HomeMy WebLinkAboutItem 17 - Construction Contract Award for MacArthur Boulevard ResurfacingPublic Works Agency
www.santa-ana.org/pw
Item # 17
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
April 19, 2022
TOPIC: Construction Contract Award for MacArthur Boulevard Resurfacing
AGENDA TITLE
Award a Construction Contract to All American Asphalt in the Amount of $823,333 for the
MacArthur Boulevard Resurfacing Project from Flower Street to Main Street, Fiscal Year
(FY) 2021-22, with an Estimated Project Delivery Cost of $1,127,000 (Project No. 20-
6957) (Non -General Fund)
RECOMMENDED ACTION
1. Authorize budget reallocation of $126,576 in unspent HUTA 2103 Gas Tax funds to
the MacArthur Boulevard Resurfacing Project from Flower Street to Main Street (No.
20-6957) from the Gas Tax Local Street Improvements Project (No. 20-6956).
2. Award a construction contract to All American Asphalt, the lowest responsible bidder,
in accordance with the base bid in the amount of $823,333, for construction of the
MacArthur Boulevard Resurfacing Project from Flower Street to Main Street FY 2021-
22.
3. Approve the Project Cost Analysis for a total estimated construction delivery cost of
$1,127,000, which includes $823,333 for the construction contract, $113,334 for
contract administration, inspection and testing, and a $190,333 project contingency
for unanticipated, unforeseen work, and additional nearby asphalt pavement
improvements.
DISCUSSION
The City's Pavement Management Program (PMP) has been developed to prioritize and
recommend the most cost-effective roadway repairs, and maximize the return from
available funding for street pavement. The segment of MacArthur Boulevard, from Flower
Street to Main Street (Exhibit 1), is identified as a high priority for pavement rehabilitation
in the PMP.
This work includes reconstruction/resurfacing of existing pavement and replacement/
installation of missing and damaged curbs, gutters, sidewalks, and curb ramps within this
street segment. The proposed contract has favorable bid pricing for asphalt pavement
Construction Contract Award for MacArthur Boulevard Resurfacing
April 19, 2022
Page 2
repair. As a result, the project contingency amount is being increased to 23 percent to
perform additional asphalt repairs in the surrounding areas as necessary.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was
advertised in the Orange County Register newspaper on December 20 and 27, 2021. The
project was also advertised on PlanetBids, and bids were received electronically via
PlanetBids on January 18, 2022.
The City notified a total of 1,216 regional vendors via PlanetBids, 77 of which are Santa
Ana based. Forty-four vendors requested bidding documents. A total of five bids were
received. However, no bids were received from Santa Ana contractors.
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
All American Asphalt
Corona
$823,333
2
R.J. Noble Company
Orange
$866,058
3
Hardy & Harper Inc.
Lake Forest
$870,000
4
EBS General Engineering Inc.
Corona
$928,526
5
Excel Paving Co
Long Beach
$972,348
A total of five bids were received and all were deemed responsive. All American Asphalt
submitted the lowest responsive base bid in the amount of $823,333 (Exhibit 2). As
specified in the bid documents, the lowest bid shall be determined on the basis of the
Base Bid. Based on the bid analysis and a contractor's reference check, staff
recommends awarding the construction contract to All American Asphalt in the amount of
the base bid totaling $823,333 (Exhibit 3).
All American Asphalt has worked on various projects for the City of Santa Ana throughout
the last several years. The most recent projects are Bristol Street Protected Bike Lanes
Project from Edinger Avenue to First Street, Residential Street Repair Program, and
Flower Street Rehabilitation from McFadden Avenue to First Street.
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes construction administration, inspection, and testing, along
with an allowance for contingencies to account for unexpected, unforeseen conditions,
and additional nearby asphalt pavement improvements. Construction administration and
inspection includes the following: construction management; implementation of the City's
Community Workforce Agreement requirements; inspection of the Contractor's work to
Construction Contract Award for MacArthur Boulevard Resurfacing
April 19, 2022
Page 3
ensure contract compliance, workmanship, and quality; and materials testing. As
indicated in the Cost Analysis (Exhibit 4) and as summarized in the table below, the
estimated total construction delivery cost of the project is $1,127,000.
