City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
August 20, 2024
TOPIC: Grand Avenue Rehabilitation from McFadden Avenue to First Street
AGENDA TITLE
Award a Construction Contract to All American Asphalt for the Grand Avenue
Rehabilitation from McFadden Avenue to First Street Project (Project No. 23-6702)
(Non -General Fund)
RECOMMENDED ACTION
Approve an appropriation adjustment recognizing $972,882 in Coronavirus
Response and Relief Supplemental Appropriations Act (CRRSAA) grant from
Select Street Construction, State Grant -Direct revenue account and appropriate
the same amount into the Select Street Construction, Improvements Other Than
Buildings, expenditure account. (Requires five affirmative votes.)
2. Approve an appropriation adjustment recognizing $676,000 of prior -year fund
balance from Special Gas Tax, Prior Year Carry Forward and Select Street
Construction, Transfer from Fund 029 revenue accounts and appropriate the same
amount into the Gas Tax Interfund Transfer, Transfer to Fund 059 and HUTA 2103
Gas Tax, Improvements Other Than Buildings, expenditure account. (Requires five
affirmative votes.)
3. Approve an appropriation adjustment to transfer $30,907 from Roadway
Maintenance, Improvements Other Than Buildings, Transfer from Fund 029
revenue accounts and appropriate the same amount into the Gas Tax Interfund
Transfer, Transfer to Fund 059 and Select Street Construction, Improvements
Other Than Buildings, Improvements Other Than Buildings, Improvements Other
Than Buildings, expenditure account. (Requires five affirmative votes.)
4. Authorize a budget reallocation of $44,590 in unspent funds from the Santa Clara
Avenue Bike Lane from Lincoln Avenue to Tustin Avenue Project (No. 23-6997)
and $30,907 from Omnibus Concrete Program Support Project (No. 22-6970) to
construction funds for the Grand Avenue Rehabilitation from McFadden Avenue to
First Street Project (No. 23-6702)
5. Approve an amendment to the Fiscal Year 2024-25 Capital Improvement Program
(CIP) to include $972,882 from Select Street Construction funds, $676,000 from
Grand Avenue Rehabilitation from
August 20, 2024
Page 2
McFadden Avenue to First Street
HUTA 2103 Gas Tax funds and $75 497 in unspent funds from projects 22-6970
and 23-6997, for the Grand Avenue Rehabilitation from McFadden Avenue to First
Street Project.
6. Approve the Project Cost analysis for a total estimated construction delivery cost of
$2,242,499, which includes $1,793,999, for the construction contract; $269,100 for
contract administration, inspection, and testing; and a $179,400 project
contingency for unanticipated or unforeseen work.
7. Award a construction contract to All American Asphalt, the lowest responsible
bidder, in accordance with the base bid in the amount of $1,793,999, subject to
change orders in accordance with the Greenbook: Standard Specifications for
Public Works Construction, for term beginning August 20, 2024, and ending upon
project completion, and authorize the City Manager to execute the contract.
8. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption
Environmental Review No. ER-2023-29 was filed for Project 23-6702.
GOVERNMENT CODE 484308 APPLIES: No
DISCUSSION
The Public Works Agency's Engineering Services Division (PWA) is responsible for
managing the City's roads and transportation network. The section of Grand Avenue
between McFadden Avenue and First Street (Exhibit 1) was identified in needing
rehabilitation and was programmed into the Capital Improvement Project (CIP). In
addition to Senate Bill 1 Funding, the City received funding from the Coronavirus
Response and Relief Supplemental Appropriations Act (CRRSAA) for the Grand
Avenue Rehabilitation from McFadden Avenue to First Street. The scope of work
includes restoring asphalt pavement, curb and gutter, driveway approaches, utility
adjustments, traffic loops, and signing, and striping. Once completed, these
improvements will improve the overall pavement condition, enhance the visual
appearance of the street, upgrade ride quality, drainage, and support compliance with
Americans with Disabilities Act (ADA) standards.
Public Outreach and Contractor Participation
To provide an opportunity for local vendors to submit bids, the City notified a total of 58
regional vendors via PlanetBids, many of which are Santa Ana -based. A total of six bids
were received. No bids were received from any Santa Ana contractors.
