Loading...
HomeMy WebLinkAboutItem 12 - Construction Contract for the Westminster Avenue Rehabilitation Project from Newhope Street to Harbor Boulevard and Appropriation AdjustmentPublic Works Agency www.santa-ana.org/public-works Item # 12 City of Santa Ana 20 Civic Center Plaza, Santa Ana, CA 92701 Staff Report September 19, 2023 TOPIC: Award Construction Contract for the Westminster Avenue Rehabilitation Project and Approve Appropriation Adjustment AGENDA TITLE Approve an Appropriation Adjustment, Cooperative Cost Reimbursement Agreement with the City of Garden Grove, and Award a Construction Contract to R.J. Noble Company in the Amount of $1,643,676 for the Westminster Avenue Rehabilitation Project from Newhope Street to Harbor Boulevard with an Estimated Project Delivery Cost of $2,112,595 (Project No. 22-6989) (Non -General Fund) RECOMMENDED ACTION Approve an appropriation adjustment recognizing $542,000 in cost reimbursements from the City of Garden Grove into the Selected Street Construction revenue account, and appropriating the same amount to the Selected Street Construction expenditure account for the Westminster Avenue Improvement Project. (Requires five affirmative votes.) 2. Authorize the City Manager to execute a Cooperative Cost Reimbursement Agreement with the City of Garden Grove for improvements on Westminster Avenue within the Garden Grove jurisdiction from Newhope Street to Harbor Boulevard, subject to non -substantive changes approved by the City Manager and the City Attorney. 3. Authorize budget reallocation of $185,405 in unspent Roadway Maintenance and Rehabilitation Account (SB-1) from the Fairview Rehabilitation from South City Limits to Segerstrom Avenue Improvement (No. 21-6978) Project and $47,595 in unspent Roadway Maintenance and Rehabilitation Account (SB-1) from the Euclid Rehabilitation from First Street to Hazard Avenue Improvements (No. 20-6955) Project to construction funds for the Westminster Avenue Rehabilitation from Newhope Street to Harbor Boulevard Project (No. 22-6989) to complete the project funding requirement 4. Award a construction contract to R.J. Noble Company, the lowest responsible bidder, in accordance with the base bid in the amount of $1,643,676, subject to change orders (not to exceed 25% of the base bid amount) in accordance with the Greenbook: Standard Specifications for Public Works Construction, for construction Construction Contract for the Westminster Avenue Rehabilitation Project from Newhope Street to Harbor Boulevard and Appropriation Adjustment September 19, 2023 Page 2 of the Westminster Avenue Rehabilitation, for the term beginning September 19, 2023 and ending upon project completion, and authorize the City Manager to execute the contract subject to non -substantive changes approved by the City Manager and the City Attorney. 5. Approve the Project Cost Analysis for a total estimated construction delivery cost of $2,112,595, which includes $1,643,676 for the construction contract; $246,551 for contract administration, inspection, and testing; $58,000 for design engineering; and a $164,368 project contingency for unanticipated or unforeseen work. 6. Determine that the recommended actions are exempt from further review in accordance with the California Environmental Quality Act as Categorical Exemption Environmental Review No. ER-2023-77 was filed for the project. DISCUSSION Staff has identified Westminster Avenue from Newhope Street to Harbor Boulevard Project (Exhibit 1) as a priority in the City's pavement management program. The pavement is deteriorating due to weather, age, and heavy usage. The scope of work includes excavation, grading, removal and replacement of asphalt concrete pavement and Portland cement concrete, landscaping, irrigation, and signing and striping. Once completed, the improvements will enhance the streets drivability, visual appearance, accessibility, and drainage issues. The City of Garden Grove shares the right-of-way within the project area; therefore, a Cooperative Cost Reimbursement Agreement is required for the City of Garden Grove to fund their portion of the improvements (Exhibit 2). The Cooperative Cost Reimbursement Agreement between the City of Santa Ana and the City of Garden Grove identifies the roles and responsibilities of each party and has estimated each City's share of the project costs. The City of Garden Grove's cost reimbursement of up to $542,000 includes $58,000 for their share of the Design Engineering costs. Additionally, the City of Garden Grove's total cost reimbursement will be funded by their California Highway Users Tax Account (Gas Tax) allocation. Public Outreach and Contractor Participation To provide an opportunity for local vendors to submit bids, the City notified a total of 900 regional vendors via PlanetBids, many of which are Santa Ana based. Thirty-eight vendors requested bidding documents and a total of five bids were received. Bids were not received from any Santa Ana contractors. As legally required, a Notice Inviting Bids was advertised in the Orange County Register newspaper on June 2, 2023 and June 9, 2023. The project was also advertised in PlanetBids from June 2, 2023 through June 29, 2023. Bids