UIA M. -V/& -V o4— PROGRAM MANAGEMENT AGREEMENT FOR
CONSTRUCTION OF THE CITY HALL PARKING STRUCTURE
THIS PROGRAM MANAGEMENT AGREEMENT ("Agreement") is entered into this Zs:'day
,V
of Lwg"is� 2002, by and between GORDON & WILLIAMS, INC. a California corporation
(hereinafter referred to as "Program Manager") and THE CITY OF SANTA ANA, a charter the
City and municipal corporation duly organized and existing under the constitution and laws of the
State of California (hereinafter referred to as the "City").
RECITALS
A. The City issued a Request for Qualifications to select a program manager assist in the
design and construction of a new parking structure (the "Project") adjacent to Santa Ana City Hall
(the "RFQ"). A copy of the RFQ is attached hereto as Exhibit A.
B. Program Manager submitted what was determined to be the best statement of qualifications
(the "Statement of Qualifications"). Program Manager also submitted a fee proposal. A copy of the
Fee Proposal is attached hereto as Exhibit B and a copy of the Statement of Qualifications is
attached hereto as Exhibit C.
C. City and Program Manager wish to enter into this Agreement to carry out development of
the Project.
ARTICLE I
PHASE 1--DESIGN DEVELOPMENT/PROJECT TEAM
1.1 The scope of services under this Article shall be the development of a preliminary design,
project budget, and scheduling required to accomplish the preparation and submission of the
Program Manager's Design Development Proposal and Project Budget, based on the Conceptual
Site Plan attached as exhibit A to the RFQ (the "Design Proposal"). Design services shall include
the soils investigation (including hazardous materials), civil, architectural, structural, mechanical,
and electrical design. Site survey to be provided by others. Design includes investigation of
structure placement and pedestrian access options, as well as alternate foundation and structural
framing systems. All services required by this Article shall be performed by the Project Team as
identified in the Statement of Qualifications. The contractual obligations of the Project Team are
undertaken and performed in the interest of the Program Manager. The make up of the Project
Team was central to Program Manager being selected. Therefore, Program Manager shall not
substitute any member of the Project Team without the written consent of the Designated City
Representative in his/her sole and absolute discretion.
1.2 The Program Manager shall be responsible to the City for acts and omissions of the Project
Team or other subconsultants performing any portion of the Program Manager's obligations under
this Agreement.
1.3 Nothing contained in this Article shall create a contractual relationship between the City
and any person or entity other than the Program Manager.
�41:(DEIVED
C'1013DON & WiLlIAMS
1.4 The Program Manager shall visit the site, become familiar with the local conditions, and
correlate observable conditions with the requirements of the City's program and schedule.
1.5 In developing the Design Proposal, the Program Manager shall review with the Designated
City Representative any alternative approaches to design and construction of the Project which the
Project Team may consider recommending.
1.6 The Program Manager shall submit to the City the Design Proposal, including the
completed Preliminary Design Documents, a statement of the proposed Project Budget, and a
proposed schedule for completion of the Project. Preliminary Design Documents shall consist of
preliminary design drawings, outline specifications or other documents sufficient to establish the
size, quality and character of the entire Project, its architectural, structural, mechanical and
electrical systems, and the materials and such other elements of the Project as may be appropriate
(the "Project Documents"). Deviations from the City's program shall be disclosed in the Project
Documents. The Project Budget will be tied to the construction documents for definition of scope.
If the proposed Project Budget exceeds the $2,540,000 budget including the appropriate
contingencies, the project will be redesigned. The number of parking stalls provided on site will be
determined by the funds available, but the Program Manager will use its best efforts to maximize
the number of spaces on site
1.7 In consideration for services provided under this Article, the City shall pay the Program
Manager the Pre -Construction Phase fee set forth in Exhibit B (the "Design Development Fee").
1.8 If the Project Documents and Project Budget is accepted by the City, the parties proceed
with the balance of this Agreement under which the Program Manager shall agree, subject to the
terms and conditions of this Agreement, to deliver the completed Project for the Contract Sum.
1.9 The City reserves the absolute discretion to reject Program Manager's Design Development
Proposal and Project Budget, in which case, the Program Manager shall transfer or assign use of
any plans or designs developed to the City for use as the City deems appropriate, the City shall pay
the Design Development Fee, and thereafter the parties shall have no further rights or
responsibilities under this Agreement.
ARTICLE 2
PHASE 2-CONSTRUCTION-GENERAL, TERMS
2.1 This Agreement represents the entire agreement between the City and Program Manager
with regard to the Project, and supersedes all prior negotiations, representations or agreements. This
Agreement shall not be superseded by any provisions of the documents for construction and may be
amended only by written instrument signed by both the City and Program Manager.
2.2 Program Manager shall (i) provide general administration of the Agreement, (ii) prepare all
Project Documents, (iii) manage and supervise the Project Team and the processing of plans and
specifications for the Project; (iv) manage as the City's representative the putting out for bid of all
components of construction for the Project, including assuring all competitive bidding requirements
applicable to the Project pursuant to City Charter Section 421 are complied with; (v) cause the
Project to be completed within the Project Budget and in accordance with the Project Documents.
Construction services include demolition of the existing juvenile detention center, hazardous
materials removal, pre -construction budgets, constructability analysis and public subcontractor
bidding for items in excess of $10,000. During construction, services include issuing subcontracts,
processing necessary documentation and submittals, providing field supervision and project
management services and third party testing and inspection, as well as permit processing,
construction administration, maintaining all project files, accounting records and as -built drawings,
and providing temporary field offices and all associated improvements required to support
construction.
2.3 Program Manager agrees to furnish the services set forth herein and agrees to furnish
efficient business administration and management, and cause the Project to be completed in the
most expeditious and economical manner consistent with the interests of the City. Program
Manager represents that it possesses any and all licenses necessary to discharge its obligations
under this Agreement.
2.4 Upon approval of the Design Proposal, Program Manager shall cause the Project Team to
prepare all necessary drawings, plans and specifications necessary to construct the Project within
the Project Budget. It is understood and agreed that as work proceeds on the Project, certain
clarifications and modifications will have to be made, including adjustments in floor plans,
circulation, site work and elevations, as well as detailing of materials, colors and finishes. All
scope of work shall be subject to mutual approval by the parties. The Designated City
Representative is hereby authorized and directed to review and approve all of the Project
Documents as set forth below, provided they substantially conform to the scope of the Project as set
forth in Project Documents, as well as later developed drawings, provided further except as
authorized in writing by the City, under no circumstances shall the cost of the Project exceed the
Project Budget.
ARTICLE 3
PROGRAM MANAGER'S RESPONSIBILITIES
3.1 Program Manager shall be responsible to cause to be delivered to the City in a timely
manner all design work necessary for the implementation of the Project, to assure that all
construction work is competitively bid in accordance with bid documents approved by the City and
to supervise all contractors retained thereby.
3.2 Program Manager shall execute necessary agreements with all Contractors as agent for the
City, and ensure that they will, in the aggregate, satisfactorily provide all labor, materials, tools,
and construction equipment necessary for the execution and completion of the Project, and that all
Construction Contracts will incorporate within their contract sums the payment by the Contractors
for all sales, use, gross receipts and similar taxes related to the Project. Program Manager shall be
responsible for any of such costs due to its failure to cause same to be provided by the Contractors.
3
3.3 Program Manager shall prepare and submit for the City's approval, an estimated progress
schedule for the Project, including a completion date (the "Completion Date"). The schedule shall
indicate the date for the commencement and completion of any stages of the design and
construction and provide for a completion date as set forth in Section 5.1 hereof. The Project
schedule is subject to revisions as required by the conditions of the Project, change orders, and
those conditions and events that are beyond the control of Program Manager, or the Contractors,
including force majeure delays.
3.4 The Program Manager shall assure that all bid documents released for competitive bidding
to prospective Contractors, and all contracts awarded to Contractors, include a requirement that
such Contractors keep the Project Site free from accumulation of waste materials or rubbish caused
by such Contractors operations. If any subsequent law and/or ordinance are enacted which affect
the cost of the Project, Program Manager shall submit a revised Project Budget to reflect such
change and, once approved by the City, is authorized to process change orders with affected
Contractors consistent with such Project Budget revision.
3.5 The Program Manager shall make sure that all applicable provisions of federal, state and
local safety laws to safeguard against accidents or injury to persons on, about or adjacent to the
Project Site are complied with by the Contractors. The foregoing shall not apply, however, with
respect to the elimination or abatement of safety hazards created or otherwise resulting from work
at the Project carried on by persons or firms directly employed or engaged by the City and not a
part of the Project.
3.6 Program Manager shall keep, such full and detailed accounts as may be necessary for the
proper construction and financial management under this Agreement. The system will contain
Program Manager's records, books, correspondence, instructions, drawings, receipts, vouchers,
memoranda and similar data relating to this Agreement. Post construction services include
providing as-builts and owners manuals. Guarantee the improvements for materials and
workmanship for one year.
3.7 Program Manager shall obtain or keep, and the City shall have the right to examine and
audit, all books, estimates, records, contracts, documents, bid documents, subcontracts, and other
data of Program Manager (including computations and projections), and the Contractors related to
negotiating, pricing, or performing the change order modifications in order to evaluate the accuracy
and completeness of the cost or pricing data. The expense of said audit shall be at the sole cost of
the City. Program Manager shall retain the materials described in this paragraph, for examination,
audit, or reproduction, until four (4) years after completion of the Project.
3.8 Program Manager shall insert a clause materially containing the above audit provisions, in
all subcontracts over Ten Thousand Dollars ($10,000.00).
3.9 Program Manager shall publicize bids for the Project construction work in accordance with
the City's "Standard Specifications" and the Santa Ana Municipal Code, as it pertains to public
works projects. Program Manager, as agent and fiduciary to the City, shall have control of the
bidding procedures inclusive of determination of the lowest responsible bidder(s).
4
3.10 Program Manager will require all Contractors to use their best efforts to prosecute the
Project work in a manner to minimize public inconvenience and possible hazard, to restore the
streets and other work areas to their original condition and former usefulness as soon as possible,
and to protect public and private property adjacent to the Project.
ARTICLE 4
THE CITY'S RESPONSIBILITIES
4.1 The City shall provide in a timely manner full information regarding its requirements for the
Project hereunder. The Executive Director of Public Works is hereby designated as the Designated
City Representative and is authorized and directed to carry out such duties and exercise such
discretion as may be heretofore or hereafter delegated.
4.2 The Designated City Representative shall render, in a timely manner, all decisions requested
by Program Manager which may be necessary to perform the Project work. All decisions rendered
by the Designated City Representative shall be binding upon the City. Furthermore, any City
representative(s) present at the job site during construction shall be subject to reasonable rules as
may be imposed by Program Manager.
4.3 If the City discovers any fault, defect or nonconformance in the Project or with the
Drawings or Specifications, the City shall give prompt written notice to the Program Manager. The
Designated City Representative shall sign the final plans and specifications prior to issuance of
building permit.
4.4 The Program Manager will submit all plans for plan checks and will apply for and obtain all
building permits, grading permit(s) and construction permit(s) required by the City of Santa Ana.
The City shall pay or waive all fees in connection therewith, at no cost to Program Manager, The
City shall cooperate with the Program Manager at all times and shall expedite all plan checks and
issuance of all requisite permits in accordance with the Project's requirements and schedules.
ARTICLE 5
TIME SCHEDULE/LIDUIDATED DAMAGES
5.1 The work required under the Project Documents shall be substantially completed subject to
§3.3 of Article 3 (the "Completion Date"). The date of Substantial Completion of the Project is the
date when construction is sufficiently complete in accordance with the Project Documents so that
the City can occupy/use the Project for the use for which it is intended as reasonably determined by
Program Manager. Program Manager shall assure that each Construction Contract provides that
warranties called for by the Project Documents shall commence on the date of Substantial
Completion of the Project. This date shall be established by a certificate of Substantial Completion
("Certificate") signed by the appropriate Consultant, the Program Manager and the City. The City
and the Program Manager shall prepare an addendum to the Certificate stating their respective
responsibilities for security, maintenance, heat, utilities, changes to the work and insurance. The
Certificate shall also list the items to be completed or corrected and establish the time for the
completion and correction.
5.2 If the Program Manager or any Contractor is delayed at any time in the progress of the
Project by any act or neglect of the City, by any separate contractor or agent employed by the City
or by changes ordered in the Project, or by labor disputes, fire, act of war, unusual delay in
transportation, adverse weather condition not reasonably anticipated, unavoidable casualties, or any
causes beyond the Program Manager's control, or a delay authorized by the City pending settlement
of a dispute ("Permissible Delay"), then the date for substantial completion shall be extended by
change order for the period caused by such Permissible Delay. In the event of a delay other than a
Permissible Delay, damage will be sustained by the City in amounts impracticable to quantify. It is
thus agreed that the City shall receive the sum of $650.00 per day as liquated damages for each and
every calendar day's delay in finishing the work following the Completion Date. If the delay is due
to the fault of Program Manager, then the cost responsibility for such delay shall be borne by
Program Manager. If the delay is caused by any Contractor, Program Manager shall have the
authority and responsibility to collect said sums from the delaying parties and pay them over to the
City. Program Manager shall be financially responsible for the failure of any Contractor to pay said
delay fees. If Program Manager fails to pay or collect such liquidation damages, the City may
deduct the amount thereof from any money due or that may become due Program Manager under
this Agreement.
ARTICLE 6
PROJECT BUDGET
6.1 The Project Budget for the Project, subject to additions and deductions as provided herein,
is that sum submitted by Program Manager and agreed to by the City as set forth in Article 1. The
final cost of the Project may be less than the Project Budget. Program Manager is responsible for
assuring that the Project Budget is not exceeded and under no circumstances will the City be
obligated to expend an amount for the Project in excess of the Budget. In the event the cost of
Project, after accounting for all soft and hard costs (as such hard costs are bid by Contractors),
exceeds the Project Budget, Program Manager shall either cause the Project or components thereof
be re -designed in a manner satisfactory to the City and within the Budget, or proceed with the
Project as approved and pay with its own funds for the costs in excess of the Project Budget.
6.2 The parties acknowledge that the Project Budget to be submitted by the Program Manager
and approved by the Designated City Representative shall include includes the fixed Construction
Phase Fee as set forth in Exhibit B (the "Construction Phase Fee").
6.3 Pursuant to California Labor Code Section 1861, Program Manager gives the following
certifications: Program Manger is aware of the provisions of Section 3700 of the California Labor
Code which require every employer to be insured against liability for Worker's Compensation or to
undertake self-insurance in accordance with the provisions of that code, and Program Manager will
comply with such provisions (to the extent applicable) and cause the Construction Manger and all
Contractors to comply with such provisions before commencing the performance of their respective
Project work.
6
ARTICLE 7
PROGRESS PAYMENTS
7.1 Payments shall be made by the City to the Program Manager for disbursement to
Contractors according to the following procedure:
7.2 The City shall make progress payments monthly as the work proceeds. The Program
Manager shall furnish a summary breakdown of the total Project Budget, in a format acceptable to
the City, showing the amount included therein for each principal category of the work, in such
detail as requested, to provide a basis for determining progress payments.
7.3 Unless otherwise provided in the Project Documents, payments shall be made on account of
materials and equipment delivered and suitably stored at the site for subsequent incorporation in the
work. If approved in advance by the City, payment may similarly be made for materials and
equipment suitably stored off the site at a location agreed upon in writing. Payment to Contractors
and suppliers for materials and equipment stored on or off the site shall be conditioned upon
compliance with procedures satisfactory to the City to establish the City's title to such materials and
equipment or otherwise protect the City's interest, and shall include applicable insurance, storage
and transportation to the site for such materials and equipment stored off the site.
7.4 Program Manager shall submit to The City its draft request for payment on or about the 25th
day of each month estimating the percentage of completion of each category in the breakdown of
the Project Budget as referred to in Article 3 for approval by the City. The Designated City
Representative shall review the Program Manager's request for payment and shall inform the
Program Manager of any reasons why such request is not suitable for payment, if any. Prior to the
submittal to the City, the City will review the requested percentage of completion for each activity.
Provided the request is in proper form, the Program Manager shall submit the request to the City.
The payment request will be in the format as provided by the City and will refer to the schedule. In
the event of any difference between the City's estimate and Program Manager's estimate of
completion of a breakdown item, the City's judgment shall prevail.