Project Item
Total
Construction Contract
$823,333
Construction Administration, Inspection, Testing
$113,334
Contingencies
$190,333
TOTAL CONSTRUCTION DELIVERY COST
$1,127,000
Approval of the amendment to the FY 2021-22 Capital Improvement Program (Exhibit 5)
will officially incorporate this project into the program.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions
are exempt from further review. Categorical Exemption Environmental Review No. ER-
2020-98 was filed for the project.
FISCAL IMPACT
As indicated in the Cost Analysis, the estimated total construction delivery cost of the
project is $1,127,000.00 which includes construction, contract administration, inspection,
testing, and an authorized contingency.
The following table summarizes the funds budgeted and available for expenditure to
deliver construction of this project.
Fiscal
Accounting Unit -
Fund
Accounting Unit -
Y
Year
Account No.
Description
Account No.
Amount
(Project No.)
Description
EXISTING PROJECT BUDGET
2021-22
05917665-66220
Select Street
HUTA Gas Tax-
RMRA, Improvements
$1,000,424
(20-6957)
Construction
Other Than Building
BUDGET REALLOCATION
05917663-66220
Select Street
HUTA 2103 Gas Tax,
2021-22
(From Proj. 20-6956
Construction
Improvements Other
$126,576
To Pro'. 20-6957)
Than Buildin dff
Total
$1,127,000
EXHIBIT(S)
1. Location Map
2. Bid Proposal
Construction Contract Award for MacArthur Boulevard Resurfacing
April 19, 2022
Page 4
3. Construction Contract
4. Cost Analysis
5. CIP Worksheet
Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency
Approved By: Kristine Ridge, City Manager
SANTAANA Project No. 20-6957:
1 Exhibit 1 MACARTHUR BOULEVARD
umJ RESURFACING: FLOWER STREET TO
PUBLICWORKS AGENCY I MAIN STREET
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6957
MACARTHUR BOULEVARD RESURFACING FROM FLOWER STREET TO MAIN
STREET
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Al American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation
360
CY
$ 179.00
$ 64,440.00
2
Asphalt Concrete
1,030
TN
$
90.00
$
92,700.00
3
ARAM
16,340
SY
$
6.10
$
99,674.00
4
Cold Mill (3")
147,000
SF
$ 0.25
$ 36,750.00
5
Cold Mill (2")
56,300
SF
$
0.17
$
9,571.00
6
Asphalt Rubber Hot Mix
2,300
TN
$ 106.00
$ 243,800.00
7
PCC Sidewalk (4")
2,600
SF
$ 7.38
$19,188.00
8
PCC Driveway Approach
400
SF
$ 12.98
$ 5,192.00
(Commercial = 8")
9
PCC Curb Ramp
1,100
SF
$ 15.79
$17,369.00
10
PCC Curb and Gutter (Type
400
LF
$ 45.60
$18,240.00
A-2-8)
11
PCC Curb and Gutter (Type
200
LF
$
31.84
$
6,368.00
B-1)
12
PCC Cross -Gutter (Local
700
SF
$ 16.78
$1 1, 746.00
Street)
13
PCC Bus Pad
5,970
SF
$ 18.00
$107,460.00
P-1 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6957
MACARTHUR BOULEVARD RESURFACING FROM FLOWER STREET TO MAIN
STREET
Item
Description
Qty
Unit
Unit Price
Amount
14
Root Shave
5
EA
$ 265.00
$ 1,325.00
15
Furnish and Install New #6
1
EA
$ 1,060.00
$ 1,060.00
Pullbox
16
Adjust Sewer and Drainage
8
EA
$ 1,500.00
$ 12,000.00
Manhole to Finished Grade
17
Furnish and Install New Water
7
EA
$ 1,500.00
$
Valve Frame and Cover to
10,500.00
Finished Grade
18
Furnish and Install New Water
1
EA
$ 950.00
$ 950.00
Meter Box
19
Adjust Survey Monument to
2
EA
$ 1,200.00
$ 2,400.00
Finished Grade
20
Furnish and Install Traffic
74
EA
$ 300.00
$
22,200.00
Loops
21
Project Advertisement Sign
2
EA
$ 2,650.00
$ 5,300.00
22
Signing and Striping
I
LS
$ 18,600.00
$18,600.00
23
Construct Circular PCC Collar
I
EA
$ 1,500.00
$
10,500.00
24
Construction Permit
1
EA
$ 10,000
$ 10,000
25
As -Built Plans
1
EA
$ 5,000
$ 5,000
P-2 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6957
MACARTHUR BOULEVARD RESURFACING FROM FLOWER STREET TO MAIN
STREET
TOTAL BASE BID (1-25) ' 823,333.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within 60 working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount. in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $2,200 per calendar day.
