HomeMy WebLinkAbout23A - HICKORY/HOBART WATER MAINREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
CLERK OF COUNCIL USE ONLY:
JANUARY 5, 2004
TITLE:
APPROVED
HICKORY STREET ~ HOBART
STREETWATER~IN
IMPROVEMENTS (PROJECT 3164)
ECOMMENDED ACTION
[] As Recommended
[] As Amended
[] Ordinance on 1st Reading
[] Ordinance on 2"d Reading
[] Implementing Resolution
[] Set Public Hearing For
CONTINUED TO
FILE NUMBER
1. Award a contract to Nikola Corporation, the
bidder, in accordance with unit bid prices in the
$338,472.
lowest responsible
estimated amount of
2. Approve a Funding Analysis with a total estimated construction cost
of $431,800.
DI,SCUSSION
This project involves the construction of new water main and
appurtenances on Hickory Street between McFadden Avenue and Hobart Street
and on Hobart Street between The Bike Trail and Standard Avenue (Exhibit
1). Work encompasses the construction of new water mains, valves, fire
hydrants, and water services. Once completed, this project will eliminate
water main breaks and leaks associated with older and deteriorated water
mains. In addition, it will enhance water service capacity and provide
fire protection to the surrounding neighborhoods.
The Notice Inviting Bids was advertised on November 4 and 5, 2003 and
bids were opened on December 4, 2003. A sun%~ary of the bid invitations
mailed, the bids received, and the bid results follows.
Santa Ana Contractors receiving notices: 5
Contractors requesting bidding documents: 10
Bids received: 4
Bids received from Santa Ana Contractors: 1
Page 23 23.A.
Hickory Street and Hobart Street
Water Main Improvements
Project 3164
January 5, 2004
Page 2
NAME OF BIDDER
CITY
BID AMOUNT
1. Nikola Corporation
2. R&L Sewer
3. Caliber Engineering Co.
4. Palp Inc.
Irvine
Paramount
Santa Aha
Long Beach
$338,472.00
$430,832.40
$528,155.00
$533,979.00
A total of 4 bids were received and all were responsive. The lowest bid
was submitted by Nikola Corporation, for $338,472, which is below the
Engineer's estimate of $370,000.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the proposed
project is exempt from further review. Categorical Exemption No. 2003-
227 will be filed for this project.
FISCAL IMPACT
The Funding Analysis shows a total estimated construction cost of
$431,800 for the project (Exhibit 2). The funds are available in the
Water Capital Construction Fund (account 66-579-6635).
Executive Director
Public Works Agency
K\Construction\RFCA-draft\3164 60 WD
APPROVED AS TO FUNDS AND ACCOUNTS:
23.A. Page 24
_]/
NTS
City Council
Agenda Date
January 5, 2004
PROJECT LOCATIONS
NOT TO SC~I.~
EXHIBIT 1
Title:
PROJECT 3164
HICKORY AND HOBART STREET
~,~lV~ IMPROVEMENTS
FUNDINGANA_LYSIS
PROJECT 3164
HICKORY STREET AND HOB~RT STREET
WATER MAIN IMPROVEMENTS
Construction Contract
Contract Administration
Inspection and Testing
Survey Staking
Contingencies
TOTAL ESTIMATED CONSTRUCTION COSTS
$338,472
9,481
35,000
15,000
33,847
$431,800