7.5 Upon receipt of a payment request, the City shall:
Review that request promptly for the purpose of determining if the payment
request is a proper payment request; and,
2. Return any payment request determined not to be a proper request suitable for
payment to Program Manager as soon as practicable, but not later than seven (7)
days after receipt. The returned request for payment shall be accompanied by a
document setting forth in writing the reasons why the payment request is not
proper.
7.6 Any progress payment which is undisputed and properly submitted shall be paid within
thirty (30) days of submission. If not so paid, the amount unpaid shall accrue interest to Program
Manager equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the California
Code of Civil Procedure. The number of days available to the City to make a payment without
incurring interest pursuant to this Section shall be reduced by the number of days by which the City
exceeds the seven-day return requirement set forth in this Article 7, Section 7.5.2.
7.7 In making these progress payments, the City will retain ten percent (10%) (of the direct cost
component of the Project Budget only -excluding fees payable to the Program Manager) of the
estimated amount until final completion and acceptance of the work unless otherwise agreed upon
by Program Manager and the City. When the work is substantially complete as defined in Article 5,
the City shall retain a maximum amount of 5% and shall release to Program Manager all of any
excess amount for disbursement to the Contractors.
7.8 Except as otherwise prohibited by law, Program Manager may elect to require the City to
disburse to Program Manager payments payable to Contractors without any retention, by causing
the affected Contractors to post securities in accordance with California Public Contract Code
Section 22300.
79 The City may withhold payment (in excess of retentions) or, on account of subsequently
discovered evidence, nullify the whole or a part of any certificate to such extent as may be
necessary to protect the City from loss on account of the following (and each contract awarded to
Contractors shall allow withholding for):
1. Defective work not in the process of being remedied.
2. "Stop Notice" claims filed.
3. Failure of Program Manager or its Construction to make payments properly
to Contractors for material or labor when no actual dispute exists concerning
such payment.
4. Default of Program Manager, in the performance of the material terms of this
Agreement.
7.10 If stop notices are filed with the City, the City shall withhold the amount required from
certificates until such claims shall have been resolved pursuant to applicable law California Civil
Code Section 3179, ct seq.
ARTICLE S
FINAL PAYMENT
8.1 The City shall pay the final payment due Program Manager under this Agreement and Program
Manager shall be authorized to disburse same when:
1. The Agreement has been fully performed by the Program Manager;
2. Request for Final Payment has been made;
3. Release of all liens and Stop Notices has been accomplished;
4. Program Manager has presented to the City releases of all filed claims against
the City by the Contractors; and,
5. Program Manager has complied with the conditions precedent set forth below.
8.2 The Program Manager may, if any Contractor refuses to furnish a release or receipt in full,
furnish a bond satisfactory to the City, to indemnify against any such lien.
8.3 When a certificate of substantial completion from Program Manager is received by the City
covering the entire Project, the Designated City Representative will issue a Notice of Completion
and within ten (10) days thereafter record such Notice of Completion. A certified conformed copy
of the recorded Notice of Completion will be sent to the Program Manager.
8.4 Notwithstanding the foregoing, neither final payment nor any remaining retained percentage
shall become due until the Program Manager submits to the City (1) an affidavit that payrolls, bills
for materials and equipment, and other indebtedness connected with the work for which the City or
the City's property might be responsible or encumbered (less amounts withheld by the City have
been paid or otherwise satisfied, (2) a certificate evidencing that insurance required by the Project
Documents to remain in force after final payment is currently in effect and will not be canceled or
allowed to expire until at least thirty (30) days' prior written notice has been given to the City, (3) a
written statement that the Program Manager knows of no substantial reason that the insurance will
not be renewable to cover the period required by the Project Documents, (4) consent of surety, if
any, to final payment and (5) if required by the City, other data establishing payment of satisfaction
of obligations. such as receipts, releases and waivers of liens, claims, security interests or
encumbrances arising out of the Agreement to the extent and in such form as may be designated by
the City. If a subcontractor refuses to furnish a release or waiver required by the City, the Program
Manager may furnish a bond satisfactory to the City to indemnify the City against such lien. If such
lien remains unsatisfied after payments are made, the Program Manager shall refund to the City all
money that the Program Manager may be compelled to pay in discharging such lien, including all
costs and reasonable attorneys' fees.
8.5 After issuance of the Certificate of Substantial Completion by the appropriate Consultant(s),
but not later than 35 days thereafter, Program Manager will submit to the City a detailed statement
showing the remaining unpaid Project costs, together with a request for the City payment in the
amount thereof; provided, the City shall not be responsible for any payment in excess of the Project
Budget (as amended from time to time); provided further, the City may withhold sums for
incomplete work; and for any other cause under the Agreement.
8.6 Program Manager shall, from the effective date of Acceptance until the expiration of four
years after final settlement under this Agreement, preserve and make available to the City, all its
books, records, documents, and other evidence bearing on the costs and expenses of Program
Manager under this Agreement.
ARTICLE 9
INDEMNIFICATION
9.1 Program Manager shall indemnify, defend and hold harmless the City, its officers, agents,
employees, and volunteers from and against;
9
1. Any and all claims, actions, and proceedings relating to:
(1) any breach or default in the performance of, or the omission to perform, any
obligation on Program Manager's part under any term or condition of the
Agreement; and
(2) any negligent act or omission to act by Program Manager, Program
Manager's agents, representatives, or employees, relating to the performance
of, or omission to perform, any term or condition of the Agreement; and
(3) any liability of any nature, for or on account of any patented or unpatented
article, appliance or device used in the performance of the Agreement;
2. All reasonable costs, attorneys' fees, expenses, and liabilities incurred in the
defense of any claim, action or proceeding brought pursuant to this Section.
9.2 if any such claim, action, or proceeding is brought pursuant to Section 9.1 against the City
or the City's officers, agents, employees, or independent contractors, Program Manager upon notice
from the City, shall defend the same at Program Manager's expense by counsel satisfactory to the
City and Program Manager.
9.3 The City shall promptly notify Program Manager of any claim, action, or proceeding
against the City or the City's officers, agents, employees, or independent contractors, relating to the
performance, or omission to perform, any term or condition of this Agreement. The City shall
cooperate fully in the defense of such claim, action, or proceeding.
9.4 The City shall not be liable or responsible for any accident, loss or damage occurring on or
to the work prior to the completion and acceptance of same, unless otherwise specifically
agreed to at the time of occupancy by the City, unless caused by the active negligence of the
City or its employees, but specifically excluding the Program Manager or anyone acting by
or through the Program Manager.
ARTICLE 10
CONCEALED OR UNKNOWN CONDITIONS
If conditions are encountered at the site which are (a) subsurface or otherwise concealed
physical conditions which are at variance with those indicated in the Project Documents or (b)
unknown physical conditions of an unusual nature which differ materially than those ordinarily
found to exist and generally recognized as inherent in construction activities of the character
provided for in the Project Documents, then notice by the observing party shall be given to the
other party promptly before conditions are disturbed and in no event later than 21 days after first
observance of the conditions, The appropriate Consultant will promptly investigate such conditions
and notify the City and Program Manager if any anticipated increase in the cost of or time to
complete the Project. Upon such notification, Program Manager will cause the affected Contractors
to be notified and to prepare change orders to their Construction Contracts to reflect such additional
expense and/or time. Such change order shall processed under the guidelines set forth in Article 15
10
below. If the increases in Project cost causes the Project Budget to proceed, the City shall either (i)
instruct Program Manager to cause the re -design of the Project or a component thereof, or modify
the scope of the Project, so fit within the Project Budget, or (ii) adjust the Project Budget to include
the additional costs. Any time delay associated with the foregoing shall cause an equitable
adjustment to the Completion Date. as If the Consultant determines that the conditions at the site
are not at variance with those indicated in the Project Documents and that no change in the items of
this Agreement is justified, the Consultant shall so notify the City and Program Manager in writing,
stating the reasons, and Program Manager shall notify all potentially affected Contractors of such
determination and such reasons. Claims by the City or any affected Contractor in opposition to such
determination must be made within 21 days after the Consultant has given notice of its
determination. If the City and any Contractor cannot mutually agree on the amount of an
adjustment to the contract sum for an affected Construction Contract, the adjustment shall be
determined in accordance with the guidelines set forth in Article 17 below.
ARTICLE 11
INSURANCE
11.1 General Requirements
Before allowing a Contractor to commence the Project work, Program Manager shall
require such Contractor provides the insurance policies specified below, and shall file copies of
certificates of said insurance with the City, Each of the insurance policies shall be issued by:
1. Either a California Admitted Surety/Insurer OR a current Treasury Listed
Surety (Federal Register); and,
2. Either a current A.M. Best A VIII rated Surety or Insurer.
11.2 Public Liability and Property Damage Insurance
Occurrence type Public Liability and Property Damage Insurance shall protect the City, its
officers, agents, employees, volunteers and Program Manager, from claims for damages for
personal injury including wrongful death, as well as from claims for property damages, which may
arise from or in connection with the Contractor's performance or the Contractor's omission to
perform any term or condition set forth in the Contractor's Construction Contract, whether such
performance be by the Contractor or anyone directly or indirectly employed by the Contractor as
follows:
1. General Liability: $ 1,000,000 combined single limit per occurrence for
bodily injury, personal injury and property damage. If Commercial General liability
Insurance or other form with a general aggregate limit is used, either the general
aggregate limit shall apply separately to any act or omission to act by the Contractor
under its Construction Contract or the general aggregate limit shall be twice the
required occurrence limit;
2. Automobile Liability: $1,000,000 combined single limit per accident for
bodily injury and property damage.
11
The General Liability and Automobile Liability coverages shall name the Program
Manager, the City, and their respective officers, agents, employees and volunteers, as additional
insureds, and shall provide that the City and Program Manager shall be given thirty (30) days
advance written notice of expiration, reduction or cancellation of such coverage, .by certified mail,
Program Manager shall cause each Contractor to maintain a Commercial General Liability Policy
of insurance with an aggregate limit of liability of not less than $2,000,000.00 products completed
operations, a general aggregate of not less than $2,000,000.00 and excess coverage of not less than
$2,000,000 each occurrence and general aggregate; provided, however, the City may waive or
reduce the minimum coverage requirements with respect to any Contractor. All such policies shall
meet the requirements set forth in Section 11.1.
11.3 Fire Insurance
Program Manager shall, to the extent appropriate, and each Contractor, to the extent
appropriate, to maintain fire insurance on such party's own equipment and machinery, or to
adequately self -insure the same.
11.4 Property Insurance/Builders Risk
The City shall provide, or cause to be provided, and maintain at its sole cost, property
insurance in the amount of the value of the improvements on the property where the Project is to be
constructed on a replacement cost basis. The insurance shall include the interest of the City, the
Program Manager and its agents. Such insurance shall be on an all-risk policy form.
ARTICLE 12
BONDS
12.1 General Requirement
This Article sets forth the bonding requirements to be imposed upon the Project
Contractors. Before allowing a Contractor to enter upon the Project Site and perform Project
construction work, the Program Manager shall file with the City four duplicates of each bond
required under this Article. These bonds shall be in the amounts and for the purposes specified
below. They shall be surety bonds issued by: either a California Admitted Surety or a current
Treasury Listed Surety (Federal Register), and either a current A.M. Best A VIII rated Surety or an
admitted surety insurer which complies with the provisions of the California Code of Civil
Procedure Section 995.660. Should any surety or sureties upon said bonds or any of them become
insufficient, Program Manager shall require renewal of said bond(s) with good and sufficient
sureties within ten (10) days after receiving notice from the City that the surety or sureties are
insufficient. The cost of bonds are included in the Project Budget.
12.2 Performance Bond
Program Manager shall (i) post a Performance Bond in favor of City on a form reasonably
acceptable to the City Attorney and equal in amount to 100% of the direct construction costs of the
Project, as security for the faithful performance of its obligations under the Construction
12
Management Agreement, and (ii) require each Contractor designated by the City to deliver to the
City an executed Performance Bond in favor of the City on a form reasonably acceptable to the
City Attorney and equal in amount to 100% of the contract sum of such Contractor's Construction
Contract, as security for the faithful performance by such Contractor of his obligations under his
Construction Contract.
12.3 Payment Bond
Program Manager shall (i) post a Payment Bond in favor of the City in an amount equal to
100% of the direct costs component of the Project Budget, as security for the payment to the
Contractors, and (ii) requires each Contractor designated by the City to deliver to the City an
executed Payment Bond in favor of the City in an amount equal to 100% of the contract amount
such Contractor's Construction Contract as security for the payment of all persons performing labor
and furnishing materials under such Contractor's Construction Contract.
ARTICLE 13
DESIGN AND PROGRAM MANAGEMENT WORK PRODUCT
The City acknowledges that all reports, drawings, specifications, field data, field notes,
laboratory test data, calculations, estimates and other similar documents prepared by Program
Manager and/or its Consultants are instruments of professional service, not products. Although
ownership of such documents and any copyrights thereto or therein are normally retained by
Program Manager, they nonetheless shall in this instance become the property of the City upon
final payment to Program Manager of any and all amounts owed or due under terms of this
Agreement. No such documents should be subject to unauthorized use or reuse, that is use or reuse
without prior written authorization of Program Manager to do so. Any reuse of the documents by
the City without express written authorization by the Program Manager shall be at the City's sole
risk and without liability or legal exposure to the Program Manager or its Consultants. The Program
Manager shall cause its Consultants to turn over to the City the following: Record Drawings (as-
builts) on mylar (not sepia mylar) signed by the architects and engineers, diskettes of computer
generated plans, equipment and product manuals, all contractor's warranties and guarantees.
ARTICLE 14
TERMINATION
This Agreement may be terminated at any time by either Program Manager or the City upon
written notice to the other party. If either party gives notice of termination, the City shall issue
payment for all services and work performed and costs incurred to the date of written notice. In the
event this Agreement is terminated, Program Manager's shall assign to the City, effective upon
such termination, all of its agreements with the Project Team, subject to the prior rights of the
surety providing the payment and performance bond required under this Agreement.
13
ARTICLE 15
CHANGES
15.1 Changes affecting Program Manager.
Adjustments to the fee compensation of Program Manager under this Agreement, shall be
determined as follows.
1. For services performed by Program Manager under this Agreement due to an
approved change in the scope of the work of the Project, four percent (4%) of the net
additional cost of the work (including additional work performed by the Project
Team, additional fees, equipment, labor and materials reflected in each change order
with Contractors that results from such scope change).
ARTICLE 16
WARRANTY
16.1 The Program Manager shall require each Contractor to warrant to the City in writing that all
material and equipment furnished under such Contractor's Construction Contract will be of good
quality and new unless otherwise required or permitted by the Project Documents, that such
Contractor's work will be free from defects not inherent in the quality required or permitted, and
that the work will conform with the requirements of the Project Documents for a period of one (1)
year from the date of the Notice of Completion for the Project. Work not conforming with these
requirements, including substitutions not properly approved and authorized, may be considered
defective. Such warranties may exclude damage or defects caused by abuse, modifications not
performed by the Contractor, improper or insufficient maintenance, improper operation, normal
wear and tear under normal usage or improper or defective work on other portions of the Project
performed by other Contractors.
ARTICLE 17
DISPUTES/CLAIMS
17.1 Claims Resolution Involving Consultants and Contractors
Disputes involving Consultants and/or Contractors shall be resolved in accordance with the
rules set forth in the City's Standard Specifications.
17.2 Dispute Resolution Under this Agreement
Unless both parties otherwise agree in writing, all disputes between the parties regarding the
interpretation of this Agreement or the performance by a party hereunder shall be resolved through
binding, judicial arbitration, using a private arbitration services such as JAMS/Endispute or similar
service acceptable to each party; provided, however, in the event the parties are unable despite their
good faith efforts to agree upon the procedures for such arbitration or the arbitration service to
utilize, then, upon written notice from either party, arbitration shall be conducted pursuant to the
commercial arbitration rules of the American Arbitration Association. In the conduct of such
14
arbitration, each party shall be afforded the right for discovery of evidence in accordance with
Sections 1985 et seq. of the California Code of Civil Procedure, but any disputes that may arise
regarding discovery shall be submitted to the arbitrator for resolution.