As legally required, a Notice Inviting Bids was advertised in the Orange County Register
newspaper on June 17 and June 21, 2024. The project was also advertised in
PlanetBids from June 13 through July 3, 2024. Bids were received electronically via
PlanetBids on July 3, 2024.
Grand Avenue Rehabilitation from McFadden Avenue to First Street
August 20, 2024
Page 3
Bid Results Summary
Rank
Bidder's Name
Location
Base Bid
1
All American Asphalt
Corona, CA
$1,793,999
2
Hardy & Harper, Inc.
Lake Forest, CA
$1,950,000
3
R.J. Noble Company
Corona, CA
$2,067,735
4
DOJA, Inc.
Ontario, CA
$2,160,000
5
Excel Paving Co.
Long Beach, CA
$2,184,140
6
Onyx Paving Company, Inc.
Anaheim, CA
$2,488,000
A total of six bids were received and all were deemed responsive. All American Asphalt
submitted the lowest responsive base bid in the amount of $1,793,999 (Exhibit 2). As
specified in the bid documents, the lowest bid shall be determined on the basis of the
Base Bid. Based on the bid analysis and a contractor's reference check, staff
recommends awarding the construction contract to All American Asphalt for the base
bid (Exhibit 3).
All American Asphalt has previously performed work as a prime contractor in the City of
Santa Ana within the last five years, most recently completing the Grand Avenue
Rehabilitation from Warner to Edinger Avenue. A reference check was made with staff
and good reviews were received regarding the quality of work performed by the
contractor on previous projects.
Project Delivery
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes construction administration, inspection, and testing, along
with an allowance for contingencies to account for unexpected or unforeseen
conditions. Construction administration and inspection includes construction
management and implementation of the labor requirements.
As indicated in the Cost Analysis (Exhibit 4) and as summarized in the table below, the
estimated total construction delivery cost of the project is $2,242,499.
Project Item
Total
Construction Contract Bid Amount
$1,793,999
Construction Administration, Inspection, Testing
$269,100
Project Contingencies
$179,400
TOTAL ESTIMATED CONSTRUCTION DELIVERY COST
$2,242,499
Grand Avenue Rehabilitation from McFadden Avenue to First Street
August 20, 2024
Page 4
ENVIRONMENTAL IMPACT
Pursuant to the California Environmental Quality Act (CEQA), the recommended actions
are exempt from further review pursuant to Section 15301(c) of the CEQA Guidelines
for projects consisting of existing highways and streets, sidewalks, gutters, bicycle and
pedestrian trails, and similar facilities. The proposed project continues to meet these
parameters of the CEQA Guidelines, and Categorical Exemption Environmental Review
No. ER-2023-29 was filed for Project 23-6702 (Exhibit 5).
FISCAL IMPACT
As indicated in the Cost Analysis, the estimated total construction delivery cost of the
project (23-6702) is $2,242,499, which includes construction, contract administration,
inspection, testing, and authorized contingencies of $448,500. Funds were available
the HUTA 2103 Gas Tax, Improvements Other Than Buildings account (05917663-
66220) and Measure M2 Local Fairshare St, Improvements Other Than Buildings
account (03217662-66220) in FY 2023-24. Therefore, a proposed carry-over of unspent
funds will be presented to the City Council in September for approval of carryovers to
FY 2024-25. Any remaining balances not expended at the end of the fiscal year will be
presented to the City Council for approval of carryovers to FY 2025-26.