were received electronically via PlanetBids on June 29, 2023. Construction Contract for the Westminster Avenue Rehabilitation Project from Newhope Street to Harbor Boulevard and Appropriation Adjustment September 19, 2023 Page 3 Bid Results Summary Rank Bidder's Name Location Base Bid 1 R.J. Noble Company Orange, CA $1,643,676 2 Onyx Paving Company, Inc. Anaheim, CA $1,693,000 3 All American Asphalt Corona, CA $1,744,103 4 Excel Paving Co Long Beach, CA $1,758,414 5 Hardy & Harper, Inc. Lake Forest, CA $1,830,000 A total of five bids were received, and all were deemed responsive. R.J. Noble Company submitted the lowest responsive base bid in the amount of $1,643,676 (Exhibit 3). As specified in the bid documents, the lowest bid shall be determined on the basis of the Base Bid. Based on the bid analysis and a contractor's reference check, Staff recommends awarding the construction contract to R.J. Noble Company, in the amount of the base bid totaling $1,643,676 (Exhibit 4). R.J. Noble Company has worked satisfactorily on various projects for the City of Santa Ana throughout the last several years. The most recent project was Alton Rehabilitation from Raitt Street to Bristol Street Fiscal Year 2019-2020. Project Delivery To deliver a complete project, in addition to the construction contract, the estimated total project delivery cost includes construction administration, inspection, and testing, along with an allowance for contingencies to account for unexpected or unforeseen conditions. Construction administration and inspection includes construction management; inspection of the Contractor's work to ensure contract compliance, workmanship, and quality; and materials testing. As indicated in the Cost Analysis (Exhibit 5) and as summarized in the table below, the estimated total construction delivery cost of the project is $2,112,595. Project Item Total Construction Contract Bid Amount $1,643,676 Construction Administration, Inspection, Testing $246,551 Contract Contingencies $164,368 Design Engineering $58,000 TOTAL ESTIMATED CONSTRUCTION DELIVERY COST $2,112,595 In order to account for the widespread price increases in construction material, Staff recommends reallocating $233,000 in unspent Road Maintenance and Rehabilitation Account (SB-1) funds to supplement the existing construction funding. Funding was Construction Contract for the Westminster Avenue Rehabilitation Project from Newhope Street to Harbor Boulevard and Appropriation Adjustment September 19, 2023 Page 4 originally allocated to the Fairview Rehabilitation from South City Limits to Segerstrom Avenue Improvement (No. 21-6978) Project and Euclid Rehabilitation from First Street to Hazard Avenue Improvements (No. 20-6955) Project. The Fairview Rehab Project and Euclid Rehab Project will be fully funded with a new budget in the upcoming Fiscal Year 2023-2024 Capital Improvement Program (CIP). ENVIRONMENTAL IMPACT In accordance with the California Environmental Quality Act, the recommended actions are exempt from further review. Categorical Exemption Environmental Review No. ER- 2023-77 was filed for the project. FISCAL IMPACT As indicated in the Cost Analysis, the total construction delivery cost of the project is $2,112,595 which includes construction, contract administration, inspection, testing, and an authorized contingency. Approval of the Appropriation Adjustment will recognize the City of Garden Grove's contribution of $542,000 for project costs into the Select Street Construction, Expense Reimbursement revenue account (No. 05917002-57000) and appropriate the same amount into the Select Street Construction, Improvements Other Than Building expenditure account (No. 05917660-66220). During construction, if necessary, funds may be reallocated between Construction Administration, Inspection, Testing and/or Contingencies. The total construction delivery cost will not be exceeded without Council Authorization. Budget will be reallocated from Project No. 21-6978 and No. 20-6955 to fund this agreement. Project No. 22-6989 is the number assigned to the funding for tracking of all expenditures to deliver the construction of this project. The proposed contract enables Staff to authorize a construction cost increase of up to 25% if necessary for contingencies. Staff expect to utilize other available Public Works appropriations if a contingency becomes necessary to complete the project. If there are no other available appropriations, then Staff will return to City Council with a project update and recommendations. The following table summarizes the funds budgeted and available in current FY 2023-24 (Exhibit 6) for expenditure to deliver construction of this project. Any remaining balances not expended at the end of the fiscal year will be presented to City Council for approval of carryovers to Fiscal Year 2024-2025. Accounting Unit - Accounting Unit - Year Descri Year Account No. Account No. Amount r Fund (Project No.) ption Description EXISTING PROJECT BUDGET 2023-24 05917665-66220 Select Street HUTA Gas Tax — $1,389,000 (22-6989) Construction RMRA, Improvements Other Than Buildings Construction Contract for the Westminster Avenue Rehabilitation Project from Newhope