Cy VW A C2) FIRST AMENDMENT TO AGREEMENT WITH
ELS ARCHITECTURE AND URBAN DESIGN TO PROVIDE
LANDSCAPE ARCHITECTURAL SERVICES
THIS FIRST AMENDMENT to the above -referenced agreement is entered into on
December 5, 2023, by and between ELS Architecture and Urban Design ("Consultant"), and the
City of Santa Ana, a charter city and municipal corporation organized and existing under the
Constitution and laws of the State of California ("City"). (Consultant and City are also referred
to as the "Parties.")
RECITALS
A. The Parties entered into Agreement No. A-2023-150 ("Agreement") dated August 15,
2023 to provide master planning, preparation of contract documents, and construction
support for the new Memorial Park and Aquatics Facility Renovation. The Agreement
term runs until August 14, 2026 and is current and in effect.
B. The parties now wish to amend the Agreement to revise the scope of services to include a
"two -pool concept aquatic center" and increase the overall compensation in consideration
of the increased scope under the Agreement. No other changes are contemplated by this
First Amendment.
The Parties therefore agree:
1. Section 1, Scope of Services, is amended as follows:
a. Exhibit A-1 to this First Amendment shall replace the schematic drawing, marked as
Exhibit 1, on the last page of Exhibit A.
b. Exhibit B-1 to this First Amendment, identified as the October 23, 2023 proposal for
a request for additional services, shall be included as part of the Consultant's proposal
in Exhibit B.
2. Section 2.a., Compensation, is hereby amended to increase the total compensation by one
million, seventy-nine thousand dollars and no cents ($1,079,000.00). The total
compensation amount for this Agreement shall not exceed two million, eight hundred and
fifty-eight thousand, one hundred and seventy dollars and no cents ($2,858,170.00). Rates
and charges shall be amended to include Exhibit C-1 to this First Amendment.
Except as modified by this First Amendment, all terms and conditions of the Agreement
shall remain in 11111 force and effect.
[signature page to follow]
SIGNATURE PACE TO FIRST AMENDMENT TO AGREEMENT WITH
ELS ARCHITECTURE AND URBAN DESIGN TO PROVIDE
LANDSCAPE ARCHITECTURAL SERVICES
IN WITNESS WI IEREOF, the parties hereto have executed this First Amendment to the
Agreement on the date and year first written above.
ATTEST:
1 i
,j
ennifer,. II
erk
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
�� �✓�:-� Gip/
Jonathan T. Martinez /
Assistant City Attorney
RECOMMI NDED FOR APPROVAL:
Nabil Saha
L•'xecutive Director
Public Works Agency
CITY OF SANTA ANA
Z�y&
Tom Hatch
Interim City Manager
ELS ARCHI'I L( 11 10', \\I)
URBAN DESIGN
IJ
Project Manager/Principal in Charge
EXHIBIT A-1
m
is HRMOIA s
2IONNW
co
Y �5
w
1S N3M0l3 'S
EXHIBIT B-1
e's + architecture+
urban design
Santa Ana Memorial Park Master Plan and Aquatic Center
Additional Service Request No. 03
Scope increase to include two -pool concept aquatic center, as recently presented during community
engagement process and represented in the attached Memorial Park Master Plan dated October 21,
2023 — Please see attached Exhibit A
Date
October 23, 2023
TO
Suzi Furianic, City of Santa Ana
From
Clarence Mamuyac/Kenneth Hasegawa
Project
Santa Ana Memorial Park Master Plan and Aquatic Center
Subject
Request for Additional Service Fees No. 3
ELS requests an increase in contract fees for the following:
Advancing the Aquatic Center Concept for Memorial Park from a single pool aquatic center and
construction budget of $12MM, to a two -pool aquatic center concept with a construction budget of
$22MM. Some of the effort for this increased scope has been completed under PART I — Concept
Planning (30%), but most of the increased scope will be carried forth under PART It — Contract
Documents (60%, 90% and 100%). Construction Support is included as an optional service.
In the interest of time, and while this ASR #3 is processed, we are requesting an email authorization
to advance the scope of the work described above, as part of PART II — 60% (Design Development)
scope per our contract. We would like to receive that email authorization by 5pm on Monday,
October 23.
Please see our Fee Matrix, Exhibit B for a breakdown (by PART and TASK) of our lump sum, not -to -
exceed fee increase of $1,079,000.00 for the scope described in this ASR. The effort will include ELS
Architecture and Urban Design and SWA Landscape Architects, as well as the following:
• Aquatic Design Group (Pools)
• KPFF (Civil)
• John A Martin and Associates (Structural)
• Guttmann & Blaevoet (MEP)
• Mack5 (Cost Estimating)
If the City of Santa Ana is agreeable to the above, please sign below and return a signed copy to our
office, or we will look forward to receiving an amendment to our agreement. This Additional
Services Request will increase our total contract dollar amount by $1,079,000.00 (One Million,
Seventy -Nine Thousand Dollars and Zero Cents) + Reimbursable Expenses.
2040 Addison Street Berkeley, CA 94704 510.549.2929 elsarch.com
els +
architecture+
urban design
Thank you in advance for your consideration. Should you have any questions, please do not hesitate
to contact us.
APPROVED
Suzi Furjanic, AIA
Associate Park & Landscape Planner
City of Santa Ana, Public Works Agency
Attachments:
• Memorial Park Master Plan, Dated 10/21/2023
• Fee Matrix, dated 10/22/2023
End of Additional Service Request No. 3
2040 Addison Street Berkeley, CA 94704 510.549.2929 elsarch.com
!
-
(
§
§
-
4
�
.
;/!
-
§2
0§
f
:
/
En
2
■ |i§:
6.0 '
�
�
:
�
�
�
�
From:
City of Santa Ana
To:
Rodriguez Teresa, Furianic, Suzi
Subject:
Internal Notice of Compliance
Date:
Monday, September 18, 2023 9:34:14 AM
LB
NOTICE OF COMPLIANCE
CITI STAFF: PRINT TI [IS PAGE AND INCLI DE NN I I'H AGREE.NIEN I TO TIIE ('LERE OF THE COI'N('IL
Contractor ELS Architecture and Urban Design
Name:
Project TBD (018)
Number:
Consultant Agreement Between ELS Architecture And
Project Urban Design, And The City Of Santa Ana For Landscape
Name: Architectural Services For Memorial Park And Aquatics
Facility Renovation
The Certificate of Insurance (COI) submitted indicates that the coverages are in
compliance with the insurance requirements. No further action is required at this
time.
The compliant coverage(s) are:
AUTOMOBILE LIABILITY
GENERAL LIABILITY
PROFESSIONAL LIABILITY
POLICY EXPIRATION NUMBER DATE COI DATE FILE NAME
PSA0002551 10/01/2024 09/11/2023 Santa Ana
COI 2024.pdf
PSB0001596 10/01/2024 09/11/2023 Santa Ana
COI 2024.pdf
22-23 City of
031565618 06/10/2024 07/27/2023 Santa Ana —
Liability
Certificate.pdf
WORKERS COMPENSATION AND PSW0002642 10/01/2024 09/11/2023
EMPLOYERS' LIABILITY
Thank you,
City of Santa Ana
Santa Ana
COI 2024.pdf