17.3 Wages & Records
17.3.1 Wage Rates
a. Pursuant to Section 1770 and 1773, et seq. of the California Labor Code,
the Director of Industrial Relations has ascertained the general prevailing rate of per
diem wages and the rates for overtime and holiday work in the locality in which the
work is to be performed for each craft, classification, or type of workman needed to
execute the contract which will be awarded to the successful bidder, copies of which
are on file and available upon request at the Public Works Agency of the City, and
which Program Manager shall post at the Project Site.
b. Program Manager shall require that each Contractor and subcontractor
under him, pay not less than the said specified rates to all laborers, workmen, and
mechanics employed in the execution of the Agreement.
c. In case it becomes necessary for Program Manager, or any Contractor to
employ on the Project any person in a trade or occupation (except executives,
supervisory , administrative, clerical, or other non -manual workers as such) for
which no minimum wage rate is herein specified, such Program Manager shall
assure that such party shall immediately notify the City who will promptly thereafter
determine the prevailing rate for such additional trade or occupation and shall
furnish such party with the minimum rate based thereon. The minimum rate thus
furnished shall be applicable as a minimum for such trade or occupation from the
time of the initial employment of the person affected and during the continuance of
such employment.
d. The City will not recognize any claim for additional compensation
because of the payment by any party of any wage rate in excess of the prevailing
wage rate set forth as provided herein.
ARTICLE 18
LABOR COMPLIANCE
18.1 Labor Compliance
The parties acknowledge that certain labor compliance regulations apply to the Project. It
shall be Program Manager's responsibility to assure that the following procedures and record
keeping are undertaken by Program Manager.
18.1.1 Procedures
15
A. The Program Manager shall be responsible to enforce the Construction Contract provisions
and ensure that all labor compliance requirements are performed and documented in the
Project file(s). Generally, labor compliance requirements are discussed at the pre -
construction conference.
B. When labor compliance problems are discovered, Program Manager will require that they
be reported to the City. The City is responsible for determining the appropriate action
required to remedy or address the problem. When labor compliance problems are
discovered by process review they should be documented in the process review report with
a recommendation for correction of the problem.
18.1.2 Record Keeping_ The Program Manager shall maintain sufficient records to ensure each
Contractors' compliance with wage and apprenticeship sections of the Agreement. Specific actions
required, include but are not limited to:
A. Verify inspector's daily reports which note employee names, labor classifications, hours
worked and equipment working on the Project. Ideally, employee names, classifications,
and hours worked should be noted on each daily report. If this is not possible, then as a
minimum, the data must be reported in at least one diary during the week.
B. Conducting spot interviews with employees on the Project. State Form HC-0031 or a
similar form should be used,
C. Maintaining written evidence of apprentices employed on the Project.
D. Ensuring that each Contractor submit certified payrolls and/or owner operator listings (as
appropriate) for their work and from all subcontractors or equipment rental companies who
perform work on the Project. Every laborer or mechanic performing work on the Project
must appear on either a certified payroll or owner operator list.
E. Spot checking the payrolls or listings to ensure that at least the applicable State prevailing
wage rates as referred by the special provisions are paid.
F. Cross checking reports, interviews, payrolls and wage rates in order to determine each
Contractor's compliance. Comparing all day labor work to certified payrolls. Employees'
names, classifications, and wage rates should match.
G. Ensuring that the Program Manager posts all specified posters, notices, wage determination,
etc. at the j ob site.
H. Enforcing necessary sanctions against Contractors for failure to submit payrolls or
noncompliance with the labor standard requirements. Sanctions must be in conformance
with current state policy as described in the Caltrans Construction Manual. Chapter IX,
Section 9-01, "Labor Compliance."
16
I. Reporting any apparent violation of State or Federal labor requirements to the City
immediately upon discovery.
ARTICLE 19
GENERAL PROVISIONS
19,1 Assignment
Neither this Agreement nor any part thereof shall be assigned by the Program Manager
without prior written consent of the City.
19.2 Amendments to the Agreement
Amendments to the Agreement must be in writing and approved by both parties before they
become effective.
19.3 Conflicts in Documents
In the event of conflict between the terms set forth in the Agreement and any Exhibits, the
provisions listed in the Agreement shall control.
ARTICLE 20
NOTICES
20.1 NOTICE
Any notice, tender, demand, delivery, or other communication pursuant to this Agreement
shall be in writing and shall be deemed to be properly given if delivered in person or mailed by first
class or certified mail, postage prepaid, or sent by facsimile or other telegraphic communication in
the manner provided in this Section, to the following persons:
To the City: Clerk of the City Council
The City of Santa Ana
20 Civic Center Plaza (M-30)
P.O. Box 1988
Santa Ana, CA 92702-1988
Facsimile (714) 647-6956
With courtesy copy to:
Executive Director of Public Works Agency
The City of Santa Ana
20 Civic Center Plaza (M-21)
P,O. Box 1988
Santa Ana, California 92702
Facsimile (714) 647-5622
17
And to
Office of the City Attorney
20 Civic Center Plaza (M-29)
P.O. Box 1988
Santa Ana, California 92702
Facsimile (714) 647-6515
To Program Manager: Gordon & Williams General Contractors, Inc.
Attn. Mr. Mark Williams, Managing Principal
2 Faraday
Irvine, CA 92618
Facsimile (949) 588-2877
A party may change its address by giving notice in writing to the other party. Thereafter, any
notice, tender, demand, delivery, or other communication shall be addressed and transmitted to the
new address. If sent by mail, any notice, tender, demand, delivery, or other communication shall be
effective or deemed to have been given three (3) days after it has been deposited in the United
States mail, duly registered or certified, with postage prepaid, and addressed as set forth above. If
sent by facsimile, any notice, tender, demand, delivery, or other communication shall be effective
or deemed to have been given twenty-four (24) hours after the time set forth on the transmission
report issued by the transmitting facsimile machine, addressed as set forth above. For purposes of
calculating these time frames, weekends, federal, state, County or City holidays hall be excluded.
[Signatures provided on next page]
18
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the date and
year first above written.
ATTEST:
THE CITY OF SANTA ANA
By:
Patricia E. Healy David N. Ream, City Manager
Clerk of the Council
k th
Gordon & Williams General Contractors, Inc.,
By: \,A,A,_ , " 7
Name: kAN."Ak 'Q.
Title: 0
19
EXHIBIT 'A'
REQUESTFOR QUALIFICATIONS
DESIGN AND CONSTRUCTION. OF NEW PARKING STRUCTURE AT
SANTA. ANA BOULEVARD AND ROSS STREET
CITY OF SANTA ANA
PUBLIC WORKS AGENCY
SANTA ANA, CALIFORNIA 92701
PROJECT DIRECTOR
Souri Amirani
Manager
Phone (714) 647-5640
TABLE OF CONTENTS
Background......................................................................................................................................1
TheSponsor.................................................................................................................................1
1
ClientGroup........................................................................................................................
...........1
Project Delivery Method..............................:....................................................................
..Program ...........................
Management...... ..............................................1
I......
..........
Scopeof Work .......................................................................................................3
.................
The Selection Process- Overview .....................................................................................................3
The Selection Process -In Detail.....................................................................................................4
TheSchedule.............................................................
Other Terms and Conditions........................................................................................6
The Submittal Requirements.............................................................................................................
Request for Qualifications Costs.....................................................................................................9
TheSubmittal Deadline ...............................................................................................................9 ..
Attachment "A"
ConceptualSite Plan...............................................................................................
FeeProposal Format.........................................................................................
.......Attachment "B"
Certificate of Non -Discrimination by Contractors ...... .............................................Attachment "C"
Sample of Certificate of Insurance......................................................................... Attachment "D"
REQUEST FOR QUALIFICATIONS (RFQ)
Parking Structure at Santa Ana Boulevard and Ross Street
BACKGROUND
The City of Santa Ana is offering an opportunity for participation in the design and construction of a new
three -level (2 story), 355 space reinforced concrete public parking structure. The new parking structure
will be approximately 270 foot long by 140 foot wide. The parking garage will be located in the existing
Civic Center parking lot near the intersection of Santa Ana Boulevard and Ross Street in the City of Santa
Ana (See Attachment"A")
The new parking structure is being constructed to recover lost parking spaces as a result. of a proposed
project to build a new State Appeals Court adjacent to the proposed parking structure. The new State
Appeals court will be constructed by others in the current location of the Orange County Juvenile
Detention Center. The demolition of the juvenile detention center may be included in this contract.
THE SPONSOR
The City of Santa Ana is the public sponsor for this Request for Qualifications. The City of Santa Ana's
function will be administrative and financial. Administratively the City of Santa Ana will execute all
required contracts to support the project, and direct the Team and the working client group as defined
below. All proposals, drawings, and specifications will be subject to the final approval of the City of
Santa Ana.
In addition, the City of Santa Ana will be preparing the environmental documentation, which will be
completed prior to any demolition and construction.
CLIENT GROUP
A Working Client Group will consist of a committee of representatives from the City of Santa Ana Public
Works Agency, Planning & Building Agency and other Agencies as appropriate. The City of Santa Ana
Public Works Agency will _serve as point of contact for the Client Group.
-- PROJECT DELIVERY METHOD
r
The City of Santa Ana is seeking professional services from a Program Manager to provide Design and
Construction Management services for this project. The Program Manager may be a single firm, a
consortium, or a joint venture. This Delivery Method will be characterized by a Not -to -Exceed fee for the
professional services described herein and a single price contract for construction (fixed at the conclusion
of Design Development). The selected Team, utilizing its construction management "arm" will be
required to competitively bid out all construction trade work and comply with all local prevailing wage
requirements.
PROGRAM MANAGEMENT
The Program Manager's Team should be composed of experienced and highly regarded professionals
who have demonstrated a capacity to produce superior facilities on a cost-effective basis, especially those
involving parking structure facilities. At a minimum, the Team should include:
1 of9
A Program Managerresponsible for coordination activities such as:
- Providing general administration of the Agreement with the City of Santa Ana.
- Interpreting the requirements of the Project Documents.
- Managing and supervising its Consultants and design professionals and processing of
plans and specifications for the Project
- Managing as City of Santa Ana's 'representative the advertisement for bids for all
components of construction for the Project, including assuring all competitive
bidding requirements applicable to the Project pursuant to City of Santa Ana Charter
Section 421 are in compliance.
Managing and supervising the services provided by the Construction Management
entity, for the purpose of causing the Project to be completed within the Project
Budget and in accordance with the Project Documents.
- Coordinate work efforts and schedules with the construction manager of the State
Appeals Court building project.
Coordinate work efforts and schedules with the County relating to the juvenile
detention center and the temporary displacement of parking in the Civic Center. -
• A California licensed Architect and/or Engineer responsible for design activities such as:
Developing the design for the project within budgetary and schedule commitments.
- Processing entitlements related to design responsibilities such as planning and
plan -check approvals.
Ensuring regulatory and code compliance.
Preparing estimates of probable construction costs.
Preparing construction documents for multiple subcontractor bidding.
A Construction Management entity: responsible for pre -construction and construction activities such
as:
- Design -estimating.
- Value engineering and constructibility reviews.
- Publicly bidding out construction trades by Division pursuant to City of Santa Ana
Charter Section 421 of the Santa Ana Municipal Code Section 2-801 to 2-815.
- Obtaining entitlements related to construction such as building permits.
Maintaining the construction schedule.
- Job site safety.
�- - Providing methods and means of construction.
- Fulfilling the requirements of the construction documents.
Guaranteeing the quality of the construction.
Correcting any deficiencies covered by the guarantee. .
The proposing Team may wish to add other specialized consultants to the entity to augment its capacity to
quickly. and professionally address the requirements of the parking structure during the design, bidding
and construction process.
Note: The above descriptions are of services to be provided, not of separate individuals or entities. The
successful Team may consist of one or more individuals or entities, provided -that all of these• services are
provided to the City.
2 of 9
SCOPE OF WORK
THE SITE
The site is located in the existing parking lot at 20 Civic Center Plaza, Santa Ana, CA 92701. The eastern
boundary faces an existing juvenile detention center, the northern boundary faces the existing City Hall
building and the southern boundary faces Santa Ana Boulevard (See Attachment "A" for conceptual site
plan). The site is relatively level and currently operates as an asphalt parking lot.
• DEMOLITION OF EXISTING JUVENILE DETENTION CENTER .
The existing County of Orange Juvenile Detention Center building may be demolished as part of this
contract. The structure is located at 500 Ross Street and is approximately 18,000 square feet in size.
At the time of the preparation of this RFQ, the County of Orange was determining the feasibility of
relocating the structure. If the structure is to be. relocated, the County of Orange will perform the
relocation. Otherwise, the Program Manager and his Team are responsible for all coordination and
permitting as required for the demolition. The fee proposal should include all professional services fees
for this work.
• SITE PREPARATION
The Program Manager and his Team are responsible for all site preparation to get the proposed parking
structure site "pad ready".
THE PARKING STRUCTURE
The new parking structure will be a new three -level (2 story), 355 space parking structure. The new
parking structure will be approximately 270 foot long by 140 foot wide. The structure is to conform to all
applicable rules, regulations and codes. At a minimum, the parking structure should include the following
features:
Cast -in -place, reinforced concrete conforming to all applicable codes and regulations.
Full ADA accessibility.
-_ - Barrier cables at all interior ramp locations.
- Two (2) steel stairs
Two (2) 3-stop hydraulic elevators
One (1) pedestrian bridge from Santa Ana Boulevard to complement the Civic Center
Master Plan/Circulation pattern.
The design and construction budget for this facility is approximately $2.6 million.
THE SELECTION PROCESS - Overview
The elements and sequence of this qualification -based selection process follows: (Details may be found in
the section titled "The Selection Criteria")
Issuance of this RFQ.
Pre -Submittal Conference to Discuss Project Objectives.
Submittal of Qualifications Package and Fee Proposal.
- Evaluation of Qualifications by a Panel.
3 of
Selection of Finalist(s) by the Panel.
- Presentation by Finalists, if necessary.
- Selection of Team.
Specific project proposal or design proposals are not expected, nor are they solicited.
THE SELECTION PROCESS - IN DETAIL
1. Issuance of the Request for Qualifications
The City of Santa Ana is soliciting the qualifications of a Team to design and construct a
parking structure at the Civic Center parking lot located near the intersection of Santa Ana
Boulevard and Ross Street. .
2. Pre -Submittal Conference to Discuss Project Objectives
The City. of Santa Ana will conduct a pre -submittal conference to discuss this projects
objectives and answer questions from prospective Teams. Attendance is mandatory. This
conference will be held:
Monday, April 22, 2002
2:00 p.m.
1 st Floor
City of Santa -Ana Ross Annex
20 Civic Center Plaza
Santa Ana, CA 92701
3. Evaluation of Qualifications by Panel
A selection panel will be composed of representatives from the City of Santa Ana's Public
Works Agency, Planning and Building Agency and other Agencies as appropriate. The panel
may conduct a two-step evaluation process which will culminate in the selection of the Team.
In the first step, the panel will perform an initial review of the submittals,. and create a
"shortlist" of finalists. If a second step is used, the City of Santa Ana will invite the
s "short-listed" Teams to make an oral presentation. In addition, the panel will make the final
selection and open the most qualified Team's fee proposal, and commence negotiations.
The Selection Criteria
The panel will select a Team with the capability to deliver a project that meets the objectives of the City
of Santa Ana. The Panel will rely on the Team's written presentations, investigation of previous projects,
current commitments, references, industry contacts, and discussions with the Team.
The important threshold issues for the initial phase of the selection process are:
• Does the Team have similar experience with Public Agencies?
Does the Team have a direct, relevant experience in parking structure design, construction, and
project management?
4 of 9
+ Does -the Team have the resources (i.e., staff, physical facilities, financlai depth) needed to undertake
this project?
• Does the Team have a proven ability to implement projects quickly and cost-effectively?
• Does the Team have established, clear lines of responsibility within their -organization, as well as
open lines of communication with their clients and the community they serve?
• Is the Team associated with projects known to be of exceptional quality and reputation?
+ Does the Team have a demonstrated history of cost control on past projects?
• Do the Team and/or individuals have a history of working together as a Team?
+ Does the Team have a demonstrated history of quality control on past projects?
• Are the Team's individual participants and their office located in the same metropolitan area?
• Does the Team have a record of on -schedule delivery?
The important threshold issues for the final phase of the selection process are:
Team and client compatibility
- Experience
- The right blend of design creativity, attention to detail and functional practicality
- Reputation for reliability and well -managed projects
- Cost Control
The above threshold issues will be used by the panel in evaluating submittals, developing a short list,
evaluating finalist presentations, and awarding a contract
4. Selection of Finalists
-The panel will select finalists for oral presentations if necessary. Notice of final selection or
"short list" will be mailed to all candidates on or about May 24, 2002.
