HomeMy WebLinkAboutItem 17 - Amend CIP for First Street Slope Stabilization ProjectPublic Works Agency www.santa-ana.org/public-works Item # 17 City of Santa Ana 20 Civic Center Plaza, Santa Ana, CA 92701 Staff Report July 16, 2024 TOPIC: First Street Slope Stabilization Project AGENDA TITLE Additional Contingency Funds in the Amount of $625,000 for an Existing Construction Contract with EverLevel Holdings, LLC for the First Street Slope Stabilization Project (Project No. 22-1341) (Revive Santa Ana Program) RECOMMENDED ACTION 1. Approve an amendment to the Project Cost Analysis in the amount of $625,000 in additional contingency funds for a new total estimated construction delivery cost of $6,725,000. 2. Approve an amendment to the Fiscal Year 2024-25 Capital Improvement Program to include $625,000 of American Rescue Plan Act (ARPA) funds for the First Street Slope Stabilization Project (22-1341). GOVERNMENT CODE §84308 APPLIES: Yes DISCUSSION The Public Works Agency is overseeing the construction of the First Street Slope Stabilization Project (Project). The Project includes the installation of decorative concrete along the slopes near the railroad undercrossing, new security fencing, and a stormwater treatment device (Exhibit 1). The goal of the project is to improve water quality and address stormwater pollution via the stabilization of the dirt slopes, elimination of trespassing and encampments, and installation of a stormwater treatment device. The project will also enhance the aesthetics of this important gateway to Downtown Santa Ana. On December 20, 2022, the City Council awarded a construction contract to EverLevel Holdings, LLC for the First Street Slope Stabilization Project. The project is currently under construction and is anticipated to be completed in September 2024. The original contingency amount of $450,000 was utilized via change order #1 to deal with unforeseen site conditions, install skate stoppers, widen the sidewalk by 18 inches for ADA compliance, and facilitate other necessary changes triggered by the sidewalk widening, such as the installation of new curb and gutter, and improvements to the anchor wall (Exhibit 2). $625,000 of additional contingency funding is needed to facilitate potential change orders on the northside slope so it is consistent with the First Street Slope Stabilization Project July 16, 2024 Page 2 southside slope, replace damaged curb and gutter, improve drainage around the stormwater lift station, install additional security fencing, and deal with unforeseen site conditions and unsuitable soil. The recommended action will increase the project contingency by $625,000, thereby increasing the total estimated construction delivery cost to $6,725,000, as indicated in the Cost Analysis (Exhibit 3) and as summarized in the table below: Project Item Current Total Additional Funding New Total Construction Contract Bid Amount $5,018,520 $0 $5,018,520 Construction Administration, $581,000 $0 $581,000 Inspection, and Testing Contract Contingencies F$5-00,480 $625,000 $1,125,480 TOTAL ESTIMATED $6 $625,000 $6,725,000 CONSTRUCTION DELIVERY COST ,100,000 FISCAL IMPACT As indicated in the Cost Analysis, the total estimated construction delivery cost of the project is $6,725,000, which includes the construction contract, contract administration, inspection, testing, and an authorized contingency. On December 20, 2022, City Council approved $5,600,000 of American Rescue Plan Act (ARPA) funding for this project. On April 15, 2024, under City Manager authorization, an additional $500,000 was allocated to this project. At this time, an additional $625,000 of ARPA funding will be allocated to the contingency and added to the FY 2024-25 CIP (Exhibit 4). The following table summarizes funds budgeted and available in current FY 2024-25 for expenditure to complete construction of this project. Any remaining balances not expended at the end of the fiscal year will be presented to City Council for approval of carryovers to FY 2025-26. Fiscal Accounting Unit - Fund Accounting Unit Year Account No. Description - Account No. Amount Project No. Description Original Project Budget American ARPA-PWA, 2024-25 18117013-66220 Rescue Plan Improvements $6,100,000 (22-1341) Act (ARPA) Other Than Buildings Additional Funding First Street Slope Stabilization Project July 16, 2024 Page 3 Fiscal Accounting Unit - Fund Accounting Unit Year Account No. Description - Account No. Amount project