Loading...
HomeMy WebLinkAboutItem 16 - Lincoln Avenue Water and Sewer Main ImprovementsPublic Works Agency www.santa-ana.org/pw Item # 16 City of Santa Ana 20 Civic Center Plaza, Santa Ana, CA 92701 Staff Report April 19, 2022 TOPIC: Lincoln Avenue Water and Sewer Main Improvements AGENDA TITLE Approve Appropriation Adjustment, Budget Reallocation, and Award a Construction Contract to Big Ben, Inc. in the Amount of $1,453,765 for the Lincoln Avenue Water and Sewer Main Improvements Project, with an Estimated Project Delivery Cost of $2,000,000 (Project No. 22-6468 and 22-6620) (Non -General Fund) RECOMMENDED ACTION 1. Approve an appropriation adjustment to recognize $500,000 of prior -year fund balance in the Water Fund, Public Works Water Revenue, Prior Year Carryforward revenue account, and appropriate the same amount to the Acquisition & Construction, Water Utility Capital Projects, Water Capital Project expenditure account. (Requires five affirmative votes) 2. Award a construction contract to Big Ben, Inc., the lowest responsible bidder, in accordance with the base bid in the amount of $1,453,765, for construction of the Lincoln Water and Sewer Main Improvements Project, for the term beginning April 19, 2022 and ending upon project completion, and authorize the City Manager to execute the contract subject to non -substantive changes approved by the City Manager and the City Attorney. 3. Approve the Project Cost Analysis for a total estimated construction delivery cost of $2,000,000, which includes $1,453,765 for the construction contract, $218,000 for contract administration, inspection and testing, $100,000 for water engineering, and a $228,235 project contingency for unanticipated or unforeseen work. 4. Approve an amendment to the Fiscal Year 2021-22 Capital Improvement Program to include $500,000 in construction funds for the Lincoln Avenue Water and Sewer Improvements Project. Lincoln Avenue Water and Sewer Main Improvements April 19, 2022 Page 2 DISCUSSION The Public Works Agency's Water Resources Division staff monitors the condition of water main pipelines by assessing critical factors such as history of breaks, pipe size, alignment, location, and system redundancy to determine replacement priorities. The water main on Lincoln Avenue, as well as sewer laterals, have been identified for replacement (Exhibit 1). The improvements include a new polyvinyl chloride (PVC) water main, fire hydrants, water services, sewer laterals, appurtenances, asphalt concrete pavement, and traffic striping. Once completed, water service reliability and general service quality will improve significantly. In addition, the potential for disruption due to water main breaks will be substantially reduced. Public Outreach and Contractor Participation To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was advertised in the Orange County Register newspaper on February 26 and March 5, 2022. The project was also advertised on PlanetBids, and bids were received electronically via PlanetBids on March 17, 2022. The City notified a total of 647 regional vendors via PlanetBids, 21 of which are Santa Ana based. Fifty-eight vendors requested bidding documents. A total of four bids were received. However, no bids were received from Santa Ana contractors. Bid Results Summary RANK BIDDER'S NAME LOCATION BASE BID 1 Big Ben, Inc. Irvine $1,453,765 2 Excel Paving Co. Long Beach $1,674,170 3 DOJA INC. Ontario $2,100,000 4 Colich & Sons L.P. Gardena $2,654,475 All four bids were deemed responsive. Big Ben, Inc. submitted the lowest responsive base bid, in the amount of $1,453,765 (Exhibit 2). As specified in the bid documents, the lowest bid shall be determined on the basis of the Base Bid. Based on the bid analysis and a contractor's reference check, staff recommends awarding the construction contract to Big Ben, Inc. in the amount of the base bid totaling $1,453,765 (Exhibit 3). Big Ben, Inc. has completed the Centennial Park Neighborhood Water Main Improvements and the Baker -Glenwood Sewer Main Improvements projects in the City. Lincoln Avenue Water and Sewer Main Improvements April 19, 2022 Page 3 Project Delivery To deliver a complete project, in addition to the construction contract, the estimated total project delivery cost includes construction administration, inspection, and testing, along with an allowance for contingencies to account for unexpected or unforeseen conditions. Construction administration and inspection includes the following: construction management; implementation of