5. Presentations by Finalists/Fee Proposal
Following selection of the finalists with the "apparent best" qualifications, presentations may
be scheduled. The purpose of the presentation is to enable the finalists to provide a more
in-depth demonstration of qualifications and capacity for this project
A sealed fee cost proposal in a separate envelope' must be submitted by the Team. The
specific format for this submittal is included as Attachment "B". Upon selection of the most
qualified finalist, the sealed fee proposal will be opened and negotiations will commence to
determine the broad outlines of a working relationship (Scope of Work), including financial
matters. If an Agreement cannot be reached, negotiations will be terminated and the next
highest ranked finalist will be invited to negotiate and their sealed fee proposal will be
opened. The conclusion of these interviews and negotiations will result in the selected Team
entering into an Agreement with the City of Santa Ana. All other sealed fee proposals will be
returned (unopened). to remaining finalists.
At the conclusion of these interviews, a decision by the panel. will be forwarded to the City of
Santa Ana City Council for approval of contracts.
5 of 9 .
9
THE SCHEDULE
At present, the Sponsor believes that the timing will be as follows:
April 10, 2002 Release of RFQ w
April 22, 2002 Pre -Submittal Conference
May 13, 2002 RFQ Response Submission
May 24, 2002 Ranking of Respondents and Selection of Finalists ("Shortlist")
June 10, 2002 Presentations by Selected Finalists (if necessary)
July 1, 2002 Team's Contract Awarded by City of Santa Ana City Council
July 8, 2002 Project Kick -Off
July 8, 2002 .to September 15, 2002 Schematic Design/Design Development Complete
September 16, 2002 Commence Construction Documents and Obtain all Necessary
Permitting
November 2003 Construction Completion Deadline
December 2003 Scheduled Construction of State Appeals Court (by Others) .
OTHER TERMS AND CONDITIONS
1. The project will be implemented in compliance with the City of Santa Ana's policies, as well
as Prevailing Wages.
2. The Sponsor regards the inclusion of California -based designs, engineering, and construction
professionals, facilities, and services as part of the Team to be highly desirable, but not
mandatory.
3. ; The Sponsor reserves the right to modify any and all aspects of the selection process, and
waive any defects as to form or content of the Team's proposals.
4. The Sponsor reserves the right to accept or reject any and all responses received as a result of
this request, and to cancel in part or in its entirety this Request for Qualifications. If all
proposals are rejected, the Sponsor is not barred from resoliciting.
5. The Sponsor reserves the right to amend this Request for Qualifications by addendum prior to
the final dates of submission.
6. All reports, proposals, or other data or materials which are submitted shall become the sole
property of the City of Santa Ana with the exception of the confidential Financial Capacity
information and sealed fee proposals which will be returned to all proposers after award of
contract to the selected Team.
6of9
7. All products used or developed in the execution of any contract resulting from this request
will remain in the public domain at the completion of this project.
8. The City has an affirmative action program. The purpose of the affirmative action program is
to encourage. certified minority business enterprises and women business enterprises. All
submitting firms must have established affirmative action programs approvable by the City.
The attached "Certification of Non -Discrimination by Contractors" shall be competed by
each submitting firm and included in the proposal (Attachment "C").
9. A sample certificate of insurance is enclosed for your reference (Attachment "D"). With
respect to performance of work under this Contract, the Team shall maintain and shall require
its subcontractors, if any, to maintain insurance as described below:
A. Worker's Compensation insurance with statutory. limits, :any employer's. liability
insurance with limits not less than $1,000,000 per accident.
B. Commercial general liability insurance, or equivalent form, with a combined
single limit of not less than $1,000,000 per occurrence. If such insurance
contains a general aggregate limit, such limit shall apply separately to each
project the Team performs for the City of Santa Ana. Such insurance shall (a)
name the City of Santa Ana, its officers, agents, representatives, volunteers and
employees as additional insureds; (b) be primary with respect to insurance or
self-insurance programs maintained by the City of Santa Ana; and (c) contain
standard separation of insureds provisions; and (d) give to the City of Santa Ana
prompt and timely notice of claim made or suit instituted arising out of Team's
operations hereunder.
C. Business automobile liability insurance, or equivalent form, with a combined
single limit of not less than $1,000,000 per occurrence. Such insurance shall
include coverage for owned, hired and non -owned automobiles.
D. Professional liability (errors and omissions) insurance, with a combined single
limit of not less than $1,000,000 per occurrence.
THE SUBMITTAL REQUIREMENTS
The respondents to this RFQ should submit five numbered sets of writteri information requested below
(with the exception of the Financial Capacity materials, of which one copy should be submitted under
separate.cover and which will be kept strictly confidential). The Sponsor prefers to receive these materials
in vertically bound form, either loose-leaf or spiral, 8'/2" x l l", with section headings, tabbed and clearly
marked by subject titles.
The response should state the intended role for each partner or major consultant in the implementation of
the project, as well as -dearly delineate the party responsible for overall management.
The response will include resumes of the key individuals who will be included in the project and
alternative Team members that are candidates for inclusion on the Team. The resumes should describe
each individ.ual's/firm's relevant professional qualifications and experience. Candidates should carefully
review the qualifications of their Team members to ensure they have not included anyone that has had an
adverse history of performance on projects that may cause the panel to reject the proposal because of that
deficiency. In addition, candidates are. to include information pertaining to construction- related litigation
within the past 5 years. Inclusion of this information does not mean the candidates will be disqualified.
7 of
im
The submittal shall clearly idoniify management level personnel, any other supporting personnel, and the
entity's project manager. The submittal shall also include a graphic depiction of the organizational
structure of the persons and firms associated with the project. The Team shall not be allowed to substitute
any individuals or firms for those identified without. the written permission of the Sponsor.
1. Experience
The response should provide evidence of direct, relevant experience in the design and
construction of parking structures by members of the Team. The submittal should include a
listing of relevant, completed projects that will demonstrate the competence of all architects,
engineers, contractors, and other consultants included on the candidate's Team to undertake and
complete this project in a successful and satisfactory manner. The submittal should include all
work activities required to deliver a facility in finished condition ready. for occupancy. .
Previous projects should be identified and described, including:
- location
- size
client
development time line (from initiation of design to construction completion)
project cost and financing strategy
quality control measures
current status
references and contact information
project delivery methods (i.e., design/build, design/bid/build, etc.)
2. Financial Capacity
The Sponsor is very concerned about the financial strength and stability of the Team. All
respondents in this RFQ are required to provide, on a strictly confidential basis, the following
information for the prime design consultant and the construction manager
List of projects in the "pipeline" (include status, development schedule, and financial
commitment, if any)
Team members' litigation record
Team members' loss claims history
3. Project Approach
Respondents should present their intended approach to:
Design/quality/life cycle alternatives
Methodology in assimilating the program document
Alternative construction methods
Entitlement process
The Team should include a description of the project management system to be used. The
discussion should -detail the operating procedures, quality control procedures, and other
management methods to be employed to ensure the project is completed and available for full
function occupancy no .later than the date identified on the schedule.
8 of 9
REOUEST FOR QUALIFICATIONS COSTS
The Team will be responsible for all expenses incurred during the solicitation and negotiation process
with the City of Santa Ana. This Request for Qualifications does not and shall not commit the City of
Santa Ana or their agents to enter into any agreement, to pay any costs incurred in preparation of the
submittals, or to procure or contract for services or supplies,
THE SUBMITTAL DEADLINE
Qualifications must be delivered no later than 5:00 p.m., PST on Monday, May 1.3, 2002. Submittals
received after 5:00 p.m., PST on Monday, May 13, 2002 will not be .considered....In addition, for those
submittals that are not considered as finalists, only the financial information material will be returned.
Faxes will not be accepted.
All responses shall be marked "Request for Qualifications": City of Santa Ana Civic Center Parking
Structure Project, addressed to.
City of Santa Ana
Public Works Agency
Director of Public Works
20 Civic Center Plaza, Ross Annex
4`h Floor
Santa Ana; California 92701
The submittal must be sign by an individual authorized by the Team to bind the Team to all terms and
conditions of the submittal. Similarly, for the "shortlist" candidates, the sealed fees submittal must be
signed by an individual authorized by the Team to .bind the Team to all terms and . conditions of that
submittal. All submittals shall provide the name, title, address and telephone number of the individual or
individuals with authority to contractually bind the Team and the person who may be contacted by the
City of Santa Ana during the proposal evaluation process and contract award process.
Who to Contact
Questions regarding this Request for Qualifications should be addressed in writing, to:
Ms. Souri Amirani
Principal Engineer
Design Engineering
City of Santa Ana, Public Works Agency
20 Civic Center Plaza, Ross Annex
Yd Floor
Santa Ana, California 92701
Questions may be delivered by mail at via fax at (714) 647-5635. All questions must be received no
later than 4:00 p.m., PST an Friday, May 3, 2002: Verbal inquiries will be accepted at the
Pre -Submittal Conference.
Respondents to -this RFQ are strongly cautioned NOT to contact City of Santa Ana officials or members
of the panel regarding the selection process. Inappropriate efforts to lobby or influence individuals or
organizations involved in this selection process may result, at the panel's sole discretion, with dismissal
from further consideration.
9 of 9
ATTACHMENT "A"
CONCEPTUAL SITE PLAN
Tj
/lb�lN41r2eT/�.-�^.LC�L1LJ1LL[JILL! l _,
y� _
I t.
I MHIIIH W
- ;nnnrrrr n.,frs ROVS '+
r ANNEX
oR
0 0 0 0 0
EXISTING
CITY HALL ..
v6
co
o
ULT
x EXISTING
` �rJUVENILE,
ETE NTIOt
4 r w CENTER
— s ,
STING
LDING
ROPO�SED ST, �fE
APO �LS COI ; T
ECT LEA
R
PAOP ' SE
PEDESTFMN
Rl
.�� 1y��'��"' �f�9 " ,,,.-��� �' , • fry,:,,;, Q
r"
CONCEPTUAL SITE PLAN!
ATTACHMENT "B"
FEE PROPOSAL, FORMAT
0
FEE PROPOSAL FORMAT
The Consultant shall furnish a fee `schedule for the proposed service.
The fee schedule (3 copies) shall be separately bound, sealed, and submitted to the
City. The fee schedule shall include the following:
A. Not -to -Exceed Fee for professional services as described in the UP; The
fee proposal shall include a breakdown by task.
B. Hourly rate for each personnel category.
C. Any other.direct charges.
D. Indirect cost or overhead.
E. Cost of supplies and materials (itemized).
* The fee for the project may be negotiated following selection of the consultant.
ATTACHMENT "C"
CERTIFICATION OF NON-DISCRIMINATION BY
CONSULTANTS
CERTIFICA'HON OF NON-DISCRIMINATION BY CONSULTANTS
As suppliers of goods or services to the City of Santa Ana, the Firm listed below certifies that it does not
discriminate in its employment with regard to race, color, religion, sex, or national origin; that it is in
compliance with all federal, state and local directives and executive orders regarding non-discrimination
in employment; and that it agrees to demonstrate positively and aggressively the principle of equal
opportunity in employment.
WE AGREE SPECIFICALLY:
l . To take affirmative steps to hire minority employees with the company.
2. To establish or observe employment policies .within affirmative promotion opportunities ..for
minority persons at all job levels.
3. To communicate this policy to all persons concerned, including all company employees, outside
recruiting services, especially those servicing minority communities, and to the minority
communities at large.
TITLE OF PERSON SIGNING
SIGNATURE
DATE
Please include any additional information available regarding equal opportunity employment programs
now in effect within your company.
ATTACHMENT
SAMPLE CERTIFICATE OF INSURANCE AND
ADDITIONAL INSURED ENDORSEMENT
r
,4�C-0-RO. CERTIFICATE OF LIABILITY INSURANCE
D011311200(MMIDD1�
PRODUCER
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
INSURED
INSURER A:
INSURER B:
INSURER C:
INSURER D:
INSURER E:
r•r%%1=0 A r: G C
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
`POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR
TYPE OF INSURANCE
POLICY NUMBER
POLICY EFFECTIVE
DATE (MM/DDNYI
POLICY EXPIRATION
DATE (MMIDDM)
LIMITS
6ENERALLIABILITY
X COMMERCIAL GENERAL LIABILITY
CLAIMS MADE L ^ J OCCUR
X111111111
-
01/01/2001
01/01/2002
-
EACH OCCURRENCE
$ 1,000,000
FIRE DAMAGE (Anyone fire)
$ 5O,O(w
MED EXP (Any one person)
$ -5,000
PERSONAL & AOV INJURY
$ 1,000,000
GENERAL AGGREGATE
$ 2,000,000 '
OEN'LAGGREGATE LIMIT APPLIES PER:
POLICY M PRO- LOC
PRODUCTS-COMPIOPAGG
$ 2,000,000
AUTOMOBILE
X
LIABILITY
ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
HIRED AUTOS
NON -OWNED AUTOS
X222222222 01/01/2001 01101/2002
SEE ATTACHED ADDITIONAL
INSURED ENDORSEMENT
COVERAGES DEPEND ON TYPE
OF AGREEMENT/CONTRACT
COMBINED SINGLE LIMIT
(Ea accident)
$ 1,000,000
BODILY INJURY
(Per person)
$
BODILY INJURY
(Per accident)
$
PROPERTY DAMAGE
{Per accident)
$
GARAGELIABILITY
ANY AUTO
AUTOONLY- EAACCIDENT
$
OTHER THAN EA ACC
AUTO ONLY: AGO
$
$
EXCESS LIABILITY
OCCUR 0 CLAIMS MADE
DEDUCTIBLE
RETENTION $ -
EACH OCCURRENCE
$
AGGREGATE
$
$
$
$
WORKERS COMPENSATION AND
,I!APLOYERS' LIABILITY
#
XXX333333333
01/01/2001
-
0110112002
X WC STATU- OTH-
E.L.EACHACCIDENT
$ 1,000,000
E.L. DISEASE - EA EMPLOYEE
$ 1,000,000
E.L. DISEASE -POLICY LIMIT
-$ 1.000,000
OTHER
Professional Liability
PL444444
01/01/2001
01/01/2002
Each Occurrence 1,000,000
DESCRIPTION OF OPERATIONSILOCATIONSNEHICLES!EXCLUSIONS ADDED BY ENDORSEMENTISPECIAL PROVISIONS
Certificate- Holder is additional Insured per attached.
Project No. _
rFRTIGIrATF "pi nFR I I Anni-rmNAI INRIIRFn- INSIIRFR I F-rrFR' CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED EiEFORF; THE EXPIRATION
City Of Santa Ana
20 Civic Center Plaza - Ross Annex (M-
DATE THEREOF, THE ISSUING INSURER WILL - MAIL 30 DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TOTHE LEFT,
Santa Ana, CA 92701
AUTHORIZED -REPRESENTATIVE . '
ACORD 25-S (7197)
L
OAcaRQ GORFV ATiLIN 7Udd
ADDITIONAL INSURED ENDORSEMENT
FOR COMMERCIAL GENERAL LIABILITY POLICY
Insurance Company
This endorsement modifies such insurance as is afforded by the provisions of Policy
# relating to the following:
1. The City of Santa Ana, 20 Civic Center Plaza, Santa Ana, California
92701; its officers, employees, agents, volunteers and representatives are named as
additional insureds ("additional insureds") with regard to liability and defense of suits
arising from the operations and uses performed by or on behalf of the named insured.
2. With respect to claims arising out of the operations and uses performed by
or on behalf of the named insured, such insurance as is afforded by this policy is primary
and is not additional to or contributing with any other insurance carried by or for the
benefit of the additional insureds.
3. This insurance applies separately to each insured against whom claim is
made or suit is brought except with respect to the company's limits of liability. The
inclusion of any person or organization as an insured shall not affect any right which such
person or organization would have as a claimant if not so included.
4. With respect to the additional insureds, this insurance shall not be
cancelled, or materially reduced in coverage or limits except after thirty (30) days written
notice has been given to the City of Santa Ana, 20 Civic Center Plaza, Santa Ana,
California 92701.
(Completion of the following, including countersignature, is required to make this
endorsement effective.)
1i
Effective
Policy # _
Issued to
this endorsement form as a part of
Named Insured
Countersigned by
Authorized Representative
EXHIBIT 'B'
CITY OF SANTA ANA
SANTA ANA, CA
PARKING STRUCTURE
Fee Proposal
Submitted to:
City of Santa Ana
Public Works Agency
Attn: Souri Amirani, Project Manager
20 Civic. Center Plaza — Ross Annex, 4th Floor
.Santa Ana, CA 9270I
Submitted by:
Gordon & Williams General Contractors, Inc.