Street to Harbor Boulevard and Appropriation Adjustment September 19, 2023 Page 5 BUDGET REALLOCATION 2023-24 05917665-66220 Select Street H UTA Gas Tax — (From 21-6978 to Construction RMRA, Improvements $185,405 22-6989) Other Than Buildings 2023-24 05917665-66220 Select Street H UTA Gas Tax — (From 20-6955 to Construction RMRA, Improvements $47,595 22-6989) Other Than Buildings APPROPRIATION ADJUSTMENT 2023-24 05917660-66220 Select Street Select Street 22-6989 Construction Construction, $490,595 Improvements Other Than Buildings Total $2,112,595 EXHIBIT(S) 1. Location Map 2. Cooperative Cost Reimbursement Agreement with City of Garden Grove 3. Bid Proposal 4. Construction Contract 5. Cost Analysis 6. CIP Project Sheet Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency Approved By: Kristine Ridge, City Manager EXHIBIT 1 SANTA ANA i Project No. 22-6989: uaJ Westminster Ave Rehabilitation PUBLIC WORKS AGENCY COOPERATIVE COST REIMBURSEMENT AGREEMENT WESTMINSTER BOULEVARD (NEWHOPE ST. TO HARBOR BLVD.) STREET REHABILITATION PROJECT COOPERATIVE COST REIMBURSEMENT AGREEMENT ("Agreement") is made and entered into this ` %day &XV- U , 2023, by and between the CITY OF SANTA ANA, a California charter city ("Santa Ana"), and the CITY OF GARDEN GROVE, a California municipal corporation ("Garden Grove"). In this Agreement, Santa Ana and Garden Grove may each be individually referred to as a "Party" and collectively referred to as the "Parties." RECITALS: WHEREAS, Santa Ana has initiated a street rehabilitation project (the "Project") to improve the street condition of Westminster Blvd. from Newhope St. to Harbor Blvd; and WHEREAS, Westminster Boulevard within the Project limits contain a portion of property within Santa Ana and a portion of the street within the boundary of Garden Grove; and WHEREAS, In an effort to efficiently utilize Garden Grove resources, Garden Grove wishes to improve the portion of Westminster Boulevard within its boundary at the same time the Santa Ana Westminster Boulevard Project is conducted; and WHEREAS, the Parties desire to improve Westminster Boulevard, within their respective boundaries, as part of the "Project". NOW, THEREFORE, based upon the foregoing Recitals, and for good and valuable consideration, the receipt and sufficiency of which is acknowledged by all Parties, the Parties agree as follows: 1. The City of Santa Ana will advertise for bids, hire a contractor, approve the work and administer the contract for street rehabilitation. 2. Garden Grove is responsible for: (a) Garden Grove shall pay Santa Ana for the actual cost of the work within the Garden Grove portion based upon unit prices bid of the Successful Contractor and quantities actually used on the Garden Grove portion as set forth in the Project Location Map (Exhibit A) and the City Cost Sharing (Exhibit B), attached hereto and incorporated by this reference. Garden Grove will remit payment to Santa Ana within thirty (30) days of receipt of invoice evidencing Project work performed within Garden Grove city boundary. (b) Garden Grove shall pay Santa Ana for the actual cost of design engineering and construction engineering services provided for the work within the Garden Grove portion based upon the time spent by Santa Ana staff. Garden Grove will remit payment to Santa Ana within thirty (30) days of receipt of invoice evidencing Project work performed within Garden Grove city boundary. 3. Garden Grove will coordinate the relocation of all affected utility company facilities within the City limits of Garden Grove in a timely manner. 4. Santa Ana and Garden Grove shall extend cooperation to each other and proceed under this Agreement in good faith to facilitate timely completion of the Project. The Parties agree that when any component of this Project is subject to the approval of Garden Grove, such approval shall not be unreasonably withheld. 6. Garden Grove will be notified as to the official advertising dates, bid opening date, construction start date, and overall construction schedule. Also, a representative from Garden Grove will be invited to attend pre -construction, Project status, and final walk through meetings. 6. Change orders for work within Garden Grove must receive the written approval of the Public Works Department Engineering Manager of Garden Grove or his/her designee prior to implementation. Garden Grove is responsible for change order cost within Garden Grove respective boundaries. 7. The following staff members, or as otherwise designated in writing by the Executive Director of Public Works of Santa Ana or the Public Works Department Engineering Manager of Garden Grove, shall be the selected representatives of each City to act on each respective City's behalf with respect to this agreement. Any notices, requests, approvals, plan submittals or communications shall be provided to each representative noted below: City of Santa Ana: ATTN: Rodolfo Rosas, P.E. City Engineer Public Works Agency Santa Ana, CA 92701 20 Civic Center Plaza, M-21 Phone: (714) 647-3379 E-Mail: rrosas@santa-ana.org City of Garden Grove: ATTN: Dan Candelaria, P.E.,TE City Engineer Public Works Department 11222 Acacia Parkway Garden Grove, CA 92840 Phone: (714) 741-5185 E-Mail: danc@ci.garden-grove.ca.us 8. Santa Ana shall cause its contractor for the Project to guarantee the Garden Grove improvements against defects in workmanship and materials for a period of one (1) year from the date of acceptance by Santa Ana. It is further agreed that Santa Ana shall assume the responsibility for causing the Garden Grove improvements to be brought or restored to full compliance with the requirements of the Plans and Specifications for any portion of the Project which during said one (1) year period are found not to be in conformance with the provisions of the Plans and Specifications. 