HomeMy WebLinkAboutItem 18 - Garnsey Business District Pavement Improvements Public Works Agency www.santa-ana.org/pw Item # 18 City of Santa Ana 20 Civic Center Plaza, Santa Ana, CA 92701 Staff Report March 15, 2022 TOPIC: Garnsey Business District Pavement Improvements AGENDA TITLE Award a Construction Contract to All American Asphalt in the Amount of $4,189,151, for the Garnsey Business District Pavement Improvements FY 2021-22 Project, with an Estimated Project Delivery Cost of $4,763,666 (Project No. 22-6991) (Non-General Fund) RECOMMENDED ACTION 1. Award a construction contract to All American Asphalt, the lowest responsible bidder, in accordance with the base bid in the amount of $4,189,151, for construction of the Garnsey Business District Pavement Improvements FY 2020-21, for the term beginning March 15, 2022, and ending upon project completion, and authorize the City Manager to execute the contract subject to non-substantive changes approved by the City Manager and the City Attorney. 2. Approve the Project Cost Analysis for a total estimated construction delivery cost of $4,763,666, which includes $4,189,151 for the construction contract; $335,132 for contract administration, inspection and testing; and a $239,383 project contingency for unanticipated or unforeseen work. DISCUSSION The Garnsey Business District (Exhibit 1) is in a state of disrepair and the Garnsey Business District Pavement Improvements Project will reconstruct the local interior roadway network within the District. The scope of work involves fully reconstructing a pavement section, repair of longitudinal gutters, and replacement of damaged curb and gutter, curb ramps, and sidewalk. Traffic signage and striping will also be replaced. Public Outreach and Contractor Participation To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was advertised in the Orange County Register newspaper on January 14 and January 21, 2022. The project was also advertised on PlanetBids, and bids were received electronically via PlanetBids on February 1, 2022. Award Construction Contract to All American Asphalt March 15, 2022 Page 2 2 4 9 5 The City notified a total of 1,317 regional vendors via PlanetBids, 78 of which are based in Santa Ana. Forty vendors requested bidding documents. A total of 4 bids were received. However, no bids were received from Santa Ana contractors. Bid Results Summary RANK BIDDER’S NAME LOCATION BASE BID 1 All American Asphalt Corona $4,189,151.00 2 Excel Paving Co.Long Beach $4,236,670.00 3 R.J. Noble Company Orange $4,364,355.00 4 Hardy & Harper, Inc. Lake Forest $4,430,000.00 A total of four bids were received and all were deemed responsive. All American Asphalt submitted the lowest responsive base bid in the amount of $4,189,151 (Exhibit 2). As specified in the bid documents, the lowest bid shall be determined on the basis of the Base Bid. Based on the bid analysis and a contractor’s reference check, staff recommends awarding the construction contract to All American Asphalt, in the amount of the base bid totaling $4,189,151 (Exhibit 3). All American Asphalt has performed the following work in the City of Santa Ana within the past five years: Flower Street Rehabilitation (Project No. 21-6976), Residential Street Repair Program FY 2019-20 (Project No. 20-7533), and Local Street Preventative Maintenance FY 2019-20 (Project No. 20-6907). Project Delivery To deliver a complete project, in addition to the construction contract, the estimated total project delivery cost includes construction administration, inspection, and testing, along with an allowance for contingencies to account for unexpected or unforeseen conditions. Construction administration and inspection includes construction management; implementation of the City’s Community Workforce Agreement requirements; inspection of the Contractor’s work to ensure contract compliance, workmanship, and quality; and materials testing. As indicated in the Cost Analysis (Exhibit 4) and as summarized in the table below, the estimated total construction delivery cost of the project is $4,763,666. Project Item Total Construction Contract $4,189,151.00 Construction Administration, Inspection, Testing $335,132.00 Contingencies $239,383.00 TOTAL CONSTRUCTION DELIVERY COST $4,763,666.00 Award Construction Contract to All American Asphalt March 15, 2022 Page 3 2 4 9 5 ENVIRONMENTAL IMPACT In accordance with the California Environmental Quality Act, the recommended actions are exempt from further review. Categorical Exemption Environmental Review No. ER- 2021-109 was filed for the project. FISCAL IMPACT As indicated in the Cost Analysis, the estimated total construction delivery cost of the project is $4,763,666, which includes construction, contract administration, inspection, testing, and an authorized contingency. The following table summarizes the funds budgeted and available for expenditure to deliver construction of this project. Fiscal Year Accounting Unit - Account No. (Project No.) Fund Description Accounting Unit - Account No. Description Amount 2020-21 05917665-66220 (Proj. 22-6991) Select Street Construction HUTA Gas Tax-RMRA – Improvements Other Than Building $812,334 2021-22 05917660-66220 (Proj. 22-6991) Select Street Construction Select Street Construction – Improvements Other Than Building $3,131,332 2021-22 06617647-66301 (Proj. 22-6472) Acquisition & Construction Water Utility Capital Projects – Water Capital Project $820,000 Total $4,763,666 EXHIBIT(S) 1. Location Map 2. Bid Proposal 3. Construction Contract 4. Cost Analysis Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency Approved By: Kristine Ridge, City Manager PWA SANTA ANA PUBLIC WORKS AGENCY Project No. 22-6991: Garnsey Business District Pavement Improvements Exhibit 1 93.80 92.90 104.00 500.00 9.80 46.88 31.59 15.64 15.38 532.00 950.00 1,034,614.00 1,405,577.00 374,400.00 130,000.00 3,920.00 11,600.00 9,376.00 3,159.00 140,760.00 816,678.00 61,915.00 23,940.00 60,000.00 19,000.00 10,000.00 1,015.00 5,800.00 Exhibit 2 690.00 8,970.00 2,100.00 4,576.00 3,866.00 50,000.00 24,700.00 3,866.00 2,288.00 1,050.00 4,189,151.00 Exhibit 2 Exhibit 3 Exhibit 3 Exhibit 3 Exhibit 3 Exhibit 3 Exhibit 3 EXHIBIT 4 Construction Contract 4,189,151.00$ Contract Administration, Inspection and Testing 335,132.00$ Contingencies 239,383.00$ TOTAL ESTIMATED CONSTRUCTION COSTS 4,763,666.00$ CONSTRUCTION OF PROJECT NO. 22-6991: Garnsey Business District Pavement Improvements COST ANALYSIS