Goat Trail Project Manual 1 LS $375,000 $375,000 2 Tractor Element 1 LS $10,000 $ 10,000 3 Construction Permit 1 LS $15,000 $15,000 TOTAL BASE BID $400,000 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications. TIME FOR COMPLETION OF IMPROVEMENTS AND LIOUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within number (100) working_ & s after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $820 per calendar day. P-6 of P-22 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 21-2744 SANTA ANA ZOO GOAT TRAIL Name of Firm Harrison Building, Inc. Signature of BIDDER Title CEO (If an individual, so state. If a firm or co -partnership, state the firm name and give the names of all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-7 of P-22 EXHIBIT 4 COST ANALYSIS CONSTRUCTION OF PROJECT NO. 21-2744: Santa Ana Zoo Goat Trail Construction Contract $ 400,000.00 Contract Administration, Inspection and Testing $ 80,000.00 Contingencies $ 80,000.00 TOTAL ESTIMATED CONSTRUCTION COSTS $ 560,000.00 PROJECT TITLE: Santa Ana Zoo Goat Trail PROJECT CATEGORY: City & Park Facility Improvements Zoo Facility LOCATION MAP N 2 CITY OF SANTA ANA FY21/22CIP CAPITAL IMPROVEMENT PROJECT WORKSHEET PROJECT DESCRIPTION: The scope of work involves excavation, grading to improve accessibility, freestanding steel goat trail structure, new theme element at goat interaction yard, expanded animal interaction yards, new and rehabilitated landscape at area of work, trees, irrigation, relocation of existing signage, and replacement of existing and new storm drain basins to improve drainage (existing storm drain system to remain). PROJECT NEED: The Crean Family Farm was opened in 2004 to share Orange County's agricultural heritage and a sensory experience of farm animal care. The Goat Trail project will align that goal with the zoo's values and mission by transforming the current visitor goat interaction yard (which keeps people to one side of a fence and farm animals on the other), and connecting people up close with animals in an experiential habitat. Direct contact with animals builds empathy for living things, provides a unique educational experience, and encourages close observation and investigation of the natural world. PROJECT COSTS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 Construction 560,000 - - - - - - TOTAL 560,000 - - - - - - SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 380,000 - - - - - - PRCSA F&D 180,000 TOTAL 560,000 - - - - - - AGENCY: DIVISION: CONTACT: DATE: Parks, Rec. & Community Services C/P Engineering Sean Thomas, Senior Civil Engineer 09-May-2022