9. The City of Santa Ana shall have its contractor provide insurance as follows: 9.1 INSURANCE AMOUNTS. Contractorshall maintain the following insurance forthe duration of this Agreement: (a) Commercial general liability in the amount of $1,000,000 per occurrence; (claims ►Wade and modified occurrence policies are not acceptable); Insurance companies must be acceptable to City and have an AM Best's Guide Rating of A- Class VII or better, as approved by the City. If Contractor maintains broader coverage and/or higher limits than the minimums shown above, the City shall be entitled to the broader coverage and/or higher limits maintained by the Contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City. An Additional Insured Endorsement, ongoing and completed operations, for the policy shall designate the City of Santa Ana, the City of Garden Grove, their officers, officials, employees, agents, and volunteers as additional insureds for liability arising out of work or operations performed by or on behalf of the Contractor. Contractor shall provide to City proof of insurance and endorsement forms that conform to City's requirements, as approved by the City. (b) Automobile liability in the amount of $1,000,000 combined single limit, including mobile equipment if applicable; (claims made and modified occurrence policies are not acceptable); Insurance companies must be acceptable to City and have an AM Sest's Guide Rating of A-, Class VII or better, as approved by the City. An Additional Insured Endorsement for the policy shall designate the City of Garden Grove, the City of Santa Ana, their officers, officials, employees, agents, and volunteers as additional insureds for automobiles owned, leased, hired, or borrowed by the Contractor. Contractor shall provide to City proof of insurance and endorsement forms that conform to City's requirements, as approved by the City. (c) For any claims related to this Agreement, Contractor's insurance coverage shall be primary insurance as respects City, its officers, officials, employees, agents, and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees, agents, or volunteers shall be in excess of the Contractor's insurance and shall not contribute with it. 9.2 WORKERS COMPENSATION INSURANCE. For the duration of this Agreement, Contractor and all subcontractors shall maintain Workers Compensation Insurance in the amount and type required by law, if applicable. The insurer shall waive its rights of subrogation against the City of Garden Grove, the City of Santa Ana, their officers, officials, agents, employees, and volunteers. 9.3. CONTRACTOR shall not commence work until all certificates and endorsements have been received and approved by Santa Ana. All insurance required shall contain a Statement of Obligation on the part of the carrier to notify City of any material change, cancellation, or termination at least thirty (30) days in advance, 10. This Agreement contains all of the agreements of the Parties regarding the Project and all previous understandings, negotiations and agreements regarding the Project are integrated into and superseded by this Agreement. 11. This Agreement may be amended at any time by the mutual consent of the Parties by an instrument in writing signed by both Parties. 12. In the event that any one or more of the phrases, sentences, clauses, paragraphs, or sections contained in this Agreement shall be declared invalid or unenforceable by a valid judgment or decree of a court of competent jurisdiction, such invalidity or unenforceability shall not affect any of the remaining phrases, sentences, clauses, paragraphs, or sections of this Agreement which are hereby declared as severable and shall be interpreted to carry out the intent of the Parties hereunder, 13. The persons executing this Agreement on behalf of the Parties hereto warrant that they are duly authorized to execute this Agreement on behalf of said Parties and that by so executing this Agreement the Parties hereto are formally bound to the provisions of this Agreement. 14. This Agreement shall be binding upon and shall endure to the benefit of the Parties hereto and their respective heirs, personal representatives, successors, and assigns. 15. This Agreement may be executed by the Parties and counterparts, which counterparts shall be construed together and have the same effect as if all of the Parties had executed the same instrument. 16. This Agreement is to be governed by the laws of the State of California, in Orange County California. 