2 Faraday
Irvine, CA 926.18
July 9, 2002 (Rev. 2)
FEES and PAYMENTS
Our preliminary estimate of fees is Five Hundred Five Thousand Five Hundred Dollars ($505,500.00). The
design fee for the bridge assumes spanning to an existing higher level, eliminating the need for elevator and stairs
at the end. This scope can be determined later once the discovery of the issues are clearer. The fee breaks down
as follows:
Pre -Construction Phase
Pre --Design & Programming $ 5,000
Preliminary Estimate $ 6,500
Functional & Preliminary Design $ 38,800
Design Development $ 62,020
Construction Documentation $ 90,360
Bidding $ 14,120
Allowance for Demolition of Juvenile Detention Facility $ 125,000
Subtotal Pre -Construction Phase $ 341,800
Construction Phase
Construction Administration (Designer) $ 38,700
Construction Management Fee $ 125,000
Post -Construction Phase (Cost of the Work) $ 0
Subtotal Construction Phase $ 163,700
Total Pre -Construction and Construction $ 505,500
(including Allowance for demo of Juvenile Detention Facility)
Fees by Discipline:
Geotechnical
$
8,000
Civil (Pad design, no survey)
$
6,000
Landscape Architecture
$
13,000
Parking Consulting
$
28,000
Architectural Design
$
88,000
Structural Engineering
$
58,000
Mechanical Engineering
$
11,000
Electrical Engineering
$
13,000
Construction Management (Includes Pre -construction)
$
137,500
Architectural Renderings
$
8,000
Printing & Expenses
$
10,000
Allowance for demolition of Juvenile Detention Facility
$ 125,000
Total
$
505,500
Not included above is the cost of testing and inspection. This should be a part of your construction budget, and
will be billed at actual cost. The extent of testing required has not been determined. However we recommend an
allowance of 1% of the construction cost.
Hourly Rates: CPC — Parking Consultant/Architect
Principal - Parking Consulting $ 185.00
Principal — Architectural design $ 165.00
Project Management $ 135.00
Project Architect $ 115.00
Technician $ 75.00
Clerical/Field Enumerator $ 50.00
Page 2 of 2
Hourly Rates: Ficcadend & Waggoner - Structural Engineer
Principal
$
165.00
Senior Engineer
$
95.00
Engineer
$
80.00
Senior Draftsperson
$
85.00
Draftsperson
$
75.00
Clerical
$
50.00
Hourly Rates: OMB Engineers - Electrical Engineer
Principal
$
135.00
Project Engineer
$
110.00
Sr. Designer
$
95.00
Designer
$
75.00
CAD Drafting
$
65.00
Word processor
$
40.00
Hourly Rates: BP & Associates Inc. -Mechanical Engineer
Principal
$
120.00
Engineer
$
110.00
Sr. Designer
$
100.00
CAD Technician
$
85.00
Draftsperson
$
65.00
Clerical
$
50.00
Hourly Rates: Group Delta -- Geotechnical Engineer
Principal
Project Manager
Project Engineer
Field Investigation
Hourly Rates: Lynn Capouya - Landscape Architect
Principal
Project Manager
Irrigation Designer
Landscape Architect
Senior Staff
Intermediate Staff
Clerical
Hourly Rates: Gordon & Williams -Construction Manager
Principal
Project Manager
Project Superintendent
Project Engineer
Project Coordinator
Estimator
$ 165.00
$ 110.00
$ 90.00
$ 80.00
$ 115.00
$ 98.00
$ 92.00
$ 97.00
$ 81.00
$ ' 75.00
$ 45.00
$ 150.00
$ 80.00
$ 75.00
$ 55.00
$ 45.00
$ 80.00
Page 2 of 2
4.
EXHIBIT "C'
CITE' OF SANTA ANA
SANTA ANA, CA
PARKING STRUCTURE
QUALIFICATIONS
Submitted to:
City of Santa Ana
Public Works Agency
Attn: James G. Ross, Executive Director
20 Civic Center Plaza — Ross Annex, 4th Floor
Santa Ana, CA 92701
Submitted by:
Gordon & Williams General Contractors, Inc.
2 ,Faraday
Irvine, CA 92618
May 13, 2002
C O R D O N M w 1 L L I A M 5
GENERAL CONY kACTO R 5, 1 NC.
May 13, 2002
Mr. James G. Ross, Executive Director
City of Santa Ana
Public Works Agency
20 Civic Center Plaza — Ross Annex, 0 Floor
Santa Arta, CA 92701
RE: City of Santa Ana Parking Structure RFQ
Gentlemen:
We appreciate the opportunity to introduce our Design/Build Team for the City of Santa Ana
parking structure. The individual team members have worked together in various combinations
over the years, and have a wealth of parking structure experience both individually and
collectively. These pre-existing working relationships will guarantee the City a positive, well
coordinated experience with the Gordon & Williams Design/Build Team.' Gordon and Williams
will lead the team as the main point of contact, with Mark Williams as -the individual authorized
to contractually bind our team. His contact information is as follows. -
Mark Williams
Managing Principal
Gordon & Williams General Contractors, Inc.
2 Faraday
Irvine, CA 92618
Phone: 949-588-2855
Fax: 949-588-2877
Email: mwilliams@gwgc.com
We have included a Table of Contents directly following this cover letter to assist you in locating
items of particular interest within our proposal. We look forward to a successful review of our
Step 1 submittal, and to an interview and oral presentation, if required, to more fully discuss the
options and opportunities for this exciting project.
Sincerely,
Mark Williams
Managing Principal
Gordon & Williams General Contractors, Inc.
2 Faraday
lrvine, California 926f8
Tefephone 949,586.2855
Focsimile 949.588.2877
License No. 596323
TABLE OF CONTENTS
Section 1: Design / Build Overview
Section 2: Project Team
Section 3: Relevant Experience
Section 4: Affirmative Action Compliance
Section 5: Project Approach
DESIGNIBUILD OVERVIEW
The Gordon & Williams Design/Build Team consists of Gordon & Williams in the dual
roles of Design/Builder and Construction Manager and Choate Parking Consultants as
Parking Architect & Consultant and overall Design Team leader.
This team was carefully chosen for two main reasons. The first is the impressive list of
experience the team member firms have on significant parking structures, mostly here in
the Los Angeles basin, experience which will allow the City of Santa Ana to capitalize on
lessons learned. The second reason for inclusion on the team is the familiarity the firms
and personnel have with each other from past experience on multiple projects.
The following pages within this Section give an overview of each individual firm, the
main duties and responsibilities each will have on the City of Santa Ana Parking
Structure within the team structure, and three (3) references for each of the member
firms. Each of the firms is described on a separate page with all of the described
information. The final page of this Section is a preliminary Organization Chart of our
Design/Build Team, which gives a visual reference for understanding how our team
interacts and what the reporting relationships are as we now see them.
The proposal that follows has been constructed with attention to answering specific
points and issues that were made clear and relevant in your RFQ. It is important to the
Gordon & Williams Team to make it apparent to the City of Santa Ana that we meet and
exceed the criteria for selection. Please note the following specific and significant items:
• Our Team members have significant and relevant experience on both large and
small parking structures for public entities.
• Our Team, individually and collectively, has all the necessary resources to
undertake and execute this project immediately, and do so exceeding the City's
expectations for communication, process and performance.
• We have a demonstrated success record for delivering exceptional projects in
a timely and cost effective manner.
• Our Team has a clear organizational structure, as represented on our Org
Charts, and has worked effectively together in the past. We have shown the
ability and willingness to communicate effectively with our clients and those
with whom they deal and serve.
• We enjoy an industry wide reputation for the exceptional quality of our work
product and for the process through which we arrive at the result.
• Our proactive approach to project management, including cost and schedule
control, is undisputed.
• Our Team member firms are located close to one another, are currently working
together on other projects, and have ease in moving back and forth between
offices.
• We are proud of our reputation for delivering projects ahead of schedule, even
in circumstances where it seemed almost impossible. Our clients will attest to it.
• There is no Team that can demonstrate more design creativity in finding cost
effective solutions, nor a construction group more willing to relentlessly explore
options for implementing value added options. When you discuss with us
issues such as square footage per stall, cost per stall, etc. it will be very apparent
how creative, flexible, practical, and efficient our Design/Build Team is.
GORDON & WILLIAMS
Gordon & Williams will have two roles on the City of Santa Ana Parking Structure. We will be
the Master Design/Builder, with overall responsibility for the project. We will hold the contract
with the owner, and all design personnel, consultants, subcontractors, etc. will report up the
chain of command to Gordon & Williams. Gordon & Williams will be responsible for delivery
of the project and will assure that all of the project requirements and conditions are met. Second,
Gordon & Williams will act as Construction Manager for the project. All of the construction
staff, whether stationed at the field office or offsite, as well as all of the trade subcontractors will
report to Gordon & Williams construction Project Manager and Field Superintendent, who will,
in turn report to Mark Williams as Design/Builder Managing Principal.
We have carefully reviewed the RFQ and understand all of the requirements of the "Proposer"
(Design/Builder) and of the Construction Manager, and we are ready to undertake and
successfully execute all of those responsibilities and functions. We possess all of the requisite
experience and resources to accomplish this task.
Gordon & Williams References:
1. MS Pasadena LLC / David Simon (310) 203-1849
2, FOX Inc. / Bill Murphy (310) 369-2058
3. Legacy Partners / Michael Morris (949) 930-6650 x7841
CHOATE PARKING CONSULTANTS
CPC main task is to direct the design team to a successful project conclusion. The efforts will
include acting as the liaison with F&W, BP Associates and OMB on issues related to public agencies
planning, related code approvals and permitting for construction documentation. CPC responsibility
will be to monitor the overall project progress and relay information on a timely basis with Gordon
& Williams.
As the parking consultant and the designer of record for the parking facility, CPC will direct
different design disciplines to meet user circulation and access goals while maintaining efficient and
cost effective construction design for the project. CPC will be drawing on the consultant member's
years of experience and training in this building type and manage that effort. Program assimilation,
review, validation, Schematic Design, Design Development, Construction Documentation and
Construction Administration are included in the design effort.
CPC References:
1. University of California, Irvine J Bob Fritsch (949) 824-6641
2. Experian / Russell Tiernan (714) 830-7403
3. Hilton Hotels, Paris Casino I Michael Hilton (310) 278-4321 or (702) 967-4168
PROJECT TEAM
Gordon & Williams
DesignI tailder
Choate Parking C
Design
F&W I I I B P Assoc. I I I OMB
Stracidral Mechanical 4+leewcal
Group Y P Y
Delta Lynn Ca ou a TBD
soils Engdneer Landscape Civil
MANAGEMENT STAFF
_ Gordon & Williams
Conshvietian Manager
PrecoustructionPS.,O
Director
Haki,n Khalil
GORDON & WILLIAMS: Mark Williams
Managing .Principal for the Design/Build Team. All personnel, consultants, subcontractors, etc.
ultimately report to Mark as the Managing Principal and individual in charge of the overall
project. Mark will sign the owner contract and will be very involved with the project from pre-
planning through close-out of construction. He will monitor all preconstruction design,
estimating and scheduling efforts, and will work closely with the construction phase staff after
the project is released for field construction activity. Mark will serve as the top level of quality
assurance/control for this project and has ultimate authority in representing the Design/Build
team. Mark has worked successfully on past projects with Choate Parking Consultants. His
familiarity with this type of construction will make him a valuable resource for value added
execution of the City of Santa Ana Parking Structure.
CHOATE PARKING CONSULTANTS: Rick Choate
Responsible for development of conceptual design and providing direction for the project from
planning through to project close-out. Mr. Choate's working experience with the other team
members will control the project direction, emphasize the big picture and not allow the process
to bog down in detours or reinvention of known and historically proven means to a successful
parking facility design. Mr. Choate will be directly involved in the planning of team coordination
issues. Rick will be acting design team liaison with Gordon & Williams and administer the
quality control process for design documents throughout the project.
MARK N. WILLIAMS
EXPERIENCE:
1989 to Present GORDON & WILLIAMS „(GWGC, INC.)
Principal in charge of project development from project identification through
completion of pre -construction. Personally involved
with all phases of projects
on which he is the designated project executive.
Primarily involved with
negotiated contracts where budgetary constraints
required extensive value
engineering analysis to make construction feasible.
Gordon & Williams prqiects include:
Farmers Market Expansion
$ 27,000,000
Los Angeles, CA
Hyatt Plaza Alicante Hotel
$ 30,000,000
Garden Grove, CA
Matsushita Avionics
$ 10,000,000
Lake Forest, CA
Pasadena Corporate Parr
$ 20,100,000
Pasadena, CA
Knott's Berry Farm Amusement Park Upgrades
$ 50,000,000
Buena Park, CA
KTTV Channel 11
$ 28,000,000
Los Angeles, CA
Fox Network Center Parking Structure
$ 28,000,000
Los Angeles, CA
Fox Television Network Center
$ 57,000,000
Los Angeles, CA
Fox Animation Studios
$ 3,100,000
Phoenix, Arizona
Fox Studios Baja
$ 18,000,000
(The Titanic)
Rosarito Shores, Mexico
Mattel Toys Sound Stage & Support Facility
$ 1,000,000
El Segundo, CA
Proiects with previous employment:
Citicorp Plaza
$120,000,000
Los Angeles, CA
Main Place Mail
$
24,000,000
Santa Ana, CA
Resort at Lantern Bay
$
23,000,000
Dana Point, CA
Beverly Hilton Hotel Remodel
$
15,000,000
Beverly Hills, CA
Aerojet Corporate Headquarters
$
11,000,000
Azusa, CA
EDUCATION: California Polytechnic University - Pomona, CA
Bachelor of Science Civil Engineering
Page 1 of 1
J. RICHARD CHOATE
Principal/Project Manager
Parking Consultant
Mr, Choate is the principal of Choate Parking Consultants and has been exclusively
involved in the planning and design of parking projects for the last nineteen years of his
professional career. He is a registered architect whose parking design experience
includes site selection and analysis, demand studies, functional analysis, performance
document preparation, facility design, project management, parking systems integration
consulting, cost budgeting and operations review.
Experience: Mr. Choate has worked extensively with governmental agencies, educational institutions,
retail and commercial developers in the development of parking solutions for clients. He
has been instrumental in the design of over 500 multi -level parking facilities throughout
California and the nation as an architect and functional designer. He is recognized as one
of the parking industry`s innovative designers creating user-friendly solutions while
maintaining buildable and cost-effective facilities.