Name of Firm All American Asphalt
Signature of BIDDER
Title Edward J. Carlson, Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-3 of P-18
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 20-6957
MACARTHUR BOULEVARD REHABILITATION FROM FLOWER STREET TO MAIN STREET
This CONSTRUCTION CONTRACT is made and entered into this 5th day of April, 2022 by and between
the City of Santa Ana, California, a charter city and municipal corporation organized and existing under
the Constitution and laws of the State of California (hereinafter "CITY"), and All American Asphalt
(hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the MACARTHUR BOULEVARD REHABILITATION FROM
FLOWER STREET TO MAIN STREET (hereinafter referred to as the "WORK OF IMPROVEMENT")
identified in and in accordance with the Contract Documents prepared by the City's Public Works
Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF
IMPROVEMENT the sum total amount not to exceed Eight Hundred Twenty Three Thousand Three
Hundred Thirty -Three Dollars and No Cents ($823,333.00), as set forth and identified in the BID
PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A."
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of work
will correspond therewith, but reserves the right to increase or decrease the amount of any class or
portion of the work or to omit portions of the work as may be deemed necessary or advisable.
rev. 09/01/2017 Page 1 of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at: http://www.santa-ana.ora/pwa/documents/CWApdf
CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
DAISY GOMEZ
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By:
JO FUNK
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
NABIL SABA, PE
Executive Director
Public Works Agency
CITY OF SANTA ANA
KRISTINE RIDGE
City Manager
CONTRACTOR:
All American Asphalt
NAME: Edward J. Carlson
TITLE: Vice President
Page 3 of 3
CITY OF SANTA ANA EXHIBIT A
PROPOSAL
PROJECT NO.: 20-6957
MACARTHUR BOULEVARD RESURFACING FROM FLOWER STREET TO MAIN
STREET
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with
said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the
following schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation
360
CY
$ 179.00
$ 64,440.00
2
Asphalt Concrete
1,030
TN
$ 90.00
$ 92,700.00
3
ARAM
16,340
SY
$ 6.10
$99, 674.00
4
Cold Mill (3")
147,000
SF
$ 0.25
$ 36,750.00
5
Cold Mill (2")
56,300
SF
$ 0.17
$ 9,571.00
6
Asphalt Rubber Hot Mix
2,300
TN
$ 106.00
$ 243, 800.00
7
PCC Sidewalk (4")
2,600
SF
$ 7.38
$19,188.00
8
PCC Driveway Approach
400
SF
$
12.98
$
5,192.00
(Commercial = 8")
9
PCC Curb Ramp
1,100
SF
$ 15.79
$17,369.00
10
PCC Curb and Gutter (Type
400
LF
$ 45.60
$18,240.00
A-2-8)
11
PCC Curb and Gutter (Type
B-1)
200
LF
$ 31.84
$
6,368.00
12
PCC Cross -Gutter (Local
700
SF
$ 16.78
$1 1, 746.00
Street)
13 1
PCC Bus Pad
5,970 1
SF
$ 18.00
$107,460.00
P-1 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6957
MACARTHUR BOULEVARD RESURFACING FROM FLOWER STREET TO MAIN
STREET
Item
