City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
August 16, 2022
TOPIC: DTSA Skate Park
AGENDA TITLE:
Approve License Agreement with East End Realty Partners, LP to Construct New
Downtown Skate Park
RECOMMENDED ACTION
Authorize the City Manager to execute the first amendment to the license agreement with
East End Realty Partners, LP to construct and maintain a new skate park in Downtown
Santa Ana for a five-year term of August 16, 2022 to August 16, 2027, subject to non-
substantive changes approved by the City Manager and City Attorney.
DISCUSSION
In December 2018, City Council and East End Realty Partners, LP entered into a license
agreement to construct a new skate park in Downtown Santa Ana (DTSA) as a measure
of providing public place-making space. As a direct response to the many Santa Ana
youth that use skateboards as a mode of transportation and recreational activity, DTSA
stakeholders are interested in constructing a skate park that will promote a healthy
lifestyle, potentially alleviate damage to downtown infrastructure and minimize pedestrian
injuries.
Adding a skate park in DTSA also creates an amenity for attracting more visitors to the
area. These visitors will continue to eat, shop and play in DTSA, which in turn increases
revenues to the City.
Upon City Council approval of the License Agreement, East End Realty Partners, LP will
fund the design and construction of the skate park in the alley behind the city-owned
parking structure at 5th and Spurgeon. Currently, the alley is used by service trucks for
the adjacent businesses to exit when they enter through Spurgeon to drop off goods for
the businesses. The construction of the skate park will ultimately eliminate that exit.
Several accommodations to the area have been completed such as: removing the
overhead wires, expanding the entrance/exit to accommodate large trucks, and allowing
a two-minute grace period for trucks to drive through the entry/exit of the parking structure.
DTSA Skate Park
August 16, 2022
Page 2
2
8
8
0
The License Agreement has a five-year term and the ownership of the property remains
with the City. The downtown skate park operations will comply with the Santa Ana
Municipal Code section 31-5 under Skate Park Facility Regulations.
The License Agreement approved in December 2018 was delayed due to unforeseen
circumstances, but the East End Realty Partners, LP is committed to designing and
constructing the skate park by the end of 2023. The Planning and Building Agency and
Public Works Agency have been consulted on this project and will continue to provide
permit/plan review until the project is completed. No city funding will be used for this
project.
FISCAL IMPACT
There is no fiscal impact associated with this action
EXHIBIT(S)
1. License Agreement
Submitted By: Steven Mendoza, Assistant City Manager
Approved By: Kristine Ridge, City Manager
FIRST AMENDMENT TO RIGHT OF ENTRY AND LICENSE AGREEMENT THIS FIRST AMENDMENT TO RIGHT OF ENTRY AND LICENSE AGREEMENT is entered into on August 16. 2022, by and between East End Realty Partners, LP, a California limited partnership ("Licensee"), and the City of Santa Ana, a charter city and municipal corporation organized and existing under the Constitution and laws of the State of California ("City") (collectively, the "Parties" and each a "Party"). RECITALS A.The Parties entered into Right of Entry and License Agreement No. A-2018-272, datedDecember 4, 2018 ("License"), by which Licensee proposed to fund the design,construction and maintenance of a new Skate Park in Downtown Santa Ana ("Project") inthe City alley located behind the parking structure on the southwest comer of French andSpurgeon, in the City of Santa Ana (APN 398-326-1 l) ("Property").B.In accordance with the terms and conditions of the License, the Parties now wish toamend the License to: extend the Term of the License; revise the insurance requirements;and, extend the construction completion date for the Project.NOW THEREFORE, in consideration of the mutual and respective promises, and subject to the terms and conditions of the License, except as hereinafter modified, the Parties agree to the following: I.Section 2, Term, shall be amended to extend the Term of the License through August
16, 2027, unless an extension or renewal is granted by the City. Notwithstanding theforegoing or any other provision of the License, either City or Licensee may terminatethe License with or without cause, or for any reason, at any time, by giving the otherParty thirty (30) days written notice of termination at the address provided in the License.2.Section 7.1, City Improvements to Parking Structure, shall be amended to confirmthat all referenced City Improvements have been completed.3.Section 7.2, Completion of Work, shall be amended to set a Completion Date ofDecember 31, 2023, for Licensee to finish the Work related to the Project.4.Except as modified by this First Amendment, all terms and conditions of the Licenseshall remain in full force and effect.{signatures on following page}
EXHIBIT 1