HomeMy WebLinkAboutItem 15 - Local Street Preventative Maintenance FY 2021-22Public Works Agency
www.santa-ana.org/pw
Item # 15
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
May 17, 2022
TOPIC: Local Street Preventative Maintenance FY 2021-22
AGENDA TITLE
Award a Construction Contract to All American Asphalt in the Amount of $2,109,832 for
the Local Street Preventative Maintenance FY 2021-22 Project with an Estimated Project
Delivery Cost of $2,778,000 (Project No. 22-6907) (Non -General Fund)
RECOMMENDED ACTION
1. Award a construction contract to All American Asphalt, the lowest responsible bidder,
in accordance with the base bid in the amount of $2,109,832, for construction of the
Local Street Preventative Maintenance FY 2021-22, for the term beginning May 17,
2022 and ending upon project completion, and authorize the City Manager to execute
the contract, subject to non -substantive changes approved by the City Manager and
the City Attorney.
2. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$2,778,000, which includes $2,109,832 for the construction contract, $316,500 for
contract administration, inspection and testing, and a $351,668 project contingency
for unanticipated or unforeseen work.
DISCUSSION
The City's Pavement Management Program has been developed to identify the
preventive maintenance requirements for the City's street network. The local street
segments (Exhibit 1) recommended for the Fiscal Year 2021-22 Local Street Preventative
Maintenance Capital Improvement Project have been identified as high priority for slurry
seal. The recommended work consists of localized replacement of asphalt concrete
pavement, slurry seal resurfacing, crack sealing, striping, and signage. The
improvements also include replacement of damaged concrete curbs, gutters, sidewalks,
and curb ramps. Once completed, these improvements will improve the City's overall
pavement condition, enhance the visual appearance of the street, upgrade ride quality,
and support compliance with Americans with Disability Act standards.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, the City notified a total of
837 regional vendors via PlanetBids, many of which are Santa Ana based. Four vendors
Award Construction Contract to All American Asphalt
May 17, 2022
Page 2
requested bidding documents, and a total of four bids were received. No bids were
received from Santa Ana contractors.
As legally required, a Notice Inviting Bids was advertised in the Orange County Register
newspaper on March 7 and March 14, of 2022. The project was also advertised in
PlanetBids from March 2, 2022 through March 24, 2022. Bids were received
electronically via PlanetBids on March 24, 2022.
Bid Results Summ
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
All American Asphalt
Corona
$2,109,832
2
EBS General Engineering Inc.
Corona
$2,435,088
3
R.J. Noble Company
Orange
$2,487,280
4
Excel Paving Co
Long Beach
$2,844,500
A total of four bids were received, and all were deemed responsive. All American Asphalt
submitted the lowest responsive base bid in the amount of $2,109,832 (Exhibit 2). As
specified in the bid documents, the lowest bid shall be determined on the basis of the
Base Bid. Based on the bid analysis and a contractor's reference check, staff
recommends awarding the construction contract to All American Asphalt, in the amount
of the base bid totaling $2,109,832 (Exhibit 3). All American Asphalt has performed the
following work in the City of Santa Ana within the past 5 years: Flower Street
Rehabilitation (Project No. 21-6976), Residential Street Repair Program FY 2019/20
(Project No. 20-7533), and Local Street Preventative Maintenance FY 2019-20 (Project
No. 20-6907).
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes construction administration, inspection, and testing, along
with an allowance for contingencies to account for unexpected or unforeseen conditions.
Construction administration and inspection includes the following: construction
management; implementation of the City's Community Workforce Agreement
requirements; inspection of the contractor's work to ensure contract compliance,
workmanship, and quality; and materials testing. As indicated in the Cost Analysis
(Exhibit 4) and as summarized in the table below, the estimated total construction delivery
cost of the project is $2,778,000.
Project Item
Total
Construction Contract
$2,109,832
Construction Administration, Inspection, Testing
$316,500
Award Construction Contract to All American Asphalt
May 17, 2022
Page 3
Project Item
Total
Contingencies
$351,668
TOTAL CONSTRUCTION DELIVERY COST
$2,778,000
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions
are exempt from further review. Categorical Exemption Environmental Review No. ER-
2022-17 was filed for the project.
FISCAL IMPACT
As indicated in the Cost Analysis, the estimated total construction delivery cost of the
project is $2,778,000, which includes construction, contract administration, inspection,
testing, and an authorized contingency.
The following table summarizes the funds budgeted and available for expenditure to
deliver construction of this project.
Fiscal
Accounting Unit -
Fund
Accounting Unit -Account
Year
Account No.
Description
No. Description
Amount
(Project No.)