17. Each party agrees to defend, hold harmless, and indemnify the other as to any and all claims, judgments, liabilities or damages for injuries and damages directly arising out of each party's own performance under this Agreement, except to the extent such damage or expense is caused in whole or in part by the other party's negligence or willful misconduct. IN WITNESS WHEREOF, the Parties hereto have caused this Agreement to be executed on the day and year first written above. CITY OF SANTA ANA CITY OF GARDEN GROVE Kristine Ridge Lisa Kim City Manager City Manager ATTEST: 3170a: Jennifer L. Hall TERESA POMEROY Clerk of the Council City Clerk City Clerk APPROVED AS TO FORM: ZVAKt&(�bM ROVED A TOLFO.: SONIA R. CARVALHO City AttorneyVAL City Attorney BY; qw. T ._ JOHN M. FUNK Assistant City Attorney RECOMMENDED FOR APPROVAL: Nabil Saba, P.E. Executive Director Public Works Agency Exhibit A Location Map Westminster Boulevard (Newhope St. to Harbor Blvd.) Street Rehabilitation Project Legend ONO - Project Location Exhibit A SANTA ANA PP A Project No. 22-6989: -J Westminster Ave Rehabilitation PUBLIC WORMAGENGY From Newhope St to Harbor Blvd $AN['A A'NA EXHIBIT B City Cost Sharing Westminster Boulevard (Newhope St. to Harbor Blvd.) Street Rehabilitation Project City of Santa Ana Cost Table 1 City of Garden Grove Cost Table 2 CITY OF SANTA ANA Prieparer: AV Reviewer: GC Project No,: 22-6989 Date Revised: 05/30/23 Date Reviewed; EXHIBIT B - TABLE I COST ESTIMATE-SANTA ANA 22-6989 - Westminster Avenue Rehabilitation Newhope St to Harbor Blvd MIA OR M '2, "0. K -.'-k RRlfi3.''�95 Klr I Unclassified Excavation Cy 870 a ?$ 243,600,00. 2 Asphalt Concrete TN 1,240 $ 248,000,00 3 Cold Mill (2") SF 178,000 $ 178,000.00 4 Asphalt Rubber Hot Mix (ARHM) 1W 2,500 $ 650,000.00 5 PCC Sidewalk (T=4") SF 5,800 81,200.00 6 PCC DrivewM Approach (T�8") SF 1,100 $ 27,500.00 7 PCC Curb Ramp SF '800 I N $ 14,400.00 8 PCC Curb and Gutter (Type A-2-8) LF 500 $ 25,000.00 9 PCC (13-1) Curb (Including Steel Rebar Dowels) LF 100 $ 2,500.00 10 Root Shave* EA 5 $ 3,300.00 I I Adjust Water Valve Frame and Cover Per CSA STD, EA 22 - NMI $ 24,200,00 12 Adjust Water Vault Frame and Cover Per CSA STD, EA 1 $ 1,600,00 13 Adjust Water Meter Frame and Cover Per CSA STD. EA 6 $ 4,800,00 14 Adjust Manhole Frame and Cover Per CSA STD, EA 23 $ 27,600,00 15 Adjust Manhole Frame and Cover Per OCFCD STD, EA 3 $ 6,000,00 16 Parkway Culver Type B EA 2 V $ 800,00 17 Furnish and Install New #6 Pullbox EA 4 $ 4,400.00 18 Adjust Survey Monument Frame and Cover EA 2 aOk-, U_ 4,000.00 19 Furnish and Install Traffic Loops Ty" D t EA 28 $ 14,000.00, 20 Furnish and Install Traffic Loops Type, E t EA 56 ki M M . $ 28,000.00 21 Furnish and Install Traffic Loops Type Q t EA 2 $ 1,000.00 22 Project Advertisement Sign EA 1 $ 1,000.00 23 Signing and Striping LS I $ 39,200.00 24 As -Built Plans LS 1 W$ 3,500,00 IWO - N 23 Construction Permits EA I 7,000.00 _T Elm_ Contingency 10% 164,000.00 Construction Engineering g "�X _n .0 _Rg 'R g 15% 246,000.00 Vv. CITY OF SANTA ANA Project No.: 22-6989 Preparers AV Date Revised: 05 30/23 Reviewer: GC - Nick Hsieh Date Reviewed: EXHIBIT B - TABLE 2 COST ESTIMATE- GARDEN GROVE 22-6989 - Westminster Avenue Rehabilitation Newhope St to Harbor Blvd 1 r w � ..�^...t:�5r�'u- NS- M' ^ .,,.,F,..... Unclassified Excavation ........,. .., ,w l�N1vE>ui }p� ._..,.. .".,..,....._ .x ,...,,... Cy 170 $ 47,600.00 2 Asphalt Concrete TN 210 $ 42,000.00 3 Cold Mill (2") SF 35,000 w$ 35,000.00 4 Asphalt Rubber Hot Mix (ARHM) TN 500 $ 130,000.00 5 PCC Sidewalk (T= 4") SF 1,400 _ - $ 19,600,00 6 PCC Curb Ramp SF 1,000 ;r $ 18,000.00 7 Truncated Domes EA 3 S 4,500.00 8 PCC Curb and Gutter (Type A-2-8) LF 300 - $ 15,000.00 9 Furnish and Install Water Valve Lid and Slip Can Per GG STD EA 26 e $ 31,200.00 10 Adjust Manhole Frame and Cover Per GG STD. EA 2 $ 4,000,00 11 Adjust Manhole Frame and Cover Per OCSD STD, EA 2 a $ 4,000.00 12 Furnish and Install Manhole Per GG STD, EA 1 ". , $ 2,500.00 13 Install FABCO CPS Unit EA 5 3 ; �. $ 8,000.00 14 Catch Basin Top Slab Reconstruction LS 1 V11, =� �}.N:"a1 $ 10,000,00 15 Project Advertisement Sign EA 1 $ 1,000.00 16 Signing and Striping LS 1 Q $ 13,000.00 17 As-BuiltPlans LS ] $ 1,500.00 Design Engineering 15% $ 58,000.00 Contin envy 10% $ 39,000.00 •.zsx..'i�'^°f f3.,..m_.,m � m � � .: �. Construction Engineering T e _.. , qoa EXHIBIT 3 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6989 WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE Sr TO HARBOR BLVD BID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: R.J. NOBLE COMPANY REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following schedule: Item Description Qtyi Unit Unit Price Amount I Unclassified Excavation • 1,040 CY $ S 191.00 198,640.00 2 Asphalt Concrete • 1,450 n J 165.00 $ 239,250.00 3 Cold Mill (2") • 213.000 SF $ $ 0.70 149,100.00 4 Asphalt Rubber Hot Mix (ARHM) 3,000 IN $ S 164.00 492,000.00 S PCC Sidewalk (T=4") 7,2W SF S S 11.00 79,200.00 6 PCC Driveway Approach (T=8") 1,100 SF $ S 17.50 19,250.00 7 PCC Curb Ramp 1,800 SF $ $ 31.00 55,800.00 8 Truncated Domes 3 EA S 1 S 1,100.00 3,300.00 9 PCC Curb and Gutter (Type A-2-8) 800 LF S S 80.50 64,400.00 10 PCC (B-1 I Curb (Including Steel 100 LF $ $ Rebar