HomeMy WebLinkAbout23B - PROJ THE ZOO AT PRENTICE
CITY COUNCIL MEETING DATE:
CLERK OF COUNCIL USE ONLY:
REQUEST FOR
COUNCIL ACTION
MAY 7, 2007
TITLE:
APPROVED
CONTRACT AWARD FOR THE ZOO AT
PRENTICE PARK PICNIC AREA AND
LIGHTING, DELHI PARK LANDSCAPING,
AND CENTENNIAL PARK PICNIC
SHELTERS (PROJECT NOS. 06-6378,
06-7905, 06-6376, AND 07-6000)
o As Recommended
o As Amended
o Ordinance on 1" Reading
o Ordinance on 2" Reading
o Implementing Resolution
o Set Pubiic Hearing For
f2~
CONTINUED TO
FILE NUMBER
CI
RECOMMENDED ACTION
1. Award a contract to Fleming Environmental, Inc. , the lowest
responsible bidder for the base bid plus add-on alternate two in the
estimated amount of $673,870 for construction of the Zoo at Prentice
Park Picnic Area and Lighting, Delhi Park Landscaping, and Centennial
Park Picnic Shelters.
2. Approve a Funding Analysis with a total estimated construction cost of
$842,300.
3. Approve an appropriation adjustment recognizing $156,000 in the
Residential Development District 3 revenue account (account no. 313-
01-5070-3) and appropriating this amount to the Residential
Development District 3 expenditure account (account no. 313-232-6631);
and recognizing $74,000 in the Residential Development District 4
revenue account (account no. 314-01-5070-2) and appropriating this
amount to the Residential Development District 4 expenditure account
(account no. 314-232-6631).
DISCUSSION
Some of the existing amenities at the Zoo at Prentice Park, Delhi Park,
and Centennial Park have deteriorated and are in need of replacement or
upgrades (Exhibit 1) . This project consists of replacing the
existing shade structure with an open space picnic area including new
benches, landscaping, concrete walkways, and a new lighting system at the
Zoo at Prentice Park.
238-1
The Zoo at Prentice Park Picnic Area &
Lighting, Delhi Park Landscaping
And Centennial Park Picnic Shelters
May 7, 2007
Page 2
In addition, the project includes the installation of landscaping and an
irrigation system at Delhi Park and replacement of the existing shade
structures, including wall mounted flood lights, at Centennial Park.
Add-on alternative two will be used to install sod at Delhi Park. Once
completed, these improvements will provide better service and improve the
aesthetics at these parks.
The Notice Inviting Bids was advertised on March 12 and 14, 2007, and
bids were opened on April 4, 2007. A summary of the bid invitations
mailed, the bids received, and the bid results follows.
Santa Ana Contractors receiving notices: 13
Contractors requesting bidding documents: 17
Bids received: 7
Bids received from Santa Ana Contractors: 1
NAME OF BIDDER
CITY
BID AMOUNT
Fleming Environmental, Inc.
CS Legacy Construction
Hondo Company, Inc.
PIMA Corporation
Y & M Construction
PCN3, Inc.
Genesis Development
Buena Park
Chino
Santa Ana
Los Angeles
Gardena
Long Beach
Sylmar
$673,870
$680,478
$717,385
$762,300
$762,695
$771,052
$834,226
A total of seven bids were received and all were responsive. The lowest
bid was submitted by Fleming Environmental, Inc., for $673,870, which is
below the Engineer's estimate of $714,260.
ENVIRONMENTAL IMPACT
Environmental Review Nos. 2004-119 and 2005-75 have been completed and a
Categorical Exemption has been filed for Project Nos. 06-6376, 06-6378
and 07-6000, pursuant to the California Environmental Quality Act.
Environmental Review No. 2000-005 has been completed. Negative
Declarations has been filed for Project No. 06-7905, pursuant to the
California Environmental Quality Act.
238-2
The Zoo at Prentice Park Picnic Area &
Lighting, Delhi Park Landscaping
And Centennial Park Picnic Shelters
May 7, 2007
Page 3
FISCAL IMPACT
The funding analysis shows a total estimated construction cost of
$842,300 for the project (Exhibit 2). Funds are available in the
Community Development Block Grant Fund (account. no. 156-347-6631) and
the Park Acquisition and Development Funds (account. nos. 301-232-6631,
313-232-6631, and 314-232-6631) .
APPROVED AS TO FUNDS AND ACCOUNTS:
~ (I~~~~
James G. oss
Executive Director
Public Works Agency
'\(\~~':l;)\"--' ~'-:\~.
Francisco Gutierrez
Executive Director
Finance & Mgmt. Services Agency
j)
(1.,1
~vei
Gerar 0 Mouet
Executive Director
Parks, Recreation and Community
Services Agency
238-3
CITY
..
SANTA ANA
ORANCe COUNTY
CAlIFQRtU
.-
ft___
tcIU . raT
~,
Sl.N'LOIlER
SANTA ANA
, PW A t
, ,
91a1t..