City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
March 2, 2021
TOPIC: National Fitness Campaign Grant
AGENDA TITLE:
Adopt a resolution accepting the 2021 National Fitness Campaign Grant, approve an
appropriation adjustment for the three project sites, award a purchase order for fitness
court equipment, and amend the Fiscal Year 2020-21 Capital Improvement Program.
RECOMMENDED ACTION
1) Adopt a resolution accepting the 2021 National Fitness Campaign Grant of $30,000
per site (Thornton Park, Lillie King Park, and Heritage Park) and agreeing to endeavor to
provide $109,065 per site to fund the remaining purchase price of the Fitness Courts.
2) Approve an appropriation adjustment of $212,545 in cellular tower funds received in
prior years (Acct. No. 05113002-50001) to the capital expenditure account (No.
05113263-66220).
3) Approve a sole source purchase order to the National Fitness Campaign, LLC (NFC)
for a NFC Fitness Court at Thornton Park, Lillie King Park, and Heritage Park for an
amount not to exceed $327,195, to be funded by the Capital Outlay Fund and the
Cannabis Public Benefit Fund, subject to non-substantive changes approved by the City
Manager and City Attorney.
4) Approve an amendment to the Fiscal Year 2020-21 Capital Improvement Program to
include the Thornton Park Fitness Court, the Lillie King Park Fitness Court, and the
Heritage Park Fitness Court projects.
DISCUSSION
On June 4, 2019, the City Council adopted a resolution accepting the 2019 National
Fitness Campaign grant of $30,000 per site and agreeing to endeavor to provide $90,000
per site to fund the remaining purchase price of the equipment plus the cost of installation
at five City sites (Jerome Park, El Salvador Park, Delhi Park, Cabrillo Park, and Rosita
Park). City staff installed the five fitness courts to ensure Santa Ana residents have the
resources they need to lead a healthy lifestyle through outdoor exercise.
National Fitness Campaign Grant
March 2, 2021
Page 2
4
7
2
On February 4, 2020, the City of Santa Ana submitted a grant application to the NFC to
build three additional fitness courts at Carl Thornton Park, Lillie King Park, and Heritage
Park.
On January 20, 2021, the City of Santa Ana received three $30,000 grants from NFC to
participate as a Model City in the 2021 National Fitness Campaign. Approval of the multi-
site application was based on the City of Santa Ana’s commitment to free health and
fitness options, development of stakeholder consensus, and the exceptional and active
public spaces where we will launch our Fitness Courts and the NFC program.
Total funding required for the purchase per Fitness Court® (includes mobile app, sports
floor, communications and press releases, activation campaign, etc.) is $139,065 plus
installation. The $30,000 grant per site operates as a credit towards the total purchase
price of the Fitness Court. Installation costs may be different from site to site, as location
conditions vary as well as the ability to use in-house staff for some of the installation when
possible.
As a requirement to the grant, the City must adopt a resolution to demonstrate funding
and support towards the projects.
The City is prepared to fully fund the balance needed ($109,065 per site) for the purchase
of the three courts. This resolution does not financially commit the City, but rather states
that the City will endeavor to secure the remaining funds needed.
The Fitness Court is a 32’ x 35’ outdoor bodyweight circuit training system that supports
28 simultaneous users on 30 separate pieces of equipment that are grouped into seven
stations. The 7 movement, 7-minute system, provides a full-body workout to people of
all ability levels. The integrated system includes a sports floor to simulate the indoor gym
exercise and the steel bodyweight training wall provides users with many exercise
combinations.
The Fitness Court is supported by “National Campaign Resources”. This is a digital
ecosystem that includes a mobile app, the Campaign’s social media support team,
promotional materials and programming to assist public agencies in building support for
fit living in community spaces.
No other vendor, distributor, or organization sells this system. The fitness court must be
acquired from the NFC, LLC.
FISCAL IMPACT
Funding in the amount of $237,455 ($176,910-Cannabis Public Benefit Fund and
$60,545-Capital Outlay Fund) is budgeted and available to go towards the estimated total
cost of $450,000 for all three sites. For the balance, the requested appropriation
National Fitness Campaign Grant
March 2, 2021
Page 3
4
7
2
adjustment, as follows, will appropriate Cellular Tower revenue, in the Capital Outlay
Fund, received from prior years (No. 05113002-50001) in the amount of $212,545.
Fiscal
Year
Accounting
Unit-Account #
Fund
Description
Accounting Unit,
Account Description
Amount
FY 20-21 05113263-
66220
Capital Outlay
Fund
Capital Improvements,
Improvements Other Than
Building
$212,545
After the above appropriation adjustment, funds are budgeted and available in the
following accounts for the specified year for the purchase order.
