Item # 24
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
December 7, 2021
TOPIC: Traffic Signal and Street Lighting Maintenance
AGENDA TITLE
Approve Agreement Amendments with Econolite Systems Inc. and California
Professional Engineering Inc. for Traffic Signal and Street Lighting Maintenance
RECOMMENDED ACTION
1. Authorize the City Manager to execute a first amendment to the agreement with
Econolite Systems Inc. to expand the Traffic Signal maintenance scope of work and
increase the expenditure amount by $825,000, for a total agreement amount not to
exceed $4,200,000 for the remaining term of the agreement expiring July 1, 2024,
subject to non-substantive changes approved by the City Manager and the City
Attorney.
2. Authorize the City Manager to execute a first amendment to the agreement with
California Professional Engineering Inc. to expand the Street Lighting maintenance
scope of work and increase the expenditure amount by $360,000, for a total
agreement amount not to exceed $2,619,184 for the remaining term of the agreement
expiring October 1, 2024, subject to non-substantive changes approved by the City
Manager and the City Attorney.
DISCUSSION
Econolite System Inc. and California Professional Engineering (CPE) Inc. provide
electrical maintenance services for the City’s Traffic Signal and Street Lighting Systems.
There are two separate contracts, one for Traffic Signals and the other for Street Lighting.
Although the contracts are separate, the scope of services of the two agreements are
similar in nature providing preventative and emergency on-call maintenance services for
the citywide electrical systems. The two maintenance programs were previously managed
by separate sections within Public Works; however to improve efficiencies, both programs
are now under the supervision of the Public Works - Traffic Engineering Section (now
Traffic Signals and Street Lighting Division) as of the beginning of the current calendar
year.
By merging services, City Staff will be able to streamline repair services and improve
emergency response time to unforeseen circumstances such as damages caused by
Amend Agreements for Traffic Signal and Street Lighting Maintenance
December 7, 2021
Page 2
2
3
1
0
accidents or failure of major system components. Econolite Systems Inc. will continue to
provide preventative and emergency on-call services for the Traffic Signal System but will
now also provide Street Lighting emergency on-call maintenance services. CPE will focus
on an expanded scope of services for on-call as needed maintenance repairs of the City
streetlights. The added scope and funds, as requested, are needed to maintain
responsiveness to the significant addition of approximately 7,500 street lights purchased
from Southern California Edison.
Background
On July 2, 2019, the City Council authorized the City Manager to execute an agreement
with Econolite System Inc. for a period of three-year period with provision for two one-
year extensions. City Staff recommends increasing the total expenditure amount by
$825,000 and exercising the available extensions, for a total agreement amount not to
exceed $4,200,000 and term of the agreement expiring July 1, 2024.
On October 12, 2019, the City Council authorized the City Manager to execute and
agreement with California Professional Engineering Inc. for a period of three-year period
with provision for two one-year extensions. City Staff recommends increasing the total
expenditure amount by $360,000 and exercising the available extensions, for a total
agreement amount not to exceed $2,699,684 and term of the agreement expiring October
1, 2024.
ENVIRONMENTAL IMPACT
There is no environmental impact associated with the action.
FISCAL IMPACT
Funds are available for expenditure in Fiscal Year 2021-22 and will be budgeted in
subsequent fiscal years as shown below in the estimated spending plan:
Econolite Systems Inc.
Agreement Term (July 2, 2019, through July 1, 2022)
Fiscal
Year
Accounting
Unit –
Account No.
Fund
Description
Accounting Unit,
Account Description Amount
2019-20 02917620-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $675,000
2020-21 01117630-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $675,000
2021-22 02917620-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $675,000
Previously Approved Funding:$2,025,000
Amend Agreements for Traffic Signal and Street Lighting Maintenance
December 7, 2021
Page 3
2
3
1
0
First Amendment
Fiscal
Year
Accounting
Unit –
Account No.
Fund
Description
Accounting Unit,
Account Description Amount
2021-22
Dec.- June
02917620-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $175,000
2021-22
Dec.-June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $100,000
Amended FY 2021-22 Funding:$275,000
3-Year Agreement Term - SUBTOTAL:$2,300,000
Optional Extension Period (July 2, 2022, through July 1, 2024)
2022-23 02917620-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $675,000
2023-24 02917620-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $675,000
2-Year Extension Funding (Previously Approved) - SUBTOTAL:$1,350,000
First Amendment
2022-23 02917620-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $175,000
2022-23 01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $100,000
2023-24 02917620-
62321
Traffic Signal
Maintenance
Maintenance & Repair
Improvements $175,000
2023-24 01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $100,000
Amended 2-Year Extension Funding - SUBTOTAL:$550,000
2-Year Optional Extension Period - SUBTOTAL:$1,900,000
AGREEMENT TOTAL:$4,200,000
California Professional Engineering Inc.
Agreement Term (October 2, 2019 through October 1, 2022)
Fiscal
Year
Accounting
Unit –
Account No.
Fund
Description
Accounting Unit,
Account Description Amount
2019-20
Oct. - June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $1,247,684
2020-21
July - June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $250,000
Amend Agreements for Traffic Signal and Street Lighting Maintenance
December 7, 2021
Page 4
2
3
1
0
California Professional Engineering Inc.