Description
Qty
Unit
Unit Price
Amount
14
Root Shave
5
EA
$ 265.00
$1,325.00
15
Furnish and Install New #6
1
EA
$ 1,060.00
$ 1,060.00
Pullbox
16
Adjust Sewer and Drainage
8
EA
$ 1,500.00
$ 12,000.00
Manhole to Finished Grade
17
Furnish and Install New Water
7
EA
$ 1,500.00
$
Valve Frame and Cover to
10,500.00
Finished Grade
18
Furnish and Install New Water
1
EA
$ 950.00
$ 950.00
Meter Box
19
Adjust Survey Monument to
2
EA
$ 1,200.00
$ 2,400.00
Finished Grade
20
Furnish and Install Traffic
74
EA
$ 300.00
$ 22 200.00
Loops
,
21
Project Advertisement Sign
2
EA
$ 2,650.00
$ 5,300.00
22
Signing and Striping
1
LS
$ 18,600.00
$18,600.00
23
Construct Circular PCC Collar
1
EA
$ 1,500.00
$ 10,500.00
24
Construction Permit
1
EA
$ 10,000
$ 10,000
25
As -Built Plans
1
I EA
$ 5,000
$ 5,000
P-2 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 20-6957
MACARTHUR BOULEVARD RESURFACING FROM FLOWER STREET TO MAIN
STREET
TOTAL BASE BID (1-25) $ 823,333.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the '*25%" limit as stated in Section 3-2 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount
shown above, within 60 working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the
Standard Specifications, shall be $2,200 per calendar day.
Name of Firm All American Asphalt
Signature of BIDDER
Title Edward J. Carlson, Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-3 of P-18
EXHIBIT 4
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 20-6957: MacArthur Boulevard Project From
Flower to Main
Construction Contract
$
823,333.00
Contract Administration, Inspection and Testing
$
113,333.70
Contingencies
$
82,333.30
TOTAL ESTIMATED CONSTRUCTION COSTS
I $
1,019,000.00
PROJECT TITLE:
MacArthur Boulevard Resurfacing: Flower to
Main
PROJECT CATEGORY:
Street Improvements -
Arterial Street Rehabilitation
LOCATION MAP
u .. MMV•iN
W Warner Ave
ve �+
E Wa Are
E W.m , Aw
w
9
h
N
rry�k Ave
N
W pyv Rd F Dyer Rd
yl
�*c EA.`ran RvR
,rr �
W MacArthur sib
7.�
a
W Sunflower Ave SunRp Ara
fr�
« Sourh
u+ SWTH COAST WTRO
�Va:a � R
Cn
' er.s*v%.�-
IIr
CITY OF SANTA ANA FY 19/20 CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Reconstruction/resurfacing of existing pavement and
replacementlinstallation of missing or damaged, curbs,
gutters, sidewalks, driveway approaches, and
wheelchair ramps within this segment of roadway.
PROJECT NEED:
The City's Pavement Management Program (PMP) has
been developed to prioritize and recommend the most
cost-effective roadway repairs, and maximize the return
from available funding for street pavement. This
segment of MacArthur Boulevard pavement
rehabilitation is identified as a high priority in the PMP.
PROJECT COSTS FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26
Construction 77019,000
Engineering $81,000
TOTAL $1,100,000
SOURCE OF FUNDS FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26
RMRA SB1 $1,100,000
TOTAL $1,100,000
AGENCY DIVISION: CONTACT: DATE:
Public Works Agency Design Engineering Kenny Nguyen, Senior Civil Engineer 24-May-2019
-13-