Approval of the requested Appropriation Adjustments will recognize $676,000 of prior -
year fund balance from the Special Gas Tax Revenue, Prior Year Carry Forward
revenue account (No. 02917002-50001) and $972,882 in Coronavirus Response and
Relief Supplemental Appropriations Act (CRRSAA) grant from Select Street
Construction, State Grant -Direct revenue account (No. 05917002-52025), and
appropriate it to the Select Street Construction, Improvements Other Than Buildings
expenditure account (No. 05917660-66220) and HUTA 2103 Gas Tax, Improvements
Other Than Buildings expenditure account (No. 05917663-66220). The spendable
portion of the Gas Tax fund balance is estimated to be $676,006 at June 30, 2025,
which is sufficient to allow for the recommended appropriation of $676,000. An
appropriation adjustment to transfer $30,907 from Roadway Maintenance,
Improvements Other Than Buildings, Transfer from Fund 029 revenue accounts and
appropriate the same amount into the Gas Tax Interfund Transfer, Transfer to Fund 059
and Select Street Construction, Improvements Other Than Buildings, Improvements
Other Than Buildings, Improvements Other Than Buildings, expenditure account, is
required for the reallocation of funds from project 22-6970.
Approval of the requests to reallocate funds will provide a total of $75,497 in unspent
funds from projects 22-6970 and 23-6997.
The following table summarizes the funds budgeted for expenditure to deliver the
construction of this project:
Grand Avenue Rehabilitation from McFadden Avenue to First Street
August 20, 2024
Page 5
Fiscal
Accounting Unit
Fund
Accounting Unit,
Year
- Account No.
Description
Account No.
Amount
project No.
Description
Existing Budget
05917663-66220
Select Street
HUTA 2103 Gas Tax,
2024-25
(23-6702)
Construction
Improvements Other
$518,120
Than Buildings
Budget Reallocation
03217662-66220
Measure M-
Measure M2 Local
2024-25
(From 23-6997
Street
Fairshare St,
$44,590
to 23-6702)
Construction
Improvements Other
Than Buildings
05917663-66220
Select Street
HUTA 2103 Gas Tax,
2024-25
(From 22-6970
Construction
Improvements Other
$30,907
to 23-6720)
Than Buildings
Additional Budget
05917663-66220
Select Street
HUTA 2103 Gas Tax,
2024-25
(23-6702)
Construction
Improvements Other
$676,000
Than Buildings
Select Street
2024-25
05917660-66220
Select Street
Construction,
$972 882
(23-6702)
Construction
Improvements Other
Than Buildings
Total
$2,242,499
EXHIBIT(S)
1. Location Map
2. Bid Proposal
3. Construction Contract
4. Cost Analysis
5. Categorical Exemption Environmental Review No. ER-2023-29
6. FY 2023-24 Capital Improvement Program Sheet
Submitted By: Nabil Saba, P.E., Executive Director — Public Works Agency
Approved By: Alvaro Nunez, City Manager
EXHIBIT 1
DA 01 � DA 02 DA 03 DA 04 ' rnn�-J
a J a
a
a �
�J GRAND AVE
ST DA 05
n
rT---
LOCATION MAP
(NOT TO SCALE)
Noa NC
SANTA ANA
Pr1 Project No. 23-6702: Grand Avenue Roadway 3
Rehabilitation from McFadden Avenue to First
PU6LIC WORKS AGENCY Street Location Map
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 23-6702
GRAND AVENUE ROADWAY REHABILITATION FROM MCFADDEN AVENUE TO
FIRST STREET
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation*
1,060
CY
$
$
215.00
227,900.00
2
AC Pavement*
1,990
TN
$
$
150.00
298,500.00
3
Cold Mill (2-3/8") Expect Pavement
305,000
SF
$
$
Fabric 2" Below Existing Surface
0.54
164,700.00
4
Asphalt Rubber and Aggregate Membrane
33,990
SY
$
$
(ARAM)
7.00
237,930.00
5
Asphalt Rubber Hot Mix (ARHM)
3,900
TN
$
$
147.18
574,002.00
6
PCC Sidewalk (T=4")
100
SF
$
$
31.88
3,188.00
7
PCC Driveway Approach (T = 8")
600
SF
$
$
22.00
13,200.00
8
PCC Curb and Gutter (Type A-2-8)
500
LF
$
$
97.00
48,500.00
9
Cross -Gutter (Local Street)
1,400
SF
$
$
31.00
43,400.00
10
Furnish and Install Detectable Warning
1
EA
$
$
Surface (Caltrans STD. A88A)
3,400.00
3,400.00
11
Adjust Sewer and Drainage Manhole to
15
EA
$
$
Finished Grade
1,550.00
23,250.00
12
Furnish and Install New Water Valve
25
EA
$
$
Frame and Cover to Finished Grade
1,250.00
31,250.00
13
Furnish and Install Traffic Loops Type F
9
EA
$
$
471.00
4,239.00
P-1 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 23-6702
GRAND AVENUE ROADWAY REHABILITATION FROM MCFADDEN AVENUE TO
FIRST STREET
Item
Description
Qty
Unit
Unit Price
Amount
14
Furnish and Install Traffic Loops Type E
30
EA
$
448.00
$
13,440.00
15
Project Advertisement Sign
2
EA
$
3,800.00
$
7,600.00
16
Signing and Striping
1
LS
$ 33,000.00
$ 33,000.00
17
Construction Permit
1
LS
$8,500
$8,500
18
SCRRA Right -of -Entry Permit
I
LS
$
58,630.00
$
58,630.00
TOTAL BASE BID $ 1,793,999.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 7-3.5 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
j This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIOUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within number (50) working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $5,000 per calendar day.