Fiscal
Year
Accounting
Unit –
Account No.
Fund
Description
Accounting Unit,
Account Description Amount
2021-22
July - June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $250,000
2022-23
July-Sept
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $62,500
Previously Approved Funding:$1,810,184
First Amendment
2021-22
Dec – June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $120,000
Amended FY 2021-22 Funding:$120,000
3-Year Agreement Term - SUBTOTAL:$1,930,184
Optional Extension Period (October 2, 2022, through October 1, 2024)
2022-23
Oct. - June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $187,500
2023-24
July - June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $250,000
2024
July - Sept
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $12,000
2-Year Extension Funding (Previously Approved) - SUBTOTAL:$499,500
First Amendment
2022-23
July – Sept
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $30,000
2022-23
Oct. - June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $90,000
2024
July - June
01117630-
62321
Street Light
Maintenance
Maintenance & Repair
Improvements $120,000
Amended 2-Year Extension Funding - SUBTOTAL:$240,000
2-Year Optional Extension Period - SUBTOTAL:$689,500
AGREEMENT TOTAL:$2,619,684
EXHIBIT(S)
1. First Amendment to Agreement Econolite Systems, Inc.
2. First Amendment to Agreement California Professional Engineering, Inc.
Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency
Amend Agreements for Traffic Signal and Street Lighting Maintenance
December 7, 2021
Page 5
2
3
1
0
Approved By: Kristine Ridge, City Manager
Page 1 of 2
FIRST AMENDMENT TO AGREEMENT TO PROVIDE
TRAFFIC SIGNAL SYSTEM MAINTENANCE SERVICES
THIS FIRST AMENDMENT to the above-referenced agreement is entered into on December 7,
2021, by and between Econolite Systems, Inc. (“Contractor”), and the City of Santa Ana, a charter
city and municipal corporation organized and existing under the Constitution and laws of the State
of California (“City”).
RECITALS
A.The parties entered into Agreement No. A-2019-101, dated July 2, 2019, by which
Contractor agreed to provide preventative and extraordinary maintenance services for the
citywide Traffic Signal System (“Agreement”).
B.The Agreement remains in effect through July 1, 2022, with provision for extension.
C.The parties now wish to modify the scope of services, increase the annual sum to be expended
under the Agreement, and exercise the options to extend the Agreement.
The Parties therefore agree:
1.Section 1, Scope of Services, is amended to include Contractor’s provision of immediate or
temporary repairs to City owned series and multiple street light pole or service knock downs
or damage caused by vehicle collision, acts of God, vandals, or as required because of a public
safety hazard. Contractor shall respond to emergency calls when directed by the City and
dispatch high voltage technician and equipment. Contractor shall be compensated for the
emergency street light work at the rates set forth in Exhibit B of the Agreement for
Extraordinary Maintenance.
2.Section 2.a., Compensation, is amended to increase the total annual sum to be expended under
the Agreement by $275,000 for the current annual period and all remaining annual periods.
3.Section 3, Term, is amended to extend the term of the Agreement through July 1, 2024.
4.Except as modified by this First Amendment, all terms and conditions of the Agreement shall
remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this First Amendment to the
Agreement on the date and year first written above.
ATTEST CITY OF SANTA ANA
Daisy Gomez Kristine Ridge
Clerk of the Council City Manager
Page 2 of 2
APPROVED AS TO FORM CONTRACTOR
Sonia R. Carvalho
City Attorney
By:_
John M. Funk By: Kirk T Steudle
Senior Assistant City Attorney Title: Sr Vice President - Systems
RECOMMENDED FOR APPROVAL
Nabil Saba
Executive Director
Public Works Agency
Page 1 of 2
FIRST AMENDMENT TO AGREEMENT TO PROVIDE
STREET LIGHT MAINTENANCE SERVICES
THIS FIRST AMENDMENT to the above-referenced agreement is entered into on December 7,
2021, by and between California Professional Engineering, Inc. (“Contractor”), and the City of
Santa Ana, a charter city and municipal corporation organized and existing under the Constitution
and laws of the State of California (“City”).
RECITALS
A. The parties entered into Agreement No. A-2019-174, dated October 2, 2019, by which
Contractor agreed to provide street light maintenance services (“Agreement”).
B. The Agreement remains in effect through October 1, 2022, with provision for extension.
C. The parties now wish to increase the annual sum to be expended under the Agreement.
The Parties therefore agree:
1. Section 2.a., Compensation, is amended to increase the total annual sum to be expended under
the Agreement by $120,000 for the current annual period and all remaining annual periods.
2. Section 3, Term, is amended to extend the term of the Agreement through October 1, 2024.
3. Except as modified by this First Amendment, all terms and conditions of the Agreement shall
remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this First Amendment to the
Agreement on the date and year first written above.
ATTEST CITY OF SANTA ANA
_______________________________ ______________________________
Daisy Gomez Kristine Ridge
Clerk of the Council City Manager
APPROVED AS TO FORM CONTRACTOR
Sonia R. Carvalho
City Attorney
By:___________________________ _______________________________
John M. Funk By:
Senior Assistant City Attorney Title:
Van Nguyen
President
Page 2 of 2
RECOMMENDED FOR APPROVAL
________________________________
Nabil Saba
Executive Director
Public Works Agency