Dowels) 49.50 4,950.00 11 Root Shave- 5 EA $ $ 550.00 2,750.00 12 Adjust Water Valve Frame and 22 EA S 5 Cover Per CSA STD. 1,550.00 34)100.00 13 Furnish and Install Water Valve Lid 26 EA $ $ and Slip Can Per GG STD. 304.00 7,904.00 P-1 ofP-17 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6989 WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE ST TO HARBOR BLVD Item Description Qt Unit Unit Price Amount 14 Adjust Water Vault Frame and 1 EA $ $ Cover Per CSA STD. 8,800.00 8,800.00 15 Adjust Water Meter Frame and 6 EA $ $ Cover Per C S A STD. 1,100.00 6,600.00 16 Parkway Culvert Type B 2 EA $ $ 8,050.00 16,100.00 17 Adjust Manhole Frame and Cover 23 FA $ $ Per C S A STD. 1,460.00 33,580.00 18 Adjust Manhole Frame and Cover 2 EA $ $ PerGG STD. 1,460.00 2,920.00 19 Adjust Manhole Frame and Cover 2 EA $ $ Per OCSD STD. 2,120.00 4,240.00 20 Adjust Manhole Frame and Cover 3 EA $ $ Per OCFCD STD. 2,120.00 6,360.00 21 Furnish and Install New Manhole 1 EA $ $ PerGG STD. 2,200.00 2,200.00 22 Furnish and Install New #16 Pullbox 4 EA $ $ 1,320.00 5,280.00 23 Adjust Survey Monument Frame 2 EA $ $ and Cover 1,450.00 2,900.00 24 Install FABCO CPS Unit 5 EA S $ 4,659.60 23,298.00 25 Catch Basin Top Slab 1 EA $ $ Reconstruction 19,250.00 19,250.00 26 Furnish and Install Traffic Loops 28 EA $ $ Type D t 358.00 10,024.00 27 Furnish and Install Traffic Loops 56 EA $ $ ThxEt 330.00 18,480.00 28 Furnish and Install Traffic Loops 2 EA $ $ Type Q t • 360.00 720.00 29 Project Advertisement Sign I EA $ $ 1,100.000 1,100.00 30 Signing and Striping 1 LS $ S 121,500.00 121,500.00 31 As -Built Plans I LS $5,000 $5,000 P-2 of P-17 ADDENDUM NO ONE CITY OF SANTA ANA PROJECT NO 22-6989 PROPOSAL PROJECT NO.: 22-6989 WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE ST TO HARBOR BLVD Item Description Qty Unit Unit Price Amount 32 Construction Permits I LS $4,680 $4,680 TOTAL BASE BID 1,643,676.00 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" limit as stated in Section 3-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications. TIME FOR COMPLETION CF IMPROVEMENTS AND LIOU IDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within sixty (60) working days after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $2,700 per calendar day. Name of Firm R.J. NOBLE COMPANY Signature of BIDDER X 11/Y_ 1___ __________________ Title JACOB BREEDLOVF/SLWyARY (I f an individual, so state. I f a fiml o- rco-partnership, state the firm name and give the names of all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-3ofP-17 EXHIBIT 4 CITY OF SANTA ANA CONSTRUCTION CONTRACT PROJECT 22-6989 WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE ST TO HARBOR BLVD This CONSTRUCTION CONTRACT is made and entered into this 0 day of September, 2023 by and between the City of Santa Ana, California, a charter city and municipal corporation organized and existing under the Constitution and laws of the State of California (hereinafter "CITY"), and R.J. Noble Company (hereinafter "CONTRACTOR"). WITNESSETH: The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows: 1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction of the City Engineer of the CITY, the WESTMINSTER AVENUE REHABILITATION (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contract Documents prepared by the City's Public Works Agency and approved by the City Council. 2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard Specifications for Public Works Construction and which include the following: • Notice Inviting Bids • Information to Bidders • Bid Proposal • Bid Bond • Contract Form • Contract Bonds • General Provisions • Special Provisions • Technical Provisions and Project Plans • Community Workforce Agreement • Appendices In case of conflict between the Contract Documents, the precedence of documents shall be as established in the Standard Specifications for Public Works Construction. 3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK OF IMPROVEMENT the sum total amount not to exceed One Million Six Hundred Forty -Three Thousand Six Hundred Seventy -Six Dollars and No Cents ($1,643,676.00), as set forth and identified in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A," and in accordance with Section 2-7.1 of the Greenbook: Standard Specifications for Public Works Construction. 4. The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate quantities only, and the City does not expressly or by implication agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work or to omit portions of the work as may be deemed necessary or advisable. rev. 09/01/2017 Page 1 of 3 5. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including commencing construction within the timeframe therein specified after issuance of a Notice to Proceed. 6. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for such work as set forth in the wage determinations for this work in accordance with applicable State and Federal law. 7. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement (CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website at: httl://www.santa-ana.ora/pwa/documents/CWA.pdf 8. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY, one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%) of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment Bond). This Contract shall not become effective until such bonds are supplied to and approved by the CITY. 9. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000) or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars ($100,000) or Ten Percent (10%) of the final contract price. 10. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY. 11. INDEMNIFICATION. To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend, indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents, employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"), through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs, damages or losses, including reasonable costs and attorney's fees, for injury, including death to any person or damage to any property, arising directly or indirectly from, or in any manner relating to, any of the following: (i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its Subcontractors of any lower tier; (ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, of any of the obligations under the Contract Documents; Page 2 of 3 (iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either on the project site or on other properties; (iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower tier, for Work of Improvement performed on or off the project site; and (v) Any personal injury, property damage or economic loss to third persons related to and arising from the performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier, of the Work of Improvement. (vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all subcontract documents issued by CONTRACTOR. Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in favor of CONTRACTOR against CITY or any other Indemnitee. IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and year first above written. ATTEST: JENNIFER L. HALL City Clerk APPROVED AS TO FORM: SONIA R. CARVALHO City Attorney I0 �� n;J;j� JOSE MONTOYA Assistant City Attorney RECOMMENDED FOR APPROVAL: NABIL SABA, PE Executive Director Public Works Agency CITY OF SANTA ANA KRISTINE RIDGE City Manager CONTRACTOR: R.J. NOBLE COMPANY il NAMtSTIN M. CARVER TITL ident Page 3 of 3 CALIFORNIA ACKNOWLEDGMENT CIVIL CODE § 1189 A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, orvalidity of that document. State of California County of _ORANGE 08/29/2023 On Dote before me, personally appeared JACOB BREEDLOVE J. DEIONGH, NOTARY PUBLIC Here Insert Nome and Title of the Officer Nome(s) of Signer(s) who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/afe subscribed to the within instrument and acknowledged to me that he/&heA4ey executed the same in his e;; authorized capacity(ies), and that by his/berhhair signatures) on the instrument the person(s), or the entity upon behalf of which the persons) acted, executed the instrument. \ J.OEIONGH { ` Notary Public California Orange county z Commissian>72307aa1 �Mr Comm Expires Oct 28, 2023 Place Notary Seal ond/or Stomp Above I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct_ WITNESS my hand and official seal. Signature r I / nature of Notary Public Vi I wvvm+ Completing this information con deter alteration of the document or fraudulent reattachment of this form to an unintended document. Description of Attached Document Title or Type of Document: Document Date: Signer(s) Other Than Named Above: Capacity(ies) Claimed by Signer(s) Signer's Name: ❑ Corporate Officer — Title(s): ❑ Partner — ❑ Limited ❑ General ❑ Individual ❑ Attorney in Fact ❑ Trustee ❑ Guardian or Conservator ❑ Other: Signer is Representing: Number of Pages: Signer's Name: ❑ Corporate Officer — Title(s): ❑ Partner — ❑ Limited ❑ General ❑ Individual ❑ Attorney in Fact ❑ Trustee ❑ Guardian or Conservator ❑ Other: Signer is Representing: t�eee 02018 National Notary Association MAYOR Valerie Amezcua MAYOR PRO TEM Jessie Lopez COUNCILMEMBERS Phil Bacerra Johnathan Ryan Hernandez David Penaloza Thai Viet Phan Benjamin Vazquez June 22, 2023 ADDENDUM No. 1 CITY OF SANTA ANA PUBLIC WORKS AGENCY 20 Civic Center Plaza • P.O. Box 1988 Santa Ana, California 92702 www.santa-ana.oro ADDENDUM NO. ONE PROJECT NO 22-6989 CITY MANAGER Kristine Ridge CITY ATTORNEY Sonia R. Carvalhc CITY CLERK Jennifer L. Hall SUBJECT: Project No. 22-6989 - WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE ST TO HARBOR BLVD The following changes/revisions/clarifications have been made to the plans and/or specifications for subject project: Specifications NOTICE INVITING BIDS: Replace page iv with new page iv, (Bid due date extended) BID PROPOSAL: Replace page P-3 of P-17 with new page P-3 of P-17. (Unit price for item 32 has been revised) SPECIFICATIONS: Replace page 26, 27, 28 and 44 with new pages 26, 27, 28 and 44. DEFINITION OF BID ITEMS: Replace pages 1, 2, 3, 4, 5, 6 and 7 with new pages 1, 2, 3, 4, 5, 6and 7. Plans 1. SHEET 01 OF 06 and SHEET 03 of 06: (Construction note 9G has been modified) All other terms and conditions remain the same. FOR THE CITY OF SANTA �4o olfo R as, P. Deputy Public Works Director/City Engineer SANTA ANA CITY COUNCIL valene Amezcw .,essa Lopez 'ra: Viet Phan Benito— azauez Phi Baca- Jannatnin Ryan ^+emanaez