Fiscal
Year
Accounting
Unit-Account #
Fund
Description
Accounting Unit,
Account Description
Amount
FY 20-21 01213020-66220 Cannabis
Public Benefit
Fund
PRCSA, Improvements
Other Than Building
$109,065
FY 20-21 05113263-66220 Capital Outlay
Fund
Capital Improvements,
Improvements Other
Than Building
$218,130
EXHIBIT(S)
1. Resolution
2. National Fitness Campaign, LLC Quote
3. Capital Improvement Program Informational Sheets
Submitted By: Lisa Rudloff, Executive Director, Parks, Recreation and Community
Services
Approved By: Kristine Ridge, City Manager
LAR 3/2/21
Resolution No. 2019-XXX
Page 1 of 2
RESOLUTION NO. 2021-XXX
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA ACCEPTING THE 2021 NATIONAL FITNESS
CAMPAIGN GRANT OF $30,000 PER SITE AND
AGREEING TO ENDEAVOR TO PROVIDE $109,065 PER
EACH SITE TO FUND THE REMAINING PURCHASE
PRICE OF THE EQUIPMENT AND INSTALLATION OF THE
FITNESS EQUIPMENT AT THREE CITY PARKS
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines
and declares as follows:
A. In 2021, the National Fitness Campaign offered grants to Cities or
Colleges to install an outdoor Fitness Court®, in public parks for use by
the public at no cost.
B. The City’s Parks, Recreation and Community Services Agency submitted
an application for the 2021 National Fitness Campaign grant funds and
was selected as a recipient of the grant for three City owned sites.
C. The 2021 National Fitness Campaign grant is $30,000 per site for a total
of $90,000 for the three sites. The total cost for the purchase of the
outdoor Fitness Court® equipment at three City parks (Thornton Park,
Lillie King Park, and Heritage Park) is $139,065 per site for a total of
$417,195. The $30,000 grant per site operates as a credit toward the total
purchase price of the Fitness Court®. The City will need to obtain funding
to complete the installation of the three outdoor Fitness Court® locations.
Section 2. The City Council of the City of Santa Ana hereby authorizes the
City Manager or her designee, on terms acceptable to the City Attorney, to execute any
documents that are necessary to accept the 2021 National Fitness Campaign $30,000
grant funds per site (three sites total) for the outdoor Fitness Court® equipment;
Section 3. The City Council of the City of Santa Ana hereby agrees to
endeavor to secure funding for the remaining $109,065 per site, for a total of $327,195,
to purchase the outdoor Fitness Court® at three City sites;
Section 4. The City Council of the City of Santa Ana will endeavor to construct
and launch the outdoor Fitness Court® by the end of the 2020-2021 fiscal year,
contingent upon funding; and
Exhibit 1
Resolution No. 2021-XXX
Page 2 of 2
Section 5. The City Council of the City of Santa Ana believes the outdoor
Fitness Court® is an important recreation facility to support the health of the community
by making “world-class” fitness free at Thornton Park, Lillie King Park and Heritage
Park, to fund an outdoor bodyweight circuit training Fitness Court®, and to earn local
and national recognition as a leader in providing affordable health and wellness.
Section 5. This Resolution shall take effect immediately upon its adoption by
the City Council and the Clerk of the Council shall attest to and certify the vote adopting
this Resolution.
ADOPTED this 2nd day of March, 2021.
_______________________
Vicente Sarmiento
Mayor
APPROVED AS TO FORM:
Sonia R. Carvalho, City Attorney
By:_____________________
Laura A. Rossini
Chief Assistant City Attorney
AYES: Councilmembers _______________________________________
NOES: Councilmembers _______________________________________
ABSTAIN: Councilmembers _______________________________________
NOT PRESENT: Councilmembers _______________________________________
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, DAISY GOMEZ, Clerk of the Council, do hereby attest to and certify the attached
Resolution No. 2021-XXX to be the original resolution adopted by the City Council of the
City of Santa Ana on _______________.