Mr. Choate's unique qualifications include. extensive Design/Build experience and being
employed as Vice President of both International Parking Design and Walker Parking
Consultants during nineteen years of his professional development. The design/build
efforts with contractors has allowed him to formulate a more complete design
understanding of this particular building and construction type and the delivery process to
the client
Education: Bachelor of Architecture, University of Cincinnati
Professional Registered Architect, California/Minnesota
Affiliations: National Parking Association - Chairman, Parking Consultants Council
Urban Land Institute — Full Member International Parking Institute -Member
Design 2001— IMPC Award for Excellence, Best Facility Design over 800 Spaces
Awards: 1994 - IMPC Award for Excellence, Best Facility Design over 800 Spaces
1985 - IMPC Merit Award (runner up), Best Facility Design over 500 Spaces
1984 - IMPC Merit Award (runner up), City of Rochester, Best Facility Design under 500
Spaces
1983 - IMPC Award for Excellence, City of Minneapolis, Best Facility Design over 500
Spaces
Presentations/Articles:
"California's Architect to the Cars", Parking Magazine, January/February, 2000
"Urban Parking Geometric/What is appropriate?" League of CA Cities, Long Beach, `98
"Current & Future Parking Management Technologies: US & Abroad", AQMD
Symposium, `95
"Parking -Durability Design", Associated General Contractors Convention; San Diego, `95
"The LA Earthquake: What did we learn", NPA Convention, Orlando, 1994
"The LA Earthquake: The Truth Behind the Damage", Parking Magazine, April 1994
"Writing a Request for Proposal", IMPC Parking Operations Seminar, Los Angeles, 1992
"The Cost of Parking", IMPC Annual Convention, Orlando, 1991
"The Cost of Parking", IMPC Parking Design Seminar, San Diego, 1990
"A Peripheral Parking Tale", BOMA Office Market Journal, 1987
"For More Parking look to the Sky", American City and County Magazine, 1980
J RICHARD CHOATE
Principal
Parking Projects as Parking Consulting/Project Manager/Architect
Garfield Entertainment Center, Alhambra, CA, 5 levels, 804 spaces, completed 2002
First Street Parking Facility, Alhambra, CA, 5 levels, 250 spaces, completed 2001
*Maryland Avenue Parking Facility, Glendale, CA, 9 levels,1124 spaces, 3 levels below grade w/ retail at grade
Sierra Madre, Pasadena, CA 5 levels, 961 spaces, in construction
Johnson & Johnson Pharmaceutical Research, San Diego, CA, 3 levels, 518 spaces, in construction
Pasadena Corporate Center, Pasadena, CA, 4 levels, 453 spaces, completed 2002
Experian Parking Facility, Costa Mesa, CA, 6 levels,138o spaces, completed 2002
University of California, Irvine CA, 7 levels, l800 spaces, completed 2001
Howard Hughes, Los Angeles, CA, 8 levels,1043 spaces, completed 2001
1905 Main Street, Irvine, 5 levels, J99 spaces, completed 2oo1
Grand Avenue, El Segundo, CA, 2 levels, 325 spaces, completed 2oo1
DPSS El Monte, County of Los Angeles, CA, 6 levels, 834 space parking facility, completed 2000
Baxter Hyland Healthcare Corporation, Los Angeles, CA, 5 levels, 599 spaces, completed 2000
2300 Michelson, Irvine, CA, 4 levels, 296 spaces, pending developer continuance
LA Unified School District, Las Angeles, CA, 4 parking facilities, in design, awaiting DSA approval
*Southern California College of Optometry, Fullerton, CA, 4 levels, ago spaces, 1 partial level below grade,
completed 1998
*University of California, Santa Barbara, CA 4 levels, goo spaces, completed 1998
*County of Orange, Santa Ana Juvenile Justice Center PF's, 2 garages, 5 levels, goo spaces each
*Paris Casino Parking Facility, Las Vegas, NV,11 levels, 3900 spaces w 2 levels of convention space,
completed 1998
*California State University, Los Angeles, CA, 3 levels, 1200 spaces,l partial level below grade, completed
1996
*University of Nevada - Reno, 5 levels,lloo spaces
Parking Projects as Parking Consultant
*Huntington Memorial Hospital PF, 420 spaces, 6 levels, one level underground
r *City of Santa Ana, 5tn & Main PF, 6 levels, 380 spaces
Dana Point Harbor, 5 levels,1677 spaces, pending developer continuance
Saint Kilian's Church, Mission Viejo, CA, i level, 315 spaces
Pico Plaza, Los Angeles, CA, 3 levels, 1400 spaces, not built
Pechanga, Indian Reservation Casino/Entertainment Facility, 3 levels, 1300 spaces, completed 2002
Caltrans District 7 Parking Facility, Los Angeles, CA,1143 spaces, 4 level underground building
University of California, Irvine, two parking facilities, 1050 & 1277 spaces, 5 levels & 4 levels, completed 1992
& 1993
Ambassador City College, Pasadena, CA, 5 levels, 988 spaces
Koll Center Orange, Orange, goo spaces, 4 levels, completed 1987
Sybil Brand Institute, 600 spaces, not built
*City of Phoenix, Civic Plaza East Garage, 7 levels, 2800 spaces w/ event circulation capacity
*City of Phoenix, Jefferson St. PF, 6 levels, 1500 spaces w/ event circulation capacity
*John Wayne Airport, Orange County, CA, 81oo spaces, 3PF's, 4 levels, 1 level underground (too' short of a
1/2 mi long)
*Metro Pointe Center 3 PF's, Costa Mesa, 4, 3, & 2 levels, 2200 spaces total (office and retail pkg)
*'San Diego State University, San Diego, 15oo spaces, 2 parking levels w/ athletic track & field above,
completed x998
*Janss Marketplace PF, Thousand Oaks, 4 levels,1500 spaces
*Hone Savings of American Two Parking Facilities, 1-4 levels, 1200 spaces, 2-4 levels, goo spaces, not built
*County of Orange Twin Towers PF, Santa Ana, 7 levels,1057 spaces, w/ secure sheriff pkg below, completed
1992
*Gardens of El Paseo, Palm Desert, 2 levels, l000 spaces
*County of Riverside, Riverside, 12th St. PF, 7 levels, l000 spaces w/police parking at roof level
*Phoenix Gateway Center Multi -Office Complex & Parking, Scottsdale, AZ, 6 levels, 828 spaces, completed
1987
'Rick Choate was the principal in charge of these projects while with other parking consulting companies. Many of the
staff members at CPC were also involved in the design of these projects.
PROJECT TEAM
CLoate Parking C
Design
F&W I I I D P Assoc.
Stracturai Mechanical
Group Delta I I Lynn Capouya
Soils Engineer Landscape
SUPPORT STAFF
GORDON & WILLIAMS:
Gordon & Williams
Desigu/Builder
Gordon & Williams
Construction Manager
OM6
Procons#ruction
Project
Electrical
Director
---
Manager
Aakln xhaiU
Joh"SW
TBD
Superint
C011
C11re Waring
Senior Vice President of Preconstruction: Hakim Khalil
Manages the preconstruction & estimating operations from initial conceptual budgets through
final bidding, overseeing estimating & preconstruction activity performed by estimating staff as
well as project managers and superintendents. Analyzes site logistics, project constraints, means
and methods, project schedules and material alternatives. Directly involved in negotiated
contracts where budgetary constraints require extensive value engineering analysis to make
construction feasible. Also responsible for managing competitive bidding, working with lead
project estimators and estimating teams from subcontractor bid invitations through bid closing.
Senior Project Manager: John Staff
Responsibilities include review of architectural and engineering drawings, specifications and
project document control; review and expedite shop drawings and submittals; initiate and
coordinate request for information; coordinate with estimating for review of scopes of work
precedent to and including preparation of contracts and change orders; maintain project progress
and schedule by coordinating closely with site project manager, project superintendent, general
field superintendent, entire assigned site staff and Design/Build support team; monitor and
manage subcontractors in close coordination to assure quality standards are met or exceeded.
Project Superintendent: Clive Waring
The project lead superintendent is assigned the overall field responsibility for assuring quality
installation of the craft work. He, and any assistants reporting to him, also attend to issues such
as staging and storage, deliveries, movement of labor personnel and vehicles onsite and offsite,
parking and traffic control, etc. Responsible for daily and weekly planning of activities,
including coordination and scheduling with subcontractors under contract to Gordon & Williams
and any contractors reporting to the owner. Attends to any issues that may affect successful
ongoing business in the case of an owner occupied facility, and coordinates closely with the
owner to minimize disruptions. Oversees the onsite safety program, including required site
safety meetings in coordination with Gordon & Williams safety manager and assures adherence
to it by all personnel working on the project. Participates in all planning sessions for the project
and all meetings with the OAC team, as well as meeting with subcontractors as necessary to
maintain the project delivery schedule.
HAKIM KHALIL
EXPERIENCE:
1995 to Present GORDON &_WILLIAMS (GWGC, INC.)
Senior Vice President of Preconstruction — Manages the preconstruction &
estimating operations from initial conceptual budgets through final bidding,
overseeing estimating & preconstruction activity performed by estimating staff
as well as project managers and superintendents. Analyzes site logistics, project
constraints, means and methods, project schedules and material alternatives.
Directly involved in negotiated contracts where budgetary constraints require
extensive value engineering analysis to make construction feasible. Also
responsible for managing competitive bidding, working with lead project
estimators and estimating teams from subcontractor bid invitations through bid
closing,
Gordon & Williams nroiects include:
Universal Headquarters Building
$150,000,000
Preconstruction
Universal City, CA
Mission Bay Block 26A
$ 40,000,000
San Francisco, CA
Mission Bay Block 28
$ 37,500,000
San Francisco, CA
Mission Bay Block 26E
$ 20,000,000
Preconstruction
San Francisco, CA
Mission Bay Bloch 26W
$ 40,000,000
Preconstruction
San Francisco, CA
MTV Networks
$ 5,500,000
Santa Monica, CA
Prada- Beverly Hills
Withheld at
Preconstruction
clients request
Beverly Hills, CA
Mission Ridge Office Complex
$ 21,200,000
Mission Viejo, CA
Dodger Stadium Renovation
$ 38,000,000
Los Angeles, CA
Universal Music Group
$ 15,000,000
Santa Monica, CA
KTTV Channel 11
$ 28,000,000
Los Angeles, CA
KRIV Channel 26
$ 13,000,000
Houston, Texas
Page 1 of 2
EXPERIENCE:
HAKIM KHALIL
Knott's Berry Farm
Buena Park, CA
Independence Hall Renovation
$
1,000 000
Windjammer Rollercoaster
$
7,600,000
Supreme Scream
$
1,400 000
Ghost Rider Rollercoaster
$
14,000,000
Fox Scoring Stage.
$
3,500,000
Los Angeles, CA
Fox Video Transfer
$
1,200,000
Los Angeles, CA
Fox Earth Station Facility
$
2,400,000
Los Angeles, CA
Fox ADR/Foley Stages
$
2,500,000
Los Angeles, CA
Fox Network Center Parking Structure
$
28,000,000
Los Angeles, CA
Fox Television Network Center
$
57,000,000
Los Angeles, CA
Fox NewsCorp Executive Building
$
48,000,000
Los Angeles, CA
Fox NewsCorp Executive Building
$
10,600,000
Tenant Improvements
Los Angeles, CA
EDUCATION: University Of Southern California
Bachelor of Science - Civil Engineering
California State University, Los Angeles
Advanced Courses in Structural Engineering
Golden Gate University
Certificate in Structured COBAL Programming
Page 2 of 2
JOHN D. STAFF
EXPERIENCE:
1998 to Present GORDON & WIL_LIAMS (GWGC, INC.)
Senior Project Manager -- Responsibilities typically include managing larger
and/or complex projects, and also quite often has Project Managers (each with
assigned projects or project component responsibilities) in a subordinate
reporting relationship. Review of architectural and engineering drawings,
specifications and project document control; review and expedite shop drawings
and submittals; initiate and coordinate request for information; coordinate with
estimating for review of scopes of work precedent to and 'including preparation
of contracts and change orders; maintain project progress and schedule by
coordinating closely with site project manager, project superintendent, general
field superintendent, entire assigned site staff and Gordon & Williams office
support team; monitor and manage subcontractors in close coordination with site
project manager to assure quality standards are met or exceeded.
Gordon & Williams projects include:
Amgen Parking Structure 10
$ 9,000,000
Thousand Oaks, CA
Pasadena Corporate Park
$
6,000,000
Phase 2
Pasadena, CA
Pasadena Corporate Park
$
3,800,000
Parking Structure
Pasadena, CA
Santa Monica Business Park
$
600,000
Restrooms Remodel
Santa Monica, CA
Santa Monica Business Park
$
3,000,000
Santa Monica; CA
Matsushita Avionics
$
10,000,000
Lake Forest, CA
East L.A. Recycling and Transfer Station
$
2,000,000
East Los Angeles, CA
Proiects with previous emnlovment:
The Sports Club/Irvine
$ 30,000,000
Irvine, CA
Santa Margarita Catholic School
$ 13,000,000
Rancho Santa Margarita, CA
The Sports Club/LA Earthquake Repair
$ 18,000,000
Los Angeles, CA
Koll Center Irvine North
$ 10,000,000
Irvine, CA
Koll Anaheim Center Parking Structure
$ 11,200,000
Anaheim, CA
McCormick & Schmick's Restaurant
$ 2,500,000
Irvine, CA
Page 1 of 2
EXPERIENCE:
JOHN D. STAFF
Allergan R & D Facility
Irvine, CA
Pacifica Building
Irvine, CA
Denny's Corporation Computer Center
Buena Park, CA
Spectrum Club/Howard Hughes Center
Remodel
El Segundo, CA
Missouri Building Tenant Improvements
Earthquake Repairs
Los Angeles, CA
EDUCATION: University of Southern California
Bachelor of Science - Civil Engineering
$ 3,300,000
$ 3,000,000
$ 2,800,000
$ 140,000
$ 850,000
Page 2 of 2
CLIVE WARING
EXPERIENCE:
1999 to Present GORDON & WILLIAMS GWGC INC.
Project Superintendent — The project lead superintendent is assigned the overall
field responsibility for assuring quality installation of the craft work. He, and
any assistants reporting to him, also attend to issues such as staging and storage,
deliveries, movement of labor personnel and vehicles onsite and offsite, parking
and traffic control, etc. Responsible for daily and weekly planning of activities,
including coordination and scheduling with subcontractors under contract to
Gordon & Williams and any contractors reporting to the owner. Attends to any
issues that may affect successful ongoing business in the case of an owner
occupied facility, and coordinates closely with the owner to minimize
disruptions. Oversees the onsite safety program, including required site safety
meetings in coordination with Gordon & Williams safety manager and assures
adherence to it by all personnel working on the project. Participates in all
planning sessions for the project and all meetings with the OAC team, as well as
meeting with subcontractors as necessary to maintain the project delivery
schedule.
Gordon & Williams proiects include:
Amgen Parking Structure 10
$ 9,000,000
Thousand Oaks, CA
Pasadena Corporate Park
$ 6,000,000
Phase 2
Pasadena, CA
Pasadena Corporate Park
$ 3,800,000
Parking Structure
Pasadena, CA
Dodger Stadium Seismic Renovation Phase 1
$ 2,700,000
Los Angeles, CA
Village at Centennial Square for
Withheld at
San Francisco State University
clients request
San Francisco, CA
Dodger Stadium Renovation
$ 38,000,000
Los Angeles, CA
Proiects with previous emplovment:
Centerpointe $ 20,000,000
Chino, CA
Varon $ 2,000,000
AIiso Viejo, CA
EDUCATION: Santa Monica College -- Santa Monica, CA
Construction Technology, Construction Contracting, Construction Management,
Surveying, Architecture, Business Administration
U.S. Army & Reserves
Page 1 of 1
PROJECT TEAM
Choate Parking Consultants
Desfgn
F&W I I I B i? Assoc.
Structuml Merhanfcaf
Group Delta Lynn Capouya
Soks Engineer I I Landscape
SUPPORT STAFF
oM8
Electrical
Gordon & Williams
Desfga/Eailder
TBD
civil
CHOATE PARKING CONSULTANT'S; INC.:
Gordon & Williams
conshwilon Manager
Preconstruction Project
Director -- Manager
Hakim Khalif John Staff
Waring
Project Manager/Architect: Barry Richmond, R.A.
Responsible for the design team management, the incorporation and coordination of the team for
the Schematic Design, Design Development and Construction Documents. Barry will coordinate
the preparation and development of the Project Construction Specifications.
Assistant Project Manager: Arturo Levenant Jr., R.A.
Art assists the Project Manager in his responsibilities pertaining to the coordination of parking
facility construction documentation and construction administration tasks.
Project Designer: Fernando Sanchez
Responsible for parking facility functional design, schematic design, design development and
preparation of each design phase presentation.
Director of Operations: Emerson Flint
Directly responsible for production of documents for the parking facility throughout the project.
Responsible for the production of Concept Drawings, Design Development Drawings and
Construction Drawings and shop drawing review during the construction phase.
BARRY M. RICHMOND
Project Manager/Architect
As Project Manager/Architect to Choate Parking Consultants, Mr. Richmond is
responsible for all aspects of construction document, specification preparation and
construction administration/management for parking projects.
Experience: Project Manager/Architect, Walker Parking Consultants, Newport Beach, CA, 1995-99
Freelance Architect/Construction Management. 1994-1995.
Associate/Project Architect, International Parking Design, Costa Mesa, CA, 1991-94
Senior Project Manager, PIA+ Architects, Newport Beach, CA, 1988-90.
Sr. Project Manager, John Hanson Architects, Vancouver, British Columbia, 1986-87.
Project Manager, Mohawk Oil Co., Architectural Department, Burnaby, British
Columbia, Canada. 1983-86.
Architects Asst., Rodney Stone Architect, Vancouver, British Columbia, Canada.
1979-83.
