HomeMy WebLinkAbout23A - FLOWER & FIFTEENTH ST.
CITY COUNCIL MEETING DATE:
~
~
REQUEST FOR
COUNCIL ACTION
CLERK OF COUNCIL USE ONLY:
AUGUST 16, 2004
TITLE:
APPROVED
CONTRACT AWARD FOR FLOWER AND
FIFTEENTH STREETS SANITARY
SEWER IMPROVEMENTS (PROJECT
04-3507)
0 As Recommended
0 As Amended
0 Ordinance on 151 Reading
0 Ordinance on 2nd Reading
0 Implementing Resolution
0 Set Public Hearing For
,,/
CONTINUED TO
FILE NUMBER
,
--'
RECOMMENDED ACTION
1. Award a contract to Dominguez General Engineering and Construction,
the lowest responsible bidder, in accordance with unit bid prices for
an estimated amount of $266,120 for the installation of sewer
improvements along Flower and Fifteenth Streets.
2. Approve a Funding Analysis with a total estimated construction cost of
$332,800.
DISCUSSION
The existing sewer mains along Flower and Fifteenth Streets were built in
the 1930' s (Exhibit 1). The sewer mains have exceeded their expected
design life, encountered deterioration, and are undersized. This project
will provide for the installation of sewer mains, laterals, manholes and
cleanouts. Once completed, the project will increase sewer capacity and
eliminate the maintenance problems associated with older and deteriorated
sewer mains.
The Notice Inviting Bids was advertised on June 25 and 28, 2004, and bids
were opened on July 22, 2004. A summary of the bid invitations mailed,
the bids received, and the bid results follows.
Santa Ana Contractors receiving notices:
Contractors requesting bidding documents:
Bids received:
Bids received from Santa Ana Contractors:
3
8
5
0
23A-1
Project 04-3507
Flower and Fifteenth
Sewer Improvements
August 16, 2004
Page 2
Streets
Name of Bidder
1. Dominguez General Engineering
and Construction
2. Mike Stanton Construction
3. Southern CA Underground
4. R&L Sewer, Inc.
5. Ross A. Guy & Son, Inc.
City
Bid Amount
Rosemead
Camarillo
Brea
Paramount
Fallbrook
$ 266,120
$ 330,900
$ 334,110
$ 423,225
$ 493,383
A total of five bids were received, and all were responsive. Dominguez
General Engineering and Construction submitted the lowest responsive bid
for $266,120, which is below the Engineer's estimate of $277,510.
ENVIRONMENTAL IMPACT
Pursuant to the California Environmental Quality Act, Environmental
Review No. 2004-103 has been completed and a Negative Declaration has
been filed for this project.
FISCAL IMPACT
The Funding Analysis shows a total estimated construction cost
$332,800 for the project (Exhibit 2). Funds are available in
Sanitary Sewer Service Fund (account no. 56-575-6631).
J~~r~-
Executive Director
Public Works Agency
JGR\GA\DI\ET\RFCA\08-16-04 RFCA 04-3507 55 WD
of
the
APPROVED AS TO FUNDS AND ACCOUNTS:
Agency
23A-2
-' ,
4
«~~-\ 22
o--.\~
,pA G~ L
G'r~ i
22
FIRST ST
... ...
'" '"
ClCS''''' All( CllES''''' All(
.... I
to')
~ ~-~ LOCA PI
~
c I
~ ...
.,,:0..- $I
RlCHLAND ST
<:5 ""'SILL All(
...
~
~ ~
MCFADDEN AVE
~
17TH
,,," 5'
... :;; :;;
'" :;; :;;
.
::c
i
15TH ST
~ ! .
i I V
~ !
_IIICI'''' All(
NOT TO SCALE
PROJECT LOCATIONS
EXHIBIT 1
SANT A ANA
'PWA'
, ,
City Council
Agenda Date
August 16, 2004
Title:
PuEl.IC WORKS AGENCY
~
NTS
PROJECT 04-3507
FLOWER AND 15TH STREET
SANITARY SEWER IMPROVEMENTS
FUNDING ANALYSIS
PROJECT 04-3507
FLOWER AND FIFTEENTH STREETS SANITARY SEWER IMPROVEMENTS
Construction Contract
$266,120
Contract Administration
12,680
Inspection and Testing
16,000
Survey
11,388
Contingencies
26,612
TOTAL ESTIMATED CONSTRUCTION COSTS
$332,800
Exhibit 2
23A-4
Project No. 04-3507: FJ
BIDDER
ADDRESS
BID BOND
BID ITEM
1 Sheeting, Shoring and
Trench Protection
2 Construct 8" P.V.c. Sewer r
3 Construct P.C.C. Sewer Ma
4 Remove Existing Sewer Ma
5 Construct 6" P.V.C. Sewer I
Main to Property Line
6 Construct 6" P.V.C. Sewer
Property Line (frame and c<
7 T.V. Inspection ofComplet
8 Traffic Control, Stripping, P
and Traffic Loops
SUB-TOTAL
Add - On Alternate (If Re
9 Imported Backfi11 (If Requi
TOTAL BID PRICE PLU
CITY OF SANTA ANA
ower and 15th Street Sanitary Sewer Improvements
MS
Main
nhole
nhole
Lateral from Sewer
Cleanout at
over)
ed Sewer Main
Pavement Markings
quired)
Ired)
US ALTERNATE
BID DATE:
July 22, 2004
ENGINEER'S IDOmingueZ Gen, Eng, Cont. Mike Stanton Construction Southem Ca. Underground Cont. Inc.