Name of Firm All American Asphalt
Signature of BIDDER / Z_ �/
Title Edward J. Carlson, Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-2 of P-18
CITY OF SANTA ANA
CONSTRUCTION CONTRACT AGREEMENT
PROJECT 23-6702
GRAND AVENUE ROADWAY REHABILITATION FROM MCFADDEN AVENUE TO FIRST STREET
This CONSTRUCTION CONTRACT is made and entered into this 20d' day of August, 2024 by and
between the City of Santa Ana, California, a charter city and municipal corporation organized and existing
under the Constitution and laws ofthe State of California (hereinafter "CITY"), and All American Asphalt
(hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the Grand Avenue Roadway Rehabilitation from McFadden Avenue
to First Street Project (hereinafter referred to as the "WORK OF IMPROVEMENT") identified in and
in accordance with the Contract Documents prepared by the City's Public Works Agency and
approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed One Million Seven Hundred Ninety Three
Thousand Nine Hundred Ninety Nine Dollars and No Cents ($1,793,999.00), as set forth and
identified in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A,"
and in accordance with Section 2-7.1 of the Greenbook: Standard Specifications for Public Works
Construction.
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
rev. 08/01/2023 Page I of 3
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at: http://www.santa-ana.org/pwa/documents/CWA.pdf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (1000/0)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
- Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
Page 2 of 3
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
ATTEST: CITY OF SANTA ANA
JENNIFER L. HALL
City Clerk
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
B VI
Y•
JONE MONTOYA
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
Digitally signed by Nabil
Saba
N d b 1 I C ✓ a b a Date: 2024.08.05 14:57:16
-07'00'
NABIL SABA, PE
Executive Director
Public Works Agency
ALVARO N"EZ
Acting City Manager
CONTRACTOR:
All American Asphalt
��---
NAME. Edward J. Carlson
TITLE:Vice President
Page 3 of 3
CALIFORNIA ALL-PURPOSE ACKNOWLEDGEMENT CIVIL CODE § 1189
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached and not the tnithfitlness. accuracv. or validity of that document.
State of California
County of Riverside
On 07/31/2024 before me, Kimberly Deiro, Notary Public
Date Here Insert name and Title of the Officer
personally appeared Edward J. Carlson
NameKof Sign
who proved to me on the basis of satisfactory evidence to be the
person(s) whose name(&) is/are subscribed to the within instrument
and acknowledged to me that he/64e4hey executed the same in
his/#ef/##e# authorized capacity(ie&), and that by his/#e4theif
SFp�oF ry KIMBERLY DEIRO signatures) on the instrument the person(s), or the entity upon behalf
" F Notary Public - California n of which the persons) acted, executed the instrument.