the City's Community Workforce Agreement requirements; inspection of the Contractor's work to ensure contract compliance, workmanship, and quality; and materials testing. As indicated in the Cost Analysis (Exhibit 4) and as summarized in the table below, the estimated total construction delivery cost of the project is $2,000,000. Project Item Total Construction Contract $1,453,765 Construction Administration, Inspection, Testing $218,000 Contingencies $228,235 Water Engineering $100,000 TOTAL CONSTRUCTION DELIVERY COST $2,000,000 Approval of the amendment to the FY 2021-22 Capital Improvement Program (Exhibit 5) will officially incorporate this project into the program. ENVIRONMENTAL IMPACT In accordance with the California Environmental Quality Act, the recommended actions are exempt from further review. Categorical Exemption Environmental Review No. ER- 2021-79 was filed for the project. FISCAL IMPACT As indicated in the Cost Analysis, the estimated total construction delivery cost of the project is $2,000,000, which includes the construction contract, contract administration, inspection, testing, and project contingency. Approval of the requested appropriation adjustments will recognize sufficient funds to complete the funding to deliver the project (Exhibit 5). Recognize $500,000 from Water Fund, Public Works Water Revenue, Prior Year Carryforward revenue account (No. 06017002-50001) and appropriate the same amount to the Acquisition & Construction, Water Utility Capital Projects, Water Capital Project expenditure account (No. 06617647-66301) The following table summarizes the funds budgeted and available for expenditure to deliver construction of this project. Any remaining balances not expended at the end of the fiscal year will be carried forward for expenditure in the following fiscal year, if needed. Lincoln Avenue Water and April 19, 2022 Page 4 Sewer Main Improvements Fiscal Accounting Unit Fund Accounting Unit — Year — Account No. Description Account No. Amount Description Prior Authorized Funds 2021-22 06617647-66301 Acquisition & Water Utility Capital Projects, Water $800,000 (22-6468) Construction Capital Project Capital Recovery 2021-22 05417647-66220 Sanitary Sewer Charges, $700,000 (22-6620) Capital Improvements Other Than Building Appropriation Adjustments 2021-22 06617647-66301 Acquisition & Water Utility Capital Projects, Water $500,000 (22-6468) Construction Capital Project TOTAL: $2,000,000 EXHIBIT(S) 1. Location Map 2. Bid Proposal 3. Construction Contract 4. Cost Analysis 5. FY 2021-22 Capital Improvement Program Sheet Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency Approved By: Kristine Ridge, City Manager Exhibit 1 SANTA ANA Phi Project Nos. 22-6468 & 22-6620: Lincoln Avenue Water & Sewer Improvements PUBLIC WORKS AGENCY CITY OF SANTA ANA ADDENDUM NO. 1 PROPOSAL EXHIBIT 2 PROJECT NO.: 22-6468 & 22-6620 LINCOLN AVENUE WATER AND SEWER IMPROVEMENTS BIB PROPOSAL [1�i�911.� Iili�►[iff�i��l�. 090WK0J�"lm"rAUI 1"RON1: 4] 1 a REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or hump sure(s) set forth in the following schcdule: Item Description Qty Unit Unit .Price Amount I Mobilization (max. 5% of total bid) l LS $ 7Dfoo-o 70 000 2 8" Class 305 (DR 14) C900 PVC Pipe 920 LF $ $ 9 0 j �j f 3 l" Copper Water Service 9 EA $-; f I 4 4" Fire Sen+ice 1 EA $ r $ 5 8" Resilient Wedge Gate Valve 4 EA S of o o O 6 Firc Hydrant 4 EA S r r J 0� 0 $� 1 a) 7 Vertical Offset (As -Needed)* 3 EA S a $';� 00 J 8 1" Air and Vacuum release Valve (As -Needed)* I EA S 71 7 O Q $ r 7 7 9 Additional Potholing (As -Needed)* I EA $ 750 S 7 �_p O 10 6" SDR-26 PVC Pipe 20 LF S CJ 1 1 8" SDR-26 PVC Pipe 820 Ll= $ r 37 `7 S 3o7, �_oD 12 Scwer Lateral and Cleanout (Omen Trench) 10 EA S 6r O DQ 160 I 0-0-0 13 Remove Existing Manhole Structure 4 EA $ d Do 116, 000 14 New Manhole Structure 5 EA- S ar a 3-3 S / (9 a o-D P-1 of P-18 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6468 & 22-6620 LINCOLN AVENUE WATER AND SEWER IMPROVEMENTS Item Description Qt`° Unit Unit Price Amount 15 CCTV Inspection of New Sewer Main 840 LF $ -7 I S $ g O 16 CCTV Inspection of New Sewer Lateral 10 EA S :5 0 () S 5- r 17 Bypass Pumping I.5 S�a1 10 i 18 Unclassified Excavation 265 CY $7 Sq S 19 Asphalt Concrete 975 TN S + O i S+ + � O ! 