No. Description American ARPA-PWA, 2024-25 18117013-66220 Rescue Plan Improvements $625,000 (22-1341) Act (ARPA) Other Than Buildings Total $6,725,000 EXHIBIT(S) 1. Location Map 2. Change Order #1 3. Cost Analysis 4. First Street Slope Project FY 2024-25 CIP Sheet Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency Approved By: Alvaro Nunez, Acting City Manager EXHIBIT 1 Leg -end II11u Project Location J :A I Exhibit 1 SANTA ANA P W A Project No. 22-1341 First Street Slope Stabilization PUBLIC WORKS AGENCY PUBLIC WORKS ,AGENCY CONTRACT CHANCE ORDER Project Number Project No. 22-1341 First Street Slope Stabilization Project Change Order Number To Eyerl.evel Holdings, LLC Contractor You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included In the plans and specifications on this contract. NOTE; THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BY THE CITY COUNCIL OR CITY MANAGER. Unless otherwise stated, rates for rental of equipment cover only such time as equipment Is actually used and no allowance will be made for idle time. .. Change requested by JUSTIFICATION PUBLIC WORKS AGENCY 1. To compensate the contractor for costs associated with discovery unforeseen 8" utility lines in slope subgrade excavation and removal. (PCO No. 01). TOTAL COST = $9,863.78 l 2. To compensate the contractor for casts associated with relocation of CMS boards per City's request. (PCO No. 02). TOTAL. COST = $623.42 3. To compensate the contractor for costs associated with additional traffic control as per City's request including additional arrows and barricades. (PCO No. 03). TOTAL COST = $4,544.83 '.,/ 4. To compensate the contractor for costs associated with removal of two abandoned telephone poles on the South side of the slope. (PCO No. 04) TOTAL COST = $2,517.55 / 5. To compensate the contractor for costs associated with additional potholing on SE slope including backfill for all locations. (PCO No. 05). TOTAL COST = $9,518.96 , 6. To compensate the contractor for costs associated with backfill of anchor trench due to plan change per City direction. (PCO No. 06). TOTAL COST T $4,762,56 7. To compensate the contractor for costs associated with removal of backflow preventer and capped line at the main per City's request. (PCO No. 07). Page 1 of 4 TOTAL COST = $3,129.32 l 8. To compensate the contractor for costs associated with the stay form for the New Anchor Wall design due to the widening of the sidewalk. (PCO No. 09). TOTAL COST = $35,000.00 z 9. To compensate the contractor for costs associated with chipping down the PCC Pence Footing on the Southeast slope where the existing black wrought iron fence was placed. (PCO No. 11). TOTAL COST = $6,459.83 / 10. To compensate the contractor for costs associated with placing additional gravel base due to variable retaining curb height on Southwest and Southeast slopes. Compaction of slope also had also to be redone. (PCO No. 12). TOTAL COST = $49,645.55 11. To compensate the contractor for costs associated with removing the existing sidewalk and installing a new 18" widened sidewalk. (PCO No. 13). TOTAL ESTIMATED COST = $200,700.00 !� 12. To compensate the contractor for costs associated with repairing the v-ditch on the south slope. (PCO Na. 13.1). TOTAL COST = $4,990.00 13. To compensate the contractor for costs associated with removal and replacement of the curb & gutter on the South side of the slope, removal of the existing asphalt -concrete section adjacent to the curb & gutter, placement of asphalt -concrete slot patch, and to furnish and install three No. 6 Pull Boxes. (PCO No. 14). TOTAL. COST = $85,574.89 V 14. To compensate the contractor for costs associated with installation skate preventative devices on both the North and South retaining curbs. (PCO No. 15). TOTAL COST = $49,174.00 15. To compensate the contractor for costs associated with crack repair and re -staining of the blue River Lens. (PCO No. 16). TOTAL COST = $65,191.57 16. To compensate the contractor for costs associated with installation of anti -graffiti coating on the south anchor wall. (PCO No. 17). . TOTAL COST = $10,$00,00 17. To compensate the contractorfor costs associated with providing a smooth and uniform finish to south anchor wall (PCO No. 18). TOTAL COST = $11,250.00 Page 2 of 4 18. To compensate the contractor for costs associated with chipping the bottom of the anchor wall to facilitate the new, widened sidewalk (PCQ No. 19). TOTAL. COST = $31,773.17 Delete Bid Item