W a
Riverside County
r ° Commission # 2491436
FOp My Comm. Expires May 27, 2028 1 certify under PENALTY OF PERJURY under the laws of the State of
California that the forgoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature
Place Notary Seal Above Sig re of Nobfry Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to person relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
Description of Attached Document
Title or Type of Document Construction Contract - City of Santa Ana
Document Date: 07/31/2024
Signer(&) Other Than Named Above:
Capacity(") Claimed by Signer(s)
N/A
Number of Pages: 5
Signer's Name: Edward J. Carlson Signer's Name:
❑ Individual ❑ Individual
X Corporate Officer — Title(&): Vice President
❑ Partner ❑ o Limited ❑ General
❑ Attorney in Fact
❑ Trustee
❑ Other:
Signer is Representing:
N/A
❑ Corporate Officer — Title(s):
❑ Partner ❑ ❑ Limited ❑ General
❑ Attorney in Fact
❑ Trustee
❑ Other: N/A
Signer is Representing:
N/A
N/A
EXHIBIT A CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 23-6702
GRAND AVENUE ROADWAY REHABILITATION FROM MCFADDEN AVENUE TO
FIRST STREET
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: All American Asphalt
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Conixact Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Qty
Unit
Unit Price
Amount
1
Unclassified Excavation*
1,060
CY
$
$
215.00
227,900.00
2
AC Pavement*
1,990
TN
$
$
150.00
298,500.00
3
Cold Mill (2-3/8") Expect Pavement
305,000
SF
$
$
Fabric 2" Below Existing Surface
0.54
164, 700.00
4
Asphalt Rubber and Aggregate Membrane
33,990
SY
$
$
7.00
237, 930.00
5
Asphalt Rubber Hot Mix (ARHM)
3,900
TN
$
$
147.18
574,002.00
6
PCC Sidewalk (T=4")
100
SF
$
$
31.88
3,188.00
7
PCC Driveway Approach (T = 811)
600
SF
$
$
22.00
13,200.00
8
PCC Curb and Gutter (Type A 2-8)
500
LF
$
$
97.00
48,500.00
9
Cross -Gutter (Local Street)
1,400
SF
$
$
31.00
43,400.00
10
Furnish and Install Detectable Warning
1
EA
$
$
Surface (Caltrans STD. A88A)
3,400.00
3,400.00
11
Adjust Sewer and Drainage Manhole to
15
EA
$
$
Finished Grade
1,550.00
23,250.00
12
Furnish and Install New Water Valve
25
EA
$
$
Frame and Cover to Finished Grade
1,250.00
31,250.00
13
Furnish and Install Traffic Loops Type F
9
EA
$
$
471.00
4,239.00
P-1 of P-18
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 23-6702
GRAND AVENUE ROADWAY REHABILITATION FROM MCFADDEN AVENUE TO
FIRST STREET
Item
Description
Qty
Unit
Unit Price
Amount
14
Furnish and Install Traffic Loops Type E
30
EA
$
448.00
$
13,440.00
15
Project Advertisement Sign
2
EA
$ 3,800.00
$7,600.00
46
Signing and Striping
I
LS
$
33,000.00
$
33,000.00
17
Construction Permit
1
LS
$8,500
$8,500
18
SCRRA Right -of -Entry Permit
I
LS
$
58,630.00
$
58,630.00
TOTAL BASE BID $ 1, 793, 999.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the "25%" limit as stated in Section 7-3.5 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within number (50) working days after the commencement date stated in the Notice to
Proceed.
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $5,000 per calendar day.