20 Cold Mill (2") 570 SF S � S � g � � 21 PCC Sidewalk (T=4") 4420 SF S Sq 7� r 22 PCC Curb Ramp 12.0 SF S� S 6,600 23 PCC Driveway Approach 1020 SF S r S � 6,�o 24 PCC Cross -Gutter 140 SF $ S -7o 0 0 f 25 PCC Curb & Gutter (A-2-6) 660 LF $ ZQ S � $D'a 26 PCC Curb 610 LF S D S p 27 Fence 610 LF S 60 S U 6 ❑ O J 28 Remove Existing Bollard t2 EA $ q-0 S G � 0 0fl 29 Project Advertisement Sign. 2 EA S ()L)Q S o Oo 30 Signing & Striping 1 LS $' .y o S I 31 Construction Permit 1 LS $15,000 $15,000 32 As -Built Plans 1 LS $25,000 S25,000 P-2 of P-18 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6468 & 22-6620 LINCOLN AVENUE WATER AND SEWER IMPROVEMENTS TOTAL BASE BM $ 1 1 -! S -3f � �157, O0 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" lLnit as stated in Section ;-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly_ t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications. TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within forty-five 45) working days after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $6,700 per calendar day. Name of Firm F % � be w 1 h <-. Signature of BIDDER Title P(e-s cd ew f (If an individual, so state. If a firm or co -partnership, state the firm name and give the names of all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-3 of P-18 CITY OF SANTA ANA CONSTRUCTION CONTRACT PROJECT NOS. 22-6468 & 22-6620 LINCOLN AVENUE WATER & SEWER MAIN IMPROVEMENTS This CONSTRUCTION CONTRACT is made and entered into this 19th day of April, 2022 by and between the City of Santa Ana, California, a charter city and municipal corporation organized and existing under the Constitution and laws of the State of California (hereinafter "CITY"), and Big Ben, Inc. (hereinafter "CONTRACTOR"). WITNESSETH: The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows: 1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction of the City Engineer of the CITY, the Lincoln Avenue Water & Sewer Main Improvements (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contract Documents prepared by the City's Public Works Agency and approved by the City Council. 2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard Specifications for Public Works Construction and which include the following: • Notice Inviting Bids • Information to Bidders • Bid Proposal • Bid Bond • Contract Form • Contract Bonds • General Provisions • Special Provisions • Technical Provisions and Project Plans • Community Workforce Agreement • Appendices In case of conflict between the Contract Documents, the precedence of documents shall be as established in the Standard Specifications for Public Works Construction. 3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF IMPROVEMENT the sum total amount not to exceed One Million Four Hundred Fifty -Three Thousand Seven Hundred Sixty -Five Dollars and No Cents ($1,453,765.00), as set forth and identified in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A." The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate quantities only, and the City does not expressly or by implication agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work or to omit portions of the work as may be deemed necessary or advisable. rev. 09/01/2017 Pagel of 3 4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including commencing construction within the timeframe therein specified after issuance of a Notice to Proceed. 5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for such work as set forth in the wage determinations for this work in accordance with applicable State and Federal law. 6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement (CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website at: http://www.santa-ana.org/pwa/documents/CWA.pdf. 7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY, one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%) of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment Bond). This Contract shall not become effective until such bonds are supplied to and approved by the CITY. 8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price. 9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY. 10. INDEMNIFICATION. To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend, indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents, employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"), through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs, damages or losses, including reasonable costs and attorney's fees, for injury, including death to any person or damage to any property, arising directly or indirectly from, or in any manner relating to, any of the following: (i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its Subcontractors of any lower tier; (ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, of any of the obligations under the Contract Documents; Page 2 of 3 (iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either on the project site or on other properties; (iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower tier, for Work of Improvement performed on or off the project site; and (v) Any personal injury, property damage or economic loss to third persons related to and arising from the performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, of the Work of Improvement. (vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all subcontract documents issued by CONTRACTOR. Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in favor of CONTRACTOR against CITY or any other Indemnitee. IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and year first above written. ATTEST: DAISY GOMEZ Clerk of the Council APPROVED AS TO FORM: SONIA R. CARVALHO City Attorney By: r� 9W � 19 JOHN FUNK Senior Assistant City Attorney RECOMMENDED FOR APPROVAL: NABIL SABA, PE Executive Director Public Works Agency CITY OF SANTA ANA KRISTINE RIDGE City Manager CONTRACTOR: Big Ben, Inc. Sep Digitally signed by Sep Sharifi DN: cn=Sep Sharifi, o, ou, email=sep@big benengineerin US Date: 23:28:41 Sharifi 07,00, SEP SHARIFI President Page 3 of 3 CITY OF SANTA ANA ADDENDUM NO. 1 PROPOSAL PROJECT NO.: 22-6468 & 22-6620 LINCOLN AVENUE WATER AND SEWER IMPROVEMENTS BID PROPOSAL l(Yi�9ll.� Iili�►[iff�i��l�. 090WK0J�"lm"rAUI 1"RON1: 4] 1 a REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or hump sure(s) set forth in the following schcdule: Item Description Qty Unit Unit .Price Amount I Mobilization (max. 5% of total bid) l LS $ 7Dfoo-o 70 000 2 8" Class 305 (DR 14) C900 PVC Pipe 920 LF $ $ 9 0 j �j f 3 l" Copper Water Service 9 EA $-; f I 4 4" Fire Sen+ice 1 EA $ r $ 5 8" Resilient Wedge Gate Valve 4 EA S of o o O 6 Firc Hydrant 4 EA S r r J 0� 0 $� 1 a) 7 Vertical Offset (As -Needed)* 3 EA S a $';� 00 J 8 1" Air and Vacuum release Valve (As -Needed)* I EA S 71 7 O Q $ r 7 7 9 Additional Potholing (As -Needed)* I EA $ 750 S 7 �_p O 10 6" SDR-26 PVC Pipe 20 LF S CJ 1 1 8" SDR-26 PVC Pipe 820 Ll= $ r 37 `7 S 3o7, �_oD 12 Scwer Lateral and Cleanout (Omen Trench) 10 EA S 6r O DQ 160 I 0-0-0 13 Remove Existing Manhole Structure 4 EA $ d Do 116, 000 14 New Manhole Structure 5 EA- S ar a 3-3 S / (9 a o-D P-1 of P-18 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6468 & 22-6620 LINCOLN AVENUE WATER AND SEWER IMPROVEMENTS Item Description Qt`° Unit Unit Price Amount 15 CCTV Inspection of New Sewer Main 840 LF $ -7 I S $ g O 16 CCTV Inspection of New Sewer Lateral 10 EA S :5 0 () S 5- r 17 Bypass Pumping I.5 S�a1 10 i 18 Unclassified Excavation 265 CY $7 Sq S 19 Asphalt Concrete 975 TN S + O i S+ + � O ! 20 Cold Mill (2") 570 SF S � S � g � � 21 PCC Sidewalk (T=4") 4420 SF S Sq 7� r 22 PCC Curb Ramp 12.0 SF S� S 6,600 23 PCC Driveway Approach 1020 SF S r S � 6,�o 24 PCC Cross -Gutter 140 SF $ S -7o 0 0 f 25 PCC Curb & Gutter (A-2-6) 660 LF $ ZQ S � $D'a 26 PCC Curb 610 LF S D S p 27 Fence 610 LF S 60 S U 6 ❑ O J 28 Remove Existing Bollard t2 EA $ q-0 S G � 0 0fl 29 Project Advertisement Sign. 2 EA S ()L)Q S o Oo 30 Signing & Striping 1 LS $' .y o S I 31 Construction Permit 1 LS $15,000 $15,000 32 As -Built Plans 1 LS $25,000 S25,000 P-2 of P-18 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6468 & 22-6620 LINCOLN AVENUE WATER AND SEWER IMPROVEMENTS TOTAL BASE BM $ 1 1 -! S -3f � �157, O0 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" lLnit as stated in Section ;-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly_ t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications. TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within forty-five 45) working days after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $6,700 per calendar day. Name of Firm F % � be w 1 h <-. Signature of BIDDER Title P(e-s cd ew f (If an individual, so state. If a firm or co -partnership, state the firm name and give the names of all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-3 of P-18 EXHIBIT 4 COST ANALYSIS CONSTRUCTION OF PROJECT NOS. 22-6468 & 22-6620: LINCOLN AVENUE WATER & SEWER IMPROVEMENTS Construction Contract $ 1,453,765.00 Contract Administration, Inspection and Testing $ 218,000.00 Contingencies $ 228,235.00 Water Engineering $ 100,000.00 TOTAL ESTIMATED CONSTRUCTION COSTS 1 $ 2,000,000.00 07 07 ■ A a mv EXHIBIT 5 F ■ r r r r i r r Construction 1,300,000 - - - - i 1,3p - - - B r r t i Y i r WATER CAPITAL 1,300,000 - - - - i ■ �