03217662-66220
Measure M-
Measure M2 Local
2021-22
(22-6907)
Street
Fairshare, Improvements
$2,778,000
Construction
Other Than Building
Total
$2,778,000
EXHIBIT(S)
1. Location Map
2. Bid Proposal
3. Construction Contract
4. Cost Analysis
Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency
Approved By: Kristine Ridge, City Manager
EXHIBIT 1
0
,. IUrrr' �iesl l and ;Zack beG l gm
d I I i : ^I •I Vl I I •iiA A,r�ha It Ptlbbar Hot Mr x
i
/ o�H oagryce \
SAi Project No. 22-6907 k
LOCAL STREET PREVENTATIVE x
MAINTENANCE FY21-22 WE
,
PUBLIC WORKS AGENCY
� I
EXHIBIT 2
CITY OF SANTA ANA ADDENDUM NO. ONE
PROPOSAL
PROJECT NO.: 22-6907
LOCAL STREET SLURRY SEAL FY 21-22
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation*
CY
400
$
$
200.00
80,000.00
2
Cold Mill (2")*
SF
448,000
$
$
0.20
89,600.00
3
Asphalt Rubber Hot Mix
TN
5,600
$
S
(ARHM)*
110.00
616,000.00
4
Crack Sealing
LS
1
$
$
44,000.00
44,000.00
5
Rubberized Emulsion
TN
1,100
$
$
Aggregate Slurry (REAS)
700.00
770,000.00
Type II*
6
PCC Sidewalk (4")*
SF
9,200
$
S
8.00
73,600.00
7
PCC Curb and Gutter (Type
LF
800
$
$
A-2-6)*
59.00
47,200.00
8
PCC Cross Gutter*
SF
3,000
$
$
19.00
57 000.00
9
PCC Curb Ramp*
SF
12,300
$
S
13.00
159,900.00
10
PCC Driveway Approach
SF
700
$
$
(T=6")*
11.50
8,050.00
11
Root Shave*
EA
33
$
S
485.00
16,005.00
12
Adjust Sewer and Drainage
EA
36
$
S
Manhole Frame & Cover to
Finished Grade
885.00
31,860.00
13
Adjust Water Valve Frame
EA
62
$
$
and Cover to Finished Grade
785.00
48,670.00
P-1 of P-17
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 22-6907
LOCAL STREET SLURRY SEAL FY 21-22
Item
Description
Qty
Unit
Unit Price
Amount
14
Adjust Survey Monument to
EA
5
$
$
Finished Grade
785.00
3,925.00
15
Protection of Surface Utility
LS
1
$
$
Frames and Covers
1,040.00
1,040.00
16
Project Advertisement Sign
EA
2
$
$
3,141.00
6,282.00
17
Remove existing striping,
LS
1
$
$
pavement legends, and
markers
15,800.00
15,800.00
18
Signing and Striping
LS
1
$
$
25,900.00
25,900.00
19
Construction Permit
LS
1
$15,000
$15,000
TOTAL BASE BID (Item 1-19) F$2,109,832.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIOUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within number (60) working days after the commencement date stated in the
Notice to Proceed. All slurry seal surfacing streets shall be completed by September 30, 2022.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $4,800 per calendar day.
Name of Firm All American Asphalt
Signature of BIDDER
Title Edward J. Carlson, Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-2 of P-17
EXHIBIT 3
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 22-6907
LOCAL STREET PREVENTATIVE MAINTENANCE FY21-22
This CONSTRUCTION CONTRACT is made and entered into this 17th day of May, 2022 by and between
the City of Santa Ana, California, a charter city and municipal corporation organized and existing under
the Constitution and laws of the State of California (hereinafter "CITY"), and All American Asphalt
(hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the Local Street Preventative Maintenance FY21-22 (hereinafter
referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contract
Documents prepared by the City's Public Works Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF
IMPROVEMENT the sum total amount not to exceed Two Million One Hundred Nine Thousand
Eight Hundred Thirty -Two Dollars and No Cents ($2,109,832.00), as set forth and identified in the
BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of work
will correspond therewith, but reserves the right to increase or decrease the amount of any class or
portion of the work or to omit portions of the work as may be deemed necessary or advisable.
rev. 09/01/2017 Page 1 of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at: http://www.santa-ana.org/12wa/documents/CWA.pdf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
DAISY GOMEZ
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By: � 9W T'f
JOHN FUNK
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
All American Asphalt
NAM : Edward J. Carlson
TITLE: Vice President
Page 3 of 3
CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT CIVIL CODE § 1189
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached. and not the truthfulness. accuracv. or validity of that document.
State of California
County of Riverside
on April 11, 2022 before me, Sarah Amanda Langley Notary Public
Date Here Insert name and Title of the Officer
personally appeared Edward J. Carlson
Name(s}of Signer(st
7
who proved to me on the basis of satisfactory evidence to be the
person(s) whose name(&) is/are subscribed to the within instrument
dh and acknowledged to me that he/she4hey executed the same in
*my
SARAH AMANDA LANGLEY his/her/heir authorized capacity(ies), and that by his/heF4heiNotary Public - California signature(&) on the instrument the person(&), or the entity upon behalf
Riverside County of which the erson s acted, executed the instrument.
ommission # 2337877 p ( ) Comm. Expires Nov 20, 2024
I certify under PENALTY OF PERJURY under the laws of the State of
California that the forgoing paragraph is true and correct.
WITNES hand and fficial seal.
Signatur
Place Notary Seal Above Signature of Notary Pull
OPTIONAL
Though the information below is not required by law, it may prove valuable to person relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document
Santa Ana Construction Contract
Document Date: 04/11 /2022
Signer(s) Other Than Named Above:
Capacity(im) Claimed by Signer(e)
Signer's Name: Edward J. Carlson
❑ Individual
X Corporate Officer — Title(s): Vice President
❑ Partner u ❑ Limited ❑ General
RiGHT THUMBPRINT
❑ Attorney in Fact OF
❑ Trustee Top of thumb here
❑ Other:
Signer is Representing:
Number of Pages: 3
Signer's Name: N/A
❑ Individual
❑ Corporate Officer — Title(s): N/A
❑ Partner C ❑ Limited ❑ General
❑ Attorney in Fact •
Top of thumb here
❑ Trustee
❑ Other: N/A
Signer is Representing:
EXHIBIT 4
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 22-6907: Local Street Preventative
Maintenance FY21-22
Construction Contract
$
2,109,832
Contract Administration, Inspection and Testing
$
316,500
Contingencies
$
351,668
TOTAL ESTIMATED CONSTRUCTION COSTS
I $
2,778,000