CLERK OF COUNCIL USE ONLY:
FEBRUARY 6, 2006
TITLE:
APPROVED
o As Recommended
o As Amended
o Ordinance on 1st Reading
o Ordinance on 2" Reading
o Implementing Resolution
o Set Public Hearing For
COOPERATIVE AGREEMENT WITH
CALTRANS FOR LANDSCAPING AT
STATE ROUTE 55 AND MACARTHUR
BOULEVARD INTERCHANGE (PROJECT
NO. 06-1015)
~---
CONTINUED TO
FILE NUMBER
CITY MANAGER
RECOMMENDED ACTION
Direct the City Attorney to prepare and authorize the City Manager and
the Clerk of the Council to execute a cooperative agreement with Caltrans
in the amount of $805,800 to design and install landscaping at the State
Route 55 and MacArthur Boulevard Interchange.
DISCUSSION
The Orange County Transportation Authority's (OCTA's) Interstate 405 (1-
405)/State Route 55 (SR-55) Interchange Improvement Project was completed
in October 2005. The Cities of Santa Ana, Costa Mesa, and the majority
of businesses in the area have requested replacement landscaping at two
key interchanges to repair the conditions that deteriorated significantly
during the four-year construction period.
On June 27, 2005, the OCTA Board authorized the execution of a
cooperative agreement with the cities of Costa Mesa and Santa Ana, in a
not to exceed amount of $1,343,000. This funding was allocated for the
design and installation of new landscaping at the 1-405/Bristol Street
and SR-55/MacArthur Boulevard Interchanges. Santa Ana's share for the
SR-55/MacArthur Boulevard Interchange was $805,800.
On August 15, 2005, the City Council executed a cooperative agreement
with OCTA stipulating that we agreed to manage our landscaping project
and provide detailed monthly expenditure reports to aCTA. Further, we
agreed to fund any additional cost over the original amount allocated, or
reduce the scope of work to remain within the respective budget. A
funding transfer for the $805,800 was also authorized through the
cooperative agreement.
At this time,
execution of
staff is requesting that the City Council authorize the
a cooperative agreement with Caltrans in the amount of
25F-1
Cooperative Agreement With Caltrans
February 6, 2006
Page 2
$805,800 to design and install landscaping at the SR-55/MaArthur
Boulevard Interchange. The services that Caltrans will perform include
all necessary engineering and environmental documentation. Caltrans will
also advertise, award and administer the construction contract and
provide construction inspection services. The project schedule calls for
the project to be completed by April 2007.
ENVIRONMENTAL IMPACT
OCTA previously filed an Initial Study/Environmental Assessment in July
1999 for the installation of landscaping at this location in conjunction
with the 1-405/SR-55 Interchange Project.
FISCAL IMPACT
Funds in the amount of $805,800 are available in the Measure M Transitway
Program expenditure account (account no. 32-553-6631, project no. 06-
1015) to install new landscaping at the SR-55/MacArthur Boulevard
Interchange.
"~"""~"L'.
~<., ,-' , ,
, \ j , ;
J '" i
r I ,~ 1._
f """:
/' James G. Ross
Executive Director
Public Works Agency
APPROVED AS TO FUNDS AND ACCOUNTS:
~\\~""'~h" ,\\ ,~:-.-
Francisco Gutierrez
Executive Director
Finance & Mgmt. Services Agency~~
25F-2
'-",
"
"'
"'
~:
::l'
0,
n::,
~
f--
(J)
--'"
.~
;,/
r
1
!
Santa Ana
EXHIBIT 1
Title:
COOPERATIVE AGREEMENT WITH CALTRANS
TO DESIGN AND INSTALL LANDSCAPING AT
THE STATE ROUTE 55 AND MACARTHUR
BOULEVARD INTERCHANGE
i'l'ftl
~~
~,dvcat'on JSt
City Council
Agenda Date
SANTA ANA
IpWAI
FEBRUARY 6, 2006
Ptlblic Wori<s Agency
25F-3