CONTRACT CHANGE ORDER NO. 1
PROJECT 05-3197 - MAIN STREET
WATER MAIN IMPROVEMENTS
o As Recommended
o As Amended
o Ordinance on 151 Reading
o Ordinance on 2nd Reading
o Implementing Resolution
o Set Public Hearing For
CONTINUED TO
FILE NUMBER
RECOMMENDED ACTION
Approve Change Order No. 1 to the Main Street Water Main Improvements
Project to work overtime, remove and dispose of the existing concrete
pavement beneath the existing asphalt street, and lower the water main
to avoid existing utilities for an estimated cost of $69,500.
DISCUSSION
Change Order Number: 1
Project Description:
Main Street Water Main Improvements between
Sunflower Street and MacArthur Blvd.
Contractor: A. R. Sarmiento, Inc.
P.O. Box 1304
La Mirada, CA 90637
Original Contract Cost: $341,220
Amount of this
Change Order:
$69,500
20.3%
Previously approved
Change Order:
-0-
0%
Total Change Orders:
$69,500
20.3%
23A-1
Change Order No. 1
Project No. 05-3197
February 21, 2006
Page 2
On September 19, 2005, the City awarded a contract for the Main Street
Water Main Improvements Project to A. R. Sarmiento, Inc. for the
estimated amount of $341,220 plus a ten percent contingency totaling
$375,342. This project provides for construction of a new water main and
appurtenances along Main Street from MacArthur Boulevard to Sunflower
Avenue.
The following three items are responsible for the cost increases:
1. The limited access to the Hutton Center offices has prompted the
request to have the contractors work longer hours and Saturdays to
mitigate the impact to the offices and to complete the project as
soon as possible.
2. During construction, concrete pavement was encountered beneath the
existing asphalt street. The concrete, estimated to exist along the
entire length of the project, was not shown on the plan.
3. At several locations existing utilities were in conflict with the
new water main. To work around these utilities the contractor needs
to install the water main at a lower depth.
These unforeseen conditions will result in additional costs related to
overtime work, saw cutting, demolition, disposal, and installation of the
water main at a deeper level. The extra work will be done on a time and
materials basis.
Since this change order will exhaust the project contingency, the
Council's approval is required to cover this extra cost and preserve the
project's contingency for any additional project unforeseen conditions.
Estimated cost = $69,500
FISCAL IMPACT
The cost for the change order is estimate at $69,500. Funds are available
in the Water Utility Capital Projects Fund (account no. 66-579-6635).
APPROVED AS TO FUNDS AND ACCOUNTS:
/c2e~~fi- ~~ r"---.--
James G. ROss .
Executive Director
Public Works Agency
~~,,(~
~~rancisco Gutierrez
V Executive Director
Finance & Mgmt. Services Agency ./
. ~ (-
23A-2