Name of Firm All American
Signature of BIDDER
Title Edward J. Carlson, Vice President
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
P-2 of P-18
EXHIBIT 4
COST ANALYSIS
CONSTRUCTION OF PROJECT NO. 23-6702: Grand Avenue Roadway
Rehabilitation from McFadden Avenue to First Street
Construction Contract
$
1,793,999.00
Contract Administration, Inspection and Testing
$
269,100.00
Contingencies
$
179,400.00
TOTAL ESTIMATED CONSTRUCTION COSTS
$
2,242,499.00
Recorded in Official Records, Orange County
Hugh Nguyen, Clerk -Recorder
FILED NO FEE
*$ R 0 0 1 4 2 3 8 8 1 2$
MAR 0 9 2023 202385000181 9:36 am 03/09/23
256 Vitlndx Z01
ORANGE COUNTY CLERK -RECORDER DEPARTMENT 0.00 50.00 0.00 0.00 0.00 0.00 0.00 0.00 EXHIBIT 5
BY:
DEPUTY
MAYOR
CITY MANAGER
Valerie Amezcua"eK"
Kristine Ridge
MAYOR PRO TEM
"�
CITY ATTORNEY
Jessie Lopez
Sonia R. Carvalho
COUNCILMEMBERS
° ` ._�
CLERK OF THE COUNCIL
Phil Bacerra
Jennifer L. Hall
Johnathan Ryan Hernandez
David Penaloza
Thai Viet Phan
Benjamin Vazquez
PUBLIC WORKS AGENCY
20 Civic Center Plaza (M-36)
P.O. BOX 1988 . Santa Ana, California 92702
(714) 647-5690 - Fax (714) 647-5823
www.santa-ana.org
NOTICE OF EXEMPTION
From the Requirements of the California Environmental Quality Act (CEQA)
Fee Exemption per California Government Code Section 6103
To: COUNTY CLERK
From: City of Santa Ana
County of Orange
Public Works Agency
P.O. Box 238
20 Civic Center Plaza (M-36)
Q
Santa Ana, CA 92702 Santa Ana, CA 92702
Project Title: Grand Avenue Rehabilitation from 1st Street to McFadden
Avenue
Project Number(s): 23--6702
M
Project Location: Grand Avenue - 1st Street to McFadden Avenue
Q
City: Santa Ana County: Orange ER Number: ER-2023-29
Date of Approval: 06/21/2022
,"``...
Project Description: The project will rehabilitate and reconstruct the existing asphalt pavement, and replace damaged curbs,
gutters, curb ramps, driveway approaches, catch basins, and concrete bus pads.
Applicant Name: City of Santa Ana, Public Works Agency
Applicant Address: 20 Civic Center Plaza M-36
Santa Ana, CA 92702
M
Name of Public Agency Approving Project City Council
POSTE
Name of Agency Carrying Out Project: Public Works Agency
(
Exempt Status:
❑ Ministerial (Sec. 15268)
MAR 0 9 2023
(�
❑ Declared Emergency (Sec. 15269 (a))
❑ Emergency Project (Sec. 15269 (b through e))
ORANGE COUNTY CLERK -RECORDER DEPARTMENT
❑ General Rule (Sec. 15061(b)(3)/(5))
BY: _DEPUTY
❑ Statutory Exemption:
0 Categorical Exemption: 15301(c)
Reason(s) Why Project is Exempt From CEQA:
15301(c) consists of existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities.
City Contact: Anderson Chrysostomo Title: Associate Engineer Telephone: (714) 647-5838
Signature: Date: _�23 0gi'2v'z3
SANTA ANA CITY COUNCIL
Valerie Amezcua Jessie Lopez Thai Viet Phan Benjamin Vazquez Phil Bacerra Johnathan Ryan Hernandez David Penaloza
Mayor Mayor Pro Tem, Ward3 Ward 1 Ward 2 Ward 4 Ward 5 Ward 6
EXHIBIT 6
PROJECT TITLE:
Grand Ave Roadway Rehab:
McFadden Ave to 1st St
PROJECT CATEGORY:
Street Improvements
Arterial Street Rehabilitation
LOCATION MAP A
N
CITY OF SANTA ANA FY 24/25CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Reconstruction/resurfacing of existing pavement and
replacement/installation of missing or damaged, curbs, gutters,
sidewalks, driveway approaches, and wheelchair ramps within this
segment of roadway.
PROJECT NEED:
The City's Pavement Management Program (PMP) has been
developed to prioritize and recommend the most cost-effective roadway
Irepairs, and maximize the return from available funding for street
pavement. This segment of Grand Avenue pavement rehabilitation is
identified as a high priority in the PMP.
PROJECT COSTS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31
Construction 1,724,379 - - - - - -
Engineering 518,120
TOTAL 2,242,499 - - - - - -
SOURCE OF FUNDS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31
CMAQ 972,882 - - - - - -
GAS TAX 1,269,617
TOTAL 2,242,499 - - - - - -
AGENCY: DIVISION: CONTACT: DATE:
Public Works C/P Engineering Jason Gabriel, Principal Civil Engineer 06-Aug-2024