Quantities Bid Item #12: Remove unused bid item quantities for Bid Item #12. Two Hundred linear Feet was not used in the project @ $250.00 per linear Feet. TOTAL. CREDIT AMOUNT= ($50,000A0) TOTAL AGREED CHANGE ORDER COST: $585,619.53 TOTAL AGREED CONTRACT INCRf Asl* COST: $636,519.53 Page 3 of 4 AT' Project Number Pro To Everl-evel Holdil PUBLIC WORKS AGENCY CONTRACT CHANGE ORDER No. 22-1341 First Street Slope Stabilization Project Change Order Number 1 LLC Contractor You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract. NOTE; THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL_ APPROVED BY THE CITY COUNCIL OR CITY MANAGER, Unless otherwise staled, rates for rental of equipment cover onfy such time as equipment is actually used and no allowance will be made for idle time. Change requested by PUBLIC WORKS AGENCY The compensation both time and cost set forth in this change order comprises the total compensation due the Contractor, all Subcontractors, and all Suppliers for all work performed per this change order, including impact on unchanged work. By signing this change order, the Contractor acknowledges and agrees on behalf of himself, all Subcontractors, and all Suppliers, that the stipulated compensation includes payment for all work contained in this change order, plus all payment for interruption of schedules, extended field overhead, home office overhead, profit, delay, and all impact, ripple effect or cumulative impact on all other work under this Contract. The signing of this change order constitutes full mutual accord and satisfaction for all changes and work performed on this project, and that the time and cost paid per this change order constitutes the total equitable adjustments owed the Contractor, all Subcontractors, and all Suppliers for all work performed on this project. The Contractor on behalf of himself, all Subcontractors, and all Suppliers agrees to waive all rights, without exception or reservation of any whatsoever to file any further claim related to this project. TOTAL COST THIS CHANGE ORDER: DECREASE $ 50,000.00 INCREASE $ 685,519.53 By reason of Phis order the CONTRACT TIME completion will be adjusted as follows: One Hundred and Twelve (112) working days. We the undersigned contractor have given careful consideration to the change proposed and hereby agree, if [his proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all service necessary for the work above specified, and will accept as full payment therefor the prices shown above. Accepted, Data g- 2 �Z Contractor Ever evel Holdings, LLLLC By Title�� Approval recommended by _ f- _ f� h Date `PUBLIC WORKS AGENCY EXECUTIVE DIREG OR EST: Appreved by la 6G4l-v Date C C Alvaro Nunez Acting City Manager ennifer ll r Page 4 of 4 UPDATED COST ANALYSIS CONSTRUCTION OF PROJECT NO. 22-1341: First Street Slope Stabilization Construction Contract $ 4,482,892.00 Contract Administration, Inspection and Testing $ 667,108.00 Contingencies $ 1,075,000.00 TOTAL ESTIMATED CONSTRUCTION COSTS $ 6,225,000.00 PROJECT TITLE: First Street Slope Stabilization Project PROJECT CATEGORY: Utility/Drainage/Lighting Improvements Storm Drain/Water Quality LOCATION MAP N AGENCY: Public Works CITY OF SANTA ANA FY 24/25CIP CAPITAL IMPROVEMENT PROJECT WORKSHEET PROJECT DESCRIPTION: Installation of decorative concrete, a stormwater treatment device, and new security fencing along the First Street railroad undercrossing. PROJECT NEED: The railroad undercrossing along First Street, between Standard Avenue and Grand Avenue, consists of four dirt slopes. The dirt slopes are severely eroded, which leads to the discharge of sediment into the street and City stormdrain system during rain events. Additionally, encampments that form at the top of the slopes lead to the discharge of trash and debris. The goal of the project is to improve water quality and address stormwater pollution via the stabilization of the dirt slopes, elimination of trespassing and encampments, and installation of a stormwater treatment device. The project will also significantly enhance the aesthetics of this important gateway to Downtown Santa Ana. PROJECT COSTS FY 24/25 FY 25/26 FY 26/27 FY 27128 FY 28/29 FY 29130 FY 30131 Construction 625,000 - - - - - - TOTAL 625,000 - - - - - - SOURCE OF FUNDS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30131 ARPA Funds 625,000 - - - - - - TOTAL 625,000 - - - DIVISION: C/P Engineering CONTACT: Craig Foster, NPDES Manager DATE: 04-Jun-2024