David Penaloza t,13y01 t:,ayor Pic, Ten, _' `:tiara Vlard -1J✓ara 4 Aard ` .'; afa f. vdmeZ:�d.,l5dntd-dnd VrO ESS,eIOCGZ,1Sinid-an3 Gro ID^dnQS)n�d•dnd or /dnneMal oe2'nSanlJ•ina CrC COenil0il4�3niJ-dnd -f^ CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6989 WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE ST TO HARBOR BLVD BID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: R.J. NOBLE COMPANY REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if an)) and the specifications for the unit price(s) or lump sum(s) set forth in the following schedule: Item Description Qty Unit Unit Price Amount l Unclassified Excavation • 1.040 CY S S 191.00 19a,640 00 2 Asphalt Concrete • 1.450 TN S S 165.00 239,250.00 3 Cold Mill (2") 213.000 SF S S 0.70 149,100.00 4 Asphalt Rubber Hot Mix (ARH.M)' 3,000 Tv S S 164.00 492,000.00 5 PCC Sidewalk IT_4") 7,200 SF S S 11.00 79,200.00 6 PCC driveway Approach (T-8") 1.100 SF S $ 17.50 19,250.00 7 PCC Curb Ramp 1,800 SF S S 31.00 55,800.00 S Truncated tomes 3 £A S S 1,100.00 3,300.00 9 PCC Curb and Gutter (Type A-2-8) goo LF S S 80.50 64,400.00 10 PCC (IB-1 ) Curb I Including Steel 100 LF S S Rebar Dowels) 49.50 4,950.00 11 Root Shave* 5 EA S S 550.00 2,750.00 12 Adjust water Valve Frame and 22 EA S S Cover Per CSA STD, 1,550.00 34,100.00 13 Furnish and Install Water VaNe Lid 26 EA S S and Slip Can Per GG STD. 304.00 7,904.00 P-I of P-17 CITY OF SANTA ANA PROPOSAL PROJECT NO.: 22-6989 WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE ST TO HARBOR BLVD Item Description Qty Unit Unit Price Amount 14 Adjust Water Vault Frame and 1 EA S S Cover Per CSA STD. 8,800.00 8,800.00 15 Adjust Water Meter Frame and 6 EA S $ Cover Per CSA STD. 1,100.00 6,600.00 16 Parkway Culvert Type B 2 EA S $ 8,050.00 16,100.00 17 Adjust Manhole Frame and Cover 23 EA S $ Per CSA STD. 1,460.00 33,580.00 18 Adjust Manhole Frame and Cover 2 EA S S Per GG STD. 1,460.00 2,920.00 19 Adjust Manhole Frame and Cover 2 EA S S Per OCSD STD. 2,120.00 4,240.00 20 Adjust Manhole Fume and Cover 3 EA S $ Per OCFCD STD. 2,120.00 6,360.00 21 Furnish and Install New Manhole 1 EA $ $ Per GG STD. 2,200.00 2,200.00 22 Furnish and Install New #6 Pullbox 4 EA S $ 1,320.00 5,280.00 23 Adjust Survey Monument Frame 2 EA S $ and Cover 1,450.00 2,900.00 24 Install FABCO CPS Unit 5 EA 4 S 659.60 23,298.00 25 Catch Basin Top Slab I EA S $ Reconstruction 19,250.00 19,250.00 26 Furnish and Install Traffic Loops 28 EA S S Type D t 358.00 10,024.00 27 Furnish and Install Traffic Loops 56 EA $ $ Type E t 330.00 18,480.00 28 Furnish and Install Traffic Loops 2 EA S S Type Q t • 360.00 720.00 29 Project Advertisement Sign I EA S S 1,100.000 1,100.00 30 Signing and Striping 1 LS S 121, 500.00 $ 121, 500.00 31 As -Built Plans I LS $5,000 $5,000 P-2 of P-17 ADDENDUM NO ONE CITY OF SANTA ANA PROJECT NO 22-6989 PROPOSAL PROJECT NO.: 22-6989 WESTMINSTER AVENUE REHABILITATION FROM NEWHOPE ST TO HARBOR BLVD Item Description Qty Unit Unit Price Amount 32 Construction Permits I LS $4,680 $4.680 TOTAL BASE BID 1 S 1,643,676.00 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the " 25%" limit as stated in Section 3-2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. t This bid item is considered a Specialty Item per Section 2-3.2 of the Standard Specifications. TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within sixty 60) working days after the commencement date stated in the Notice to Proceed. The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be S2300 per calendar day. Name of Firm R.J. NOBLE COMPANY Signature of BIDDER k Title JACOB BREEDLOVF;/SLL40�AR)" (If an individual, so state. If a' f rn co -partnership. state the firm name and give the names of all individual co-partners composing the firm. If a corporation. state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-3 of P-17 EXHIBIT 4 COST ANALYSIS CONSTRUCTION OF PROJECT NO. 22-6989: Westminster Ave Rehabilitation from Newhope St to Harbor Blvd Construction Contract $ 1,643,676.00 Contract Administration, Inspection and Testing $ 246,551.00 Contingencies $ 164,368.00 Design Engineering (Garden Grove) $ 58,000.00 TOTAL ESTIMATED CONSTRUCTION COSTS $ 2,112,595.00 EXHIBIT 6 PROJECT TITLE: WestminsterA venue Rehabilitation: Newhope St to Harbor Blvd PROJECT CATEGORY: Street Improvements Arterial Street Rehabilitation LOCATION MAP 1 AGENCY: Public Works CITY OF SANTA ANA FY 21/22CIP CAPITAL IMPROVEMENT PROJECT WORKSHEET PROJECT DESCRIPTION: Roadway reconstruction along with miscellaneous concrete repairs to address accessibility and drainage issues along this segment of roadway. PROJECT NEED: This segment of WestminsterA venue has been identified as a priority by the City's Pavement Management System. The pavement is deteriorating due to weather, age, and heavy usage. PROJECT COSTS FY 21/22! FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 Construction 1. 3 8 9 .o o o - - - - - - Engineering 111,000 - - - TOTAL 1,500,000 - - - - - - SOURCE OF FUNDS FY 21/22 FY 22/23 FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 RMRASB1 1.s� � .000 - - - - - - TOTAL 1,500,000 - - - - - - DIVISION: Design Engineering CONTACT: Mike Ortiz, Senior Civil Engineer DATE: 11-May-2021