Education: Diploma in Building Technology from the British Columbia Institute of Technology,
Burnaby, British Columbia, Canada
The University of British Columbia, Vancouver, Canada
Graduate Certificate in Graphics and Sculpture from the Vancouver School of Art,
Vancouver, British Columbia, Canada
Registrations: Licensed Architect in the State of California, #C22912
Selected Projects:
Sierra Madre Villa, Pasadena, CA, 5 levels, 561 spaces, in construction
University of California, Irvine, CA, 7 levels, 1800 spaces, completed 2001
Pasadena Corporate Center, Pasadena, CA, 7 levels 1060 spaces, completed 2002
LA Unified School District, LA, CA, 5 parking facilities, awaiting DSA approval
Pechanga, Indian Reservation Casino/Entertainment P.F., CA, 3 levels, 1300 spaces
*Paris Casino Resort P. F., Las Vegas, NV, I levels, 3900 spaces, completed 1998
*Hilton Hotel "Star Trek" P, F., Las Vegas, NV, 6 levels, 1200 spaces, completed 1998
*UC Gilman Garage, San Diego CA, 2 levels, 1500 spaces, completed 1998
*Cal State Los Angeles Parking Facility II, 3, levels 1200 spaces, completed 1996
*Janss Marketplace Parking Facility, Thousand Oaks, CA, 4 levels. 1500 spaces
*One Main Place Shopping Center, NW Parking Structure, Santa Ana, CA
*Amgen Underground Parking Facility #3, Thousand Oaks, CA
*Kaiser Foundation Hospitals, Glendale Parking Structure, Glendale, CA
*Kaiser Foundation Hospitals, Lakeview Parking Structure, Anaheim, CA
*Kaiser West Anaheim MOB Parking Structure, Anaheim, CA
*Kaiser Foundation Hospitals, La Mesa Parking Structure, La Mesa, CA
*Defense-CEETA Parking Facility, Fort Belvoir, CA
*Barry Richmond was the Architect of these projects white with other parking consulting
companies.
ARTURO LAVENANT Jr.
Assistant Project Manager
As Assistant Project Manager with Choate Parking Consultants, Mr.
Lavenant assists the Project Manager'in responsibilities pertaining to the
development of parking facility construction documentation and
construction administration tasks. Mr. Lavenant's extensive experience
and background as an Architect provides our clients with hands on
experience from the design phase through construction administration
with the capability to meet an owner's needs.
Experience: Scheer Tanaka Dennehy Riley Architects, Irvine, California. Responsible
for production/working drawings of ground up freestanding, tenant
improvements & remodels restaurants through out the United States.
Coordinate with Structural, Mechanical, Electrical, Plumbing, and Food
Service Consultants. Floor plans, exterior/interior elevations, reflected
ceiling plans, roof plans and details. Codes and Planning Ordinances
research. 1998-2001.
Ralph Allen & Partners, Santa Ana, California. Involved in the production
of concept, design development, and construction drawings for school
modernizations for Pasadena Unified School District and Anaheim Union
High School District. 1995-1998. Coordination with Structural,
Mechanical, Plumbing, & Electrical Consultants, process drawing through
DSA approval
Education: California State Polytechnic University, Pomona, California, 1985-1990
College of Environmental Design. Bachelor of Architecture.
Orange Coast College, Costa Mesa,1982-1985
Associates of Arts, Certificate of Architecture
Selected Projects: Sierra Madre Villa, Pasadena, CA, 5 levels, 59x spaces, in construction
2300 Michelson, Irvine, CA, pending developer
LA Unified School District, Los Angeles, CA, 5 parking facilities, awaiting
DSA approval
Johnson & Johnson Pharmaceutical Research, San Diego, 3 levels, 5
levels, in construction
Santa Margarita Nissan, Santa Margarita, CA
'Pasadena High School Modernization, Pasadena, CA
*Muir High School Modernization, Pasadena, CA
*Savanna High School Modernization, Anaheim, CA
*Sycamore Junior High School Modernization, Anaheim, CA
*El Torito Restaurant, Palmdale, CA
*E1 Torito Restaurant, Rohnert Park, CA
*E1 Torito Express, orange, CA
*E1 Torito Express, Palm Springs, CA
*El Torito Grill, Woodland Hills, CA
*El Torito Grill, Irvine, CA
*Chi-Chi's Mexican Restaurants, East Coast/Mid West
*Art Lavenant was the Architect of these projects 'while with other parking consulting companies.
FERNANDO I SANCHEZ
Project Designer
Mr. Sanchez's outstanding organizational skills have been an asset to
Choate Parking Consultants since his initial involvement with the firm.
He is currently responsible for the project managing facet of the parking
facility/playground expansion projects with the Los Angeles Unified
School District. This task has exposed his exceptional coordination,
managing, communication, scheduling, and writing skills.
Experience: Pacific Coast Architects — Draftsman — in charge of contract document,
production of custom designed residential projects.
Courtney Architects — Draftsman — in charge of various drawings for
conceptual, design development & contract documents.
Mr. Sanchez has used his awareness for detail and completeness in the
various phases of the design and construction process.
Education: California Polytechnic State University, San Luis Obispo 1996-2001
Bachelor of Architecture
Orange Coast College, 1993-1996
Associate of Arts
Selected Projects:
Howard Hughes, Los Angeles, CA, 8 levels, 1043 spaces, completed 2000
DPSS El Monte, El Monte, CA, 6 levels, 834 spaces, completed 2000
Baxter Hyland, Los Angeles, CA, 5 levels, 599 spaces, completed 2000
LA Unified School District, LA, CA, 5 parking facilities, awaiting DSA
approval
EMERSON A. FLINT
Director of Operations
Experience:
Education:
As Director of Operations with Choate Parking Consultants, Mr. Flint is responsible for
development of parking facility projects as well as directing the technical staff in the
delineation efforts. Mr. Flint's extensive experience as a project architect of multilevel
parking facilities and manager of the design process provides CPC with the design leadership
to meet an owner's needs
Involved in the production of concept, design development and construction drawings for
parking facilities throughout Southern California for the last decade. Developed extensive
knowledge of the specific project type including code analysis, plan review and permit
issuance procedures and construction issues. Previous employment experience includes five
years at International Parking Design and four years at Walker Parking Consultants. 1990-
1999.
Furies & Luege Architecture, Hawthorne, California. Involved with the production of
working drawings and assured the compliance of building codes for different cities and
agencies. Responsible for the design and documentation of architectural details for
residential and commercial projects. Met with clients for the initial measuring and sketches
of existing structures. 1989-1990.
Frank Politeo & Associates, Long Beach, California. Diversified experience covering all
phases in the construction process of precast concrete structures and Type V buildings.
1984-1989
Autonomus University of Guadalajara 1977-1981 Guadalajara, Jalisco, Mexico
Bachelor of Science in Architecture Degree
Selected Projects:
Garfield Entertainment Center, Alhambra, CA, 5 levels, 804 spaces, completed 2002
First Street Parking Facility, Alhambra, CA, 5 levels, 250 spaces, completed 2001
DPSS El Monte, El Monte, CA, 6 levels, 834 spaces, completed 2000
Experian, Costa Mesa, CA, 6 levels, 1380 spaces, completed 2002
Howard Hughes, Los Angeles, CA, 8 Ievels, 1043 spaces, completed 2000
Pasadena Corporate Center, Pasadena, CA, 4 levels, 453 spaces, completed 2002
Pechanga, Indian Reservation P.F., Pechanga, CA, 3 levels, 1300 spaces
Ambassador City College, Pasadena, CA, 5 levels, 988 spaces
Sierra Madre Villa, Pasadena, CA, 5 levels, 961 spaces, in construction
1905 Main Street, Irvine, CA, 5 levels, 599 spaces, completed 2001
Baxter Hyland, Los Angeles, CA, 5 levels, 599 spaces, completed 2000
Johnson & Johnson Pharmaceutical Research, San Diego, CA, 3 levels, 518 spaces
Saint Kilian's Church, Mission Viejo, CA, 1 level, 31.5 spaces, study
LA Unified School District, LA, CA, 5 parking facilities, awaiting DSA approval
*University of California, Santa Barbara, CA, 4 levels, 900 spaces, completed 1998
*University of California, Irvine, CA, 2 P.F., 1050 & 1277 spaces completed 1992/93
*Rita Avenue Parking Facility, Huntington Park, CA
*Civic Center Plaza Parking Facility, Sacramento, CA
Statement of Qualifications
At Ficcadenti & Waggoner we have been providing structural consulting on several concrete
parking structures throughout Orange, and Los Angeles County. We have recently completed an
1800 car facility for the University of California at Irvine, a 1200 car facility for the Pechanga
Indian Casino in Temecula, a 1400 car facility for the Experian office center, and a 1000 car
facility for the Blueline in Pasadena, California.
Seb Ficcadenti and Michael Waggoner have been either engineer -of -record or project manager
on several other Orange County Parking Structures. That list includes: John Wayne Airport
Northwest and Southwest Structures, Mission Community Hospital Parking Structure, Juvenile
Justice Parking Structures 1 & 2, Newport Lido Parking Structure, Four Seasons Parking
Structure, Douglas Plaza Parking Structure, and Koll Center Irvine Parking Structure.
We have experience with design -build parking structures and owner developed structures, and
will provide designs which are economical and high Quality. We achieve this by selecting cost
efficient systems which are preferred by the contractors with expertise in parking structure
construction.
Our office consists of 53 individuals with expertise in the technical aspects which create
successful concrete facilities. We have six senior staff members who manage projects from their
inception through operation. The high ratio of senior staff to technical staff ensures that your
project has the full commitment of the entire firm. Most of the engineers in our firm have
advanced degrees from universities such as U.C. Berkeley, and Stanford. Our expertise in
concrete design will be a tremendous asset to your project.
Our corporate office is located in Irvine, California. We have branch offices in Walnut Creek,
California, and Las Vegas, Nevada.
MICHAEL A. WAGGONER, S.E.
Principal
Mr. Waggoner is a Principal in the firm of Ficcadenti & Waggoner, Inc. He
has experience in a wide range of projects. He has been Engineer of Record
on over 500 million dollars of construction throughout California, Nevada and
Florida. He is a registered Structural Engineer.
Professional Licenses:
Civil Engineer, State of California, Lie. No. 45000
Structural Engineer, State of California, Lie. No. 3738
Civil and Structural Engineer, State of Nevada, Lie. No. 10545
Structural Engineer, State of Illinois, Lie. No. 081-005137
Structural Engineer, State of Florida, PE-0050320
Structural Engineer, State of Minnesota, Lie. No. 25711
Structural Engineer, State of Missouri, Lie. No. 029185
Structural Engineer, State of New York, Lie. No. 075052-1
Structural Engineer, State of Louisiana, Lie. No. 28323
Education: California State Polytechnic University, Pomona, BS Civil Engineering,
Summa Cum Laude, 1982-1986
University of California, Berkeley, MS Structural Engineering, 1986-1987
Experience: Principal - 1991-present
Ficcadenti & Waggoner Consulting Structural Engineers, Inc.
Irvine, California
Project Engineer-1987-1991
Robert Englekirk Consulting Structural Engineers, Inc.
Irvine, California
Design Engineer-1985-1987
Gershfeld / Alkhaseh Engineers, Structural Engineers
Ontario, California
Professional Structural Engineers Association of Southern California
Affiliations: Earthquake Engineering Research Institute
American Concrete Institute
Statement of Qualifications
ta
BP & Associates, Inc. is a full service Mechanical and Plumbing Consulting Engineering
firm. BP & Associates, Inc. exists to serve the Consulting Engineering needs of our clients.
Simply put, we have found that this is accomplished by providing our clients with a
technically strong drawing package provided in a timely manner and for a reasonable fee.
Our goals are to establish healthy, longterm relationships with our clients.
BP & Associates, Inc. brings a diverse design experience. Our experience ranges from the
simple designs used in tilt up industrial projects to the more complex designs used in
hospitals and other medical related facilities involving special ventilation and piping systems.
We tailor our engineering approach to the design needs of the project.
BP & Associates, Inc. is concerned about your time schedule. Once we receive the go ahead
on a project with your firm, and a delivery date for the project is established, the project will
be delivered in a timely manner. We are committed to doing our part in assuring the timely
delivery of the project so that you may receive future work from your clients.
BP & Associates, Inc. in an effort to maximize our efficiency to best serve our clients,
utilizes the latest computer technology including AutoCAD 14 software for our design
documents
TIMOTHY J. POCOCK A
Principal
Education: University of California, Los Angeles, Extension Sequential Program in
Plumbing System Design 1987
Experiences: BP & ASSOCIATES, CORONA, CA —Present
Current Principal of BP & Associates and is responsible for the overall
operations of the company, including accounting, personnel, plumbing
engineering and computer operations.
T.P. DESIGN, CORONA, CA —September 1992 to January 1999
Current Principal/Owner of T.P. Design and was responsible for the overall
operations of the company, including accounting, personnel, engineering and
computer operations.
F.T. ANDREWS, ANAHEIM, CA — January 1989 to September 1992
Senior Plumbing Designer with responsibility for field investigations, client
contact and coordination, design of plumbing, piping, site utilities and fire
protection for commercial, industrial, Institutional, medical, military and
educational projects.
TSUCHIYAMA & KAINO, CONSULTANT MECHANICAL
ENGINEERS, NEWPORT BEACH, CA — April 1983- December 1988
Plumbing Designer responsible or medium to semi -large projects such as
restaurants, hotels, schools, high-rise buildings. Project Director for Tenant
Improvement Department.
Professional Affiliations:
American Society of Plumbing Engineers (ASPE) Los Angeles Chapter.
National Fire Protection Association (NFPA)
Computer Experience:
AutoCAD versions 12, 13, 14 & 2000.
Microsoft Word.
Microsoft Excel.
Projects of Note: Parking Structures
Garfield Parking Structure, Alhambra, CA
First Street Parking Structure, Alhambra, CA
Experian Parking Structure, Costa Mesa, CA
Anaheim entertainment Complex, Anaheim, CA
LA Unified School District, Los Angeles, CA
Glendale Parking, Glendale, CA
Hermosa Beach Parking, Hermosa, CA
Mission Viejo Mall Southwest P.F., Mission Viejo, CA
St. John Medical Center Phase 1B,Washington State
Mission Viejo Mall Northeast P.F., Mission Viejo, CA
UCSD Gilman Drive Parking Facility
ABBY BANERJEE A
Principal
Education: Bachelor of Science in Mechanical Engineering, California Polytechnic
University, Pomona, California, 1991.
Experiences: B.P. & ASSOCIATES, INC., CORONA, CA (February 1999-present)
Current Principal of B.P. & Associates and responsible for the overall operations
of the company, including, personnel, Mechanical engineering and computer
operations.
BUILDING MECHANICAL SYSTEMS, INC. (1991-January 1999)
f' Senior project mechanical engineer. Responsible for establishing client needs,
project coordination and design for medium to large commercial projects.
Projects include educational, institutional, industrial and medical facilities
throughout the state of California and the states of Nevada, Arizona and Texas.
Professional licensing:
Registered Mechanical Engineer - State of California.
Registered Mechanical Engineer - State of Nevada.
Registered Mechanical Engineer — State of Texas (Pending).
Registered Mechanical Engineer - State of Arizona (Pending).
Professional Affiliations:
ASHRAE — American Society of Heating, Refrigerating, Air Conditioning Engineers.
NCESS — National Council of Examiners for Engineering and Surveying.
Computer Experience:
AutoCAD versions 12, 13, 14 & 2000.
Microsoft Word and Excel.
Comply version 5.0 and Energy Pro Title 24 compliance software.
Carrier HAP building cooling and heating load calculation software.
m
Statement of Qualifications
OMB Electrical Engineers, Inc. is a full service electrical engineering firm dedicated to
providing professional services since 1987 in the areas of planning, engineering and
design, construction administration, and inspection services. Our staff of 34 gives us
excellent capability and versatility in meeting demanding design and construction
schedules.
Our designs are completely coordinated with the Architect, Mechanical Engineer and
other specialty consultants. We work closely with the design team to evaluate building
designs to ensure cost effective and energy efficient systems are utilized. Our facilities
design incorporates features promoting energy -efficient use of processes and materials,
including lighting technologies such as the prescription of energy -efficient lamps and
ballasts, and the application of automated lighting controls in public facilities and
institutions, including outdoor recreation areas.
Projects have included fast -track design and construction projects, which have resulted in
successful performance of the more -intensive program review, site-
evaluation/investigation, interdisciplinary coordination, cost control, utilities
improvements, and site adaptation efforts appropriate for working with school districts
and other educational facilities.
OMB Electrical Engineers has extensive experience in the preparation of final drawings,
specifications, cost estimates, construction schedules, design analyses, and design reports
for numerous public agency -developed and managed facilities. Performance of these
services have also included close coordination with state agencies such as the Division of
the State Architect (and California Fire Marshal), as well as, implementation of proven
in-house design quality assurance procedures.
oaaB
JEFFREY OVERMYER
P.E., Principal
Mr. Overmyer has over 29 years of experience in positions with lead -electrical
engineering responsibility. His experience includes the design of power distribution,
telecommunications, lighting, and signal systems for numerous office, industrial,
medical, educational, recreational, and residential projects. He is actively engaged in
design of current projects as well as having responsibility for project negotiations,
contract agreements and marketing. His additional duties include checking of plans and
specifications as part of OMB's in-house quality control procedures.