Date: ________________ ____________________________________
Clerk of the Council
City of Santa Ana
------------------------------------
Exhibit 1
QUOTE
City of Santa Ana
20 Civic Center Plaza
Parks, Recreation and Community Services Agency, M23
SANTA ANA CA 92701
USA
Date
Jan 29, 2021
Expiry
Mar 15, 2021
Quote Number
QU-0579
National Fitness Campaign
LLC
For all questions regarding
this invoice, contact:
info@nfchq.com
Description Quantity Unit Price Tax Amount USD
Fitness Court and National Campaign Resources -
Includes Official Installation Kit
3.00 128,000.00 9.25% 384,000.00
2021 National Grant Funding Award 3.00 (30,000.00) 9.25% (90,000.00)
Freight, Packing and Insurance for shipment 3.00 2,000.00 Tax Exempt 6,000.00
Subtotal 300,000.00
TOTAL CALIFORNIA 9.25% 27,195.00
TOTAL USD 327,195.00
Terms
Terms:
1. PAYMENT TERMS
Purchaser will pay Seller 100% of the Purchase Price within 30 days of the Delivery Date. Purchaser is responsible for payment of shipping
costs, including packing, insurance and freight. These payment terms will apply unless other approved payment terms have been agreed to
by both parties.
2. TAX EXEMPTION
This quoted total is based upon Purchaser's tax exempt status, for which verifying documentation must be provided to Seller. If Purchaser
is not tax exempt, sales tax will be applied before Purchase Price is to be considered final or binding.
Registered Office: PO Box 2367, San Francisco, CA, 94126, USA.
Exhibit 2
CITY OF SANTA ANA FY 20/21CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The Fitness Court is a 32' X 35' outdoor bodyweight circuit training
system that supports 28 simultaneous users on 30 separate pieces
of equipment that are grouped into seven stations. The 7 movement,
7 minute system provides a full-body workout to people of all ability
levels.
PROJECT NEED:
The City of Santa Ana received grants from the National Campaign
Resources to participate as a Model City in the 2021 National Fitness
Campaign. Approval of the multi-site application was based on the City
of Santa Ana's commitment to free health and fitness options and
development of stakeholder consensus.
PROJECT TITLE:
Thornton Park Fitness Court
PROJECT CATEGORY:
Park Facility Improvements
Park Facility
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Parks, Rec. & Community Services Administration Ron Ono, Administrative Services Manager 17-Feb-2021
PROJECT COSTS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
Construction 150,000 ------
TOTAL 150,000 ------
SOURCE OF FUNDS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
7,815 ------
CAPITAL OUTLAY 142,185 ------
TOTAL 150,000 ------
CANNABIS PUBLIC BENEFIT FUND
Exhibit 3
CITY OF SANTA ANA FY 20/21CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The Fitness Court is a 32' X 35' outdoor bodyweight circuit training
system that supports 28 simultaneous users on 30 separate pieces
of equipment that are grouped into seven stations. The 7 movement,
7 minute system provides a full-body workout to people of all ability
levels.
PROJECT NEED:
The City of Santa Ana received grants from the National Campaign
Resources to participate as a Model City in the 2021 National Fitness
Campaign. Approval of the multi-site application was based on the City
of Santa Ana's commitment to free health and fitness options and
development of stakeholder consensus.
PROJECT TITLE:
Heritage Park Fitness Court
PROJECT CATEGORY:
Park Facility Improvements
Park Facility
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Parks, Rec. & Community Services Administration Ron Ono, Administrative Services Manager 17-Feb-2021
PROJECT COSTS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
Construction 150,000 ------
TOTAL 150,000 ------
SOURCE OF FUNDS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
19,095 ------
CAPITAL OUTLAY 130,905 ------
TOTAL 150,000 ------
CANNABIS PUBLIC BENEFIT FUND
Exhibit 3
CITY OF SANTA ANA FY 20/21CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The Fitness Court is a 32' X 35' outdoor bodyweight circuit training
system that supports 28 simultaneous users on 30 separate pieces
of equipment that are grouped into seven stations. The 7 movement,
7 minute system provides a full-body workout to people of all ability
levels.
PROJECT NEED:
The City of Santa Ana received grants from the National Campaign
Resources to participate as a Model City in the 2021 National Fitness
Campaign. Approval of the multi-site application was based on the City
of Santa Ana's commitment to free health and fitness options and
development of stakeholder consensus.
PROJECT TITLE:
Lillie King Fitness Court
PROJECT CATEGORY:
Park Facility Improvements
Park Facility
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Parks, Rec. & Community Services Administration Ron Ono, Administrative Services Manager 17-Feb-2021
PROJECT COSTS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
Construction 150,000 ------
TOTAL 150,000 ------
SOURCE OF FUNDS FY 20/21 FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27
150,000 ------
TOTAL 150,000 ------
CANNABIS PUBLIC BENEFIT FUND
Exhibit 3