ESTIMATE 3606 Strang 3578 Corona St. P.O. Box 1747
Rosemead, CA 91770 Camari110, CA 90316 Brea, CA 92822
Yes Yes Yes
UNIT QTY. T UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
LS I I I $15,000.00 $15,000.00 $7,000.00 $7,000.00 $27,300.00 $27,300.00 $20,000.00 $20,000.00
LF I 1,410 $85.00 $119,850.00 $80.00 $112,800.00 $83.00 $117,030.00 $120.00 $169,200.00
EA I 6 $5,000.00 $30,000.00 $5,000.00 $30,000.00 $2,600.00 $15,600.00 $3,000.00 $18,000.00
EA I 3 I $1,000.001 $3,000.001 $2,000.00 $6,000.00 $3,500.00 $10,500.00 $1,000.00 $3,000.00
LF I 1,050 $65.00 $68,250.00 $80.00 $84,000.00 $95.00 $99,750.00 $80.00 $84,000.00
EA I 35 $500.00 $17,500.00 $500.00 $17,500.00 $700.00 $24,500.00 $1,000.00 $35,000.00
U)
LF I 1,410 1 $1.001 $1,410.001 $2.001 $2,820.00 I $2.00 I $2,820.00 I $1.00 I $1,410.00 I I
<C
LS I I I $15,000.001 $15,000.001 $4,500.001 $4,500.00 I $13,400.00 1 $13,400.00 1 $3,000.00 I $3,000.00 I M
N
I
$270,010.00 $264,620.00 $3 I 0,900.00 $333,610.00
CY
500
$15.00
$3.00
$1,500.00
$40.00
$20,000.00
$1.00
$7,500.00
$500.00
$277,510.00
$266,120.00
$330,900.00
$334,110.00
BIDDER ENGINEER'S R&L Sewer Inc. Ross A. Guy & Son, Inc
ESTlMA TE 8815 E. Somerset P.O. Box 1988
ADDRESS Paramount, CA 90723 Fallbrook, CA 92088
BID BOND Yes Yes
BID ITEMS UNIT QTY. UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Sheeting, Shoring and LS 1 $15,000.00 $15,000.00 $6,590.00 $6,590.00 $3,540.00 $3,540.00
Trench Protection
2 Construct 8" P.Y.c. Sewer Main LF 1,410 $85.00 $119,850.00 $145.00 $204,450.00 $178.00 $250,980.00
3 Construct P.C.C. Sewer Manhole EA 6 $5,000.00 $30,000.00 $4,340.00 $26,040.00 $2,300.00 $13,800.00
4 Remove Existing Sewer Manhole EA 3 $1,000.00 $3,000.00 $5,000.00 $15,000.00 $710.00 $2,130.00
5 Construct 6" P.Y.c. Sewer Lateral from Sewer LF 1,050 $65.00 $68,250.00 $100.00 $105,000.00 $186.00 $195,300.00
Main to Property Line
6 Construct 6" P.Y.C. Sewer Cleanout at EA 35 $500.00 $17,500.00 $550.00 $19,250.00 $270.00 $9,450.00
Property Line (frame and cover)
7 T.Y.Inspection of Completed Sewer Main LF 1,410 $1.00 $1,410.00 $2.00 $2,820.00 $1.30 $1,833.00
8 Traffic Control, Stripping, Pavement Markings LS 1 $15,000.00 $15,000.00 $17,200.00 $17,200.00 $11,500.00 $11,500.00
and Traffic Loops
SUB -TOTAL $270,010.00 $396,350.00 $488,533.00
Add - On Alternate (If Required)
9 Imported Backfill (If Required) CY 500 $15.00 $7,500.00 $53.75 $26,875.00 $9.70 $4,850.00
TOTAL BID PRICE PLUS ALTERNATE $277,510.00 $423,225.00 $493,383.00