Assignment:
Principal -in -Charge of Finance & Administrative Functions
Education:
Bachelor of Science in Electrical Engineering, University of California, Irvine (1973)
Professional Registration:
Electrical Engineer, California #8964
Registered in 15 states
Affiliations:
Joint Power Engineering and Industry Applications Societies Orange County Chapter of
the Institute of Electrical and Electronic Engineers (Past Chairman)
National Society of Professional Engineers
Illuminating Engineering Society
International Association of Electrical Inspectors
Projects of Note:
Johnson & Johnson Pharmaceutical Research P.F., San Diego, CA 3 levels, 516 cars
First Street P.F., Alhambra, CA, 4 levels, 250 cars, completed 2001
Garfield Entertainment Center, Alhambra, CA, 5 levels, 804 cars, completed 2002
University of California P.F., Santa Barbara, CA, -4 levels, 903 cars (Schematic Design)
University of California P.F., Gilman Drive, San Diego, CA, 6 levels, 861 cars
LA Unified School District, L.A., CA, 5 small parking facilities, awaiting DSA approval
2300 Michelson P.F., Irvine, CA, 4 levels, 296 cars, pending developer continuance
City P.F. at Lake Natomas Inn, Folsom, CA, -3 levels, 400 cars
City P.F. - Lot C, Sacramento, CA, -10 levels, 1,095 cars w/20,300 sf retail/office
Chapel Avenue P.F., Alhambra, CA, -3 levels, 285 cars
City of Campbell P.F., Campbell, CA, -3 levels, 306 cars
Robinson's-May - Main Place Parking Structure, Santa Ana, CA, -3 levels, 395 cars
Marsh Street Parking Structure, San Luis Obispo, CA, -4 levels, 341 cars
Homestead Village - Extended Stay Motel, Burbank, CA, -2 subterranean levels, 128 cars
Ritz Carlton - Half Moon Bay Parking Structure, Half Moon Bay, CA, -3 levels, 450 cars
LAX Parking Structure #6, Los Angeles, CA, -4 levels, 949 cars
GROUP
COMPANY QUALIFICATIONS
DELTA
Group Delta Consultants (GDC), Inc., is a minority -owned consulting engineering firm
founded in 1986. GDC now has three offices in Southern California including Torrance,
San Diego, Aliso Viejo. The firm has approximately 40 professionals consisting of civil
and geotechnicai engineers, geologists, laboratory and field technicians, deputy
inspectors, drafting/CAD, drilling and support personnel specialized in their respective
fields. GDC offers a broad range of services to serve the needs of its clients. Our
capabilities and services include geotechnical feasibility study, geotechnical field
investigation, in -situ testing, foundation design, construction monitoring and materials
testing, ground improvement and design, slope stability investigation and analyses,
preparation of plans and specifications, environmental site assessments, instrumentation,
seismic studies and earthquake engineering.
During the past 15 years, we have established a record of completing projects on
schedule and within budget for major clients in the public and private sectors. Our
laboratory facility is licensed as an approved testing facility by both the City of Los
Angeles and Caltrans. In addition, we have licensed and experienced deputy inspectors
and technicians specialized in their respective fields including concrete, masonry, batch
plant, fireproofing, shotcrete, soils, structural steel, non-destructive testing and welding to
provide construction observation and testing services.
GDC and its professionals have conducted numerous projects associated with rail
facilities, airports, roads, bridges, commercial developments, academic institutions,
industrial buildings, refineries, power plants, port and harbor facilities, marinas, levees,
dikes, reservoir and dams, sewage collection and water distribution facilities, pipelines
and trestles, hillside grading, major defense and telecommunications facilities. Our work
has included major public agency projects in Los Angeles, Orange, Riverside, San
Bernardino, and San Diego Counties.
What sets Group Delta apart from other firms is our high level of involvement of our
principals and senior managers in each project and particularly our focus on developing
innovative design solutions to reduce overall construction cost. The unique benefits of
our approach and methodologies are demonstrated through the various awards and letters
of commendation GDC has received from clients in both the public and private sectors.
Group Delta Consultants, Inc.
Torrance, Aliso Viejo, and San Diego
KUL BHUSHAN
PRINCIPAL ENGINEER/PRESIDENT
EXPERIENCE SUMMARY
Dr, Bhushan is a registered Civil and Geotechnical Engineer with over 30 years diverse geotechnical experience. His
geotechnical consulting experience includes over 100 bridge and seismic retrofit projects, 20 offshore and harbor
projects, 35 petrochemical/heavy industrial plants, 20 seismic hazard studies, two nuclear power plants, three solar
power plants, 15 medium and high-rise buildings, six airport projects, and a large number of other projects such as
schools, hospitals, commercial, industrial and residential structures, airports, highway bridges, embankments, and
transmission lines.
EDUCATION
Duke University, North Carolina, Ph.D., 1970
Panjab University, India, M.S. (Highway Engineering),
Panjab University, India, B.S. (Civil Engineering), 1962
PROFESSIONAL AFFILIATIONS
American Society of Civil Engineers
PROFESSIONAL REGISTRATION
Registered Civil Engineer, California R.C.E. 22766
1963 Registered Geotechnical Engineer, CA R.G.E. 144
Registered Civil Engineer, Arizona R.C.E. 33231
Registered Civil Engineer, Georgia R.C.E. 25228
Registered Civil Engineer, Nevada R.C.E. 10903
Dr. Bhushan has extensive experience in major development projects buildings in Southern California. He is currently
the Principal -In -Charge for Playa Vista Development (over 1,000 acres in Los Angeles), the Hilton Hotel in Huntington
Beach, the Crowne Plaza Hotel in Garden Grove, the DPSS building in Los Angeles and a number of other projects.
He served as Director of Geotechnical Engineering for Fluor Daniel for six years and, in that capacity, was responsible
for providing technical direction and .overall leadership in the areas of geotechnical engineering, offshore foundation
design, and geoseismicity on all chemical, petrochemical, pipeline, offshore platform, nuclear, solar, and conventional
power plant projects.
PUBLICATIONS AND PAPERS
"Dynamic Testing of Large Capacity Precast Concrete Piles in.the Port of Long Beach," with Dr. Alain E. Holeyman.
Fifth International Conference on Piling and Deep Foundations, Bruges, Belgium, June 1994.
"Settlement of a ring foundation using cone data," with F. Boniadi. Proceedings of The First International Symposium
on Penetration Testing/ISOPT-1/Orlando, Vol. 2, 20-24 March 1988, pp. 681-696.
"Lateral Load Tests on Drilled Pier Foundations for Solar Plant Heliostats," with Shahen Askari. Laterally Loaded
Deep Foundations: Analysis and Performance, ASTM Special Technical Publication 835, Philadelphia, Pennsylvania,
September 1984, pp. 140-156.
"Friction Capacity of Piles Driven into Clay," discussion of a paper by Leland M. Kraft, Jr., John A. Focht, Jr., and
Srinath Amerasinghe (Prot. Paper 16663), Journal of the Geotechnical Engineering Division, ASCE, Vol. 109, No. 5,
Proc. Paper 1.7924, May 1983, pp. 761-762.
"New Design Correlations for Piles in Sands," discussion of a paper by Harry M. Coyle and Reno R. Castello (Proc.
Paper 16379), Journal of the Geotechnical Engineering Division, ASCE, Vol. 108, No. GT 11, Proc. Paper 17435,
November 1982, pp. 1508-1510.
"Lateral Load Tests on Drilled Piers in Sand," with Louis J. Lee and Donald B. Grime, proceedings of a session on
drilled piers and caissons sponsored by the Geotechnical Division at the ASCE Fall Convention, St. Louis, Missouri,
October 28, 1981.
Lynn Capouya, Inc.
rF,
Landscape Architects
LYNN CAPOUYA
Principal
Lynn Capouya, Inc. (LCI), founded in 1979, is a privately owned, full service Landscape
Architectural firm specializing in commercial, industrial, parking structures, transportation,
governmental, recreational and corporate projects, not only in the United States, but
Internationally as well. The Newport Beach based firm with field offices in Los Angeles,
provides individualized quality service to its broad range of clients in both the private and public
sectors. Design services offered by the firm include: Site evaluation, planning, landscapes
harscape, surveys, resource analysis, indigenous plant material studies, as well as PS&E
preparation. LCI also executes comprehensive master, irrigation and lighting plans. As
President of the firm, Lynn E. Capouya, began her career designing governmental and residential
landscape projects in the Southeastern United States. Ms. Capouya's extensive experience with
parking structures lies exclusively in both contractor and consultant capacities. After relocating
her business to California in 1981, Ms. Capouya is successfully diversified in commercial
parking and transit landscape design planning.
LCI has successfully completed and is currently working with several prime consultants on the
preparation of design guidelines and contract plans as well as specifications and estimates
(PS&E) for construction. Commercial and Parking projects include on -site inventory, analysis,
automatic irrigation systems, landscape planting and slope erosion control. LCI is experienced
in various transportation, municipal, school, administration, and parking facilities, along with
presentation of design concepts to local agencies; special studies and other related work.
LCI has offices in the Orange and Los Angeles counties to facilitate interaction between other
agencies with which we need to work. The LCI team is committed in both talents and resources
to achieve the highest quality production in design guidelines, conceptual landscape/irrigation
plans, field investigations, calculations, water and soil evaluation studies, specifications and cost
estimates.
LCI uses professional management techniques to bring each project in on time and within
budget. Milestone schedules are prepared and updated and all tasks are well defined. Efficient
coordination is achieved by the integration and review of all disciplines by Lynn Capouya
herself.
LCT is certified as a Small Business Enterprise (SBE), and a Woman -Owned Business Enterprise
(WBE), as well.
Computer And Cad Capability is utilized in-house on a network of six Microstation/AutoCAD
workstations linked to a file server and operated by the latest Windows NT software program. In
addition, each station is fully loaded with the latest version of Microsoft Word and Excel
programs to ensure compatibility in developing a variety of formatted cost estimates and
specifications.
Lynn Capouya, Inc.
Landscape Architect`
LYNN CAPOUYA
Principal
As Principal -in -Charge, she attends all meetings and is the contact person for
coordination and design of landscape elements. Within LCI, she directs the
overall administrative requirement, schedule and cost controls. During the
PS&E phase she delegates work tasks within her firm and coordinates each
project assignment for the civil water and power concerns. Her challenge is to
creatively enhance the "quality of life' through increased visual appeal with
minimum water use and low maintenance.
Experience: Lynn Capouya has provided design for facilities with interior and exterior
Landscape Design services, including ball fields parking lots, Softscape,
hardscape, and public exterior area development at various facilities including
medical education, and the Los Angeles School District Greening Program
involving several school locations. As noted, Lynn's professional training
(BLA) was completed at the University of Arizona in Tucson, a desert
environment, which gives her versatility, training, and experience in a variety of
climatic situations. Typically, Lynn researches the local area via
nursery/contractor contacts to ensure proper plant material selection and local
availability.
Education: Bachelor of Landscape Architecture, 1979, University of Arizona
Professional: 1982, Landscape Architecture, Alabama # 245
1983, Landscape Architecture, California # 2314
1987, Landscape Architecture, Arizona # 20757
1994, Landscape Architecture, Washington # 249-01-0000630
1994, Landscape Architecture, Oregon # 326
1995, Landscape Architecture, Virginia # 0406-000595
2000 Landscape Architecture, Texas # 2009
W
Lynn Capouya, Inc.
T&q"-
Landscape Architects
Relevant Experience
PARKING STRUCTURE # 6, LA INTERNATIONAL AIRPORT, LA, CA
Our scope of work included landscape, hardscape, and irrigation. The expanded pedestrian walkways
inside the edge of the structure and bollards used to give additional security light and define this path
were included with the landscape to define vehicular/pedestrian boundaries. As xeriscape regulation has
been enacted in the City of Los Angeles, we evaluated the existing plant materials around the airport and
at the new tower as we selected our plant palette. An effort was made to emphasize more drought
tolerant varieties. The fence located next to the landscape hedge was a theme item, carried from
previous projects to control pedestrian traffic by directing it to crosswalks. An added plus was the shade
tolerant planting provided in the ramp itself. This is a very low maintenance plan. The entire project
was done on AutoCAD per project requirements, with a date of completion in 1997 and a total project
cost of 10 million dollars.
PARKING STRUCTURE # II, CALIFORNIA STATE UNIVERSITY, LA, CA:
Lynn Capouya, Inc. was the landscape architect for this 1,200 space post -tensioned concrete parking
structure serving the Cal State University at Los Angeles. The sitting and design enhances the character
of the area, visually blending the parking structure mass with that of the adjacent facilities. Plantings
indicated are compatible with the climate of Los Angeles and adjacent areas. Strong consideration was
given to the overall aesthetic and maintenance characteristics of the landscape solution, as well as to the,
incorporation of `like' planting materials on all areas disturbed by the project. All disturbed or
manufactured slopes were re -vegetated. with plant materials to match existing. The design shall
eliminate, as is practical, the steeply sloped banks from the streets to the structure in order to reduce
maintenance concerns. The structure was built to provide parking for the new Luxman Center for the
Arts which is adjacent to the parking facility. Date of completion was in May 1997 with a total cost of
$7,613,000.00.
BALDWIN PARK TRANSPORTATION CENTER, BALDWIN PARK, CA:
Lynn Capouya, Inc., was responsible for the landscape component of PS&E. The firm needed to
identify site issues and bring visual appeal to this structure. The City of Baldwin Park wanted to
establish their own look while providing rider services for the public. A cactus garden was designed as
a central focus for the parking lot and station. This transit station is part of Metro Link and Ms.
Capouya is MTA certified as a DBE,
LA SIERRA COMMUTER RAIL STATION, RIVERSIDE COUNTY, CA:
The La Sierra station is one of the Metrolink stops on the Riverside -Fullerton -Los Angeles line. The
line also carries heavy Santa Fe Railway traffic. The station consists of two 680' long passenger
platforms with passenger shelters. The facility includes a parking lot for 350 vehicles, a bus and a `kiss
and ride' drop-off area. Lynn Capouya, Inc. designed landscape and irrigation for this site area along
with the street median, platform planters, drop-off area, and perimeter. All plans include water
conserving plant materials, irrigated in a manner consistent with the State of California water
conservation ordinance and adapted for the County of Riverside.
COMPTON TRANSPORTATION FACILITY, COMPTON, CA:
This new multi -modal transportation station required landscape and irrigation plans for structure and
parking lot areas. All plans were per City of Compton Standards. This project was made similar to the
Blue Line transportation centers through out the County of Los Angeles, and LCI was sub -consultant to
the Edward C. Barker and Associates team.
CONSENT CALENDAR
25.13. AGMT NO. 2002-143 - PSYCHOLOGICAL SERVICES - Amend the
agreement with Dr. Eric Gruver for psychological services in an amount
not to exceed $40,000.00 - Police Department
........... ::0E-:TH:E-:: "Y*':HA 1-:"P.A"
doN.STRUC. TI: N
.......... .... C T.Y.': ..... R. ...............
-
----------------------------------
Councilmember Bist requested that the design plans for the proposed
parking structure be reviewed by the City Council once completed.
Motion: 1. Approve and certify a Negative Declaration for the construction of
the new City Hall parking structure and demolition of existing
juvenile detention center.
2. Approve appropriation adjustment. (Requires five affirmative
votes.)
APPROPRIATION ADJUSTMENT NO. 03-002 - Accepting funds in the
amount of $2,600,000.00 from revenue account and appropriate same
to the expenditure account to fund the project
3. Direct the City Attorney to prepare and authorize the City
Manager and Clerk of the Council to execute agreement.
AGMT NO. 2002-144 - Execute an agreement with Gordon &
Williams, Incorporated for Program Management Services to design
and construct a new parking structure within the existing City Hall
parking lot and demolish the existing Orange County Juvenile
Detention Center building located at 500 Ross Street for an overall
guaranteed maximum price of $2,540,000.00 - Public Works Agency
and Planning and Building Agency
MOTION: Bist SECOND: Alvarez
VOTE: AYES: Alvarez, Bist, Christy Franklin, McGuigan,
Solorio (6)
NOES: None (0)
ABSENT: Pulido (1)
*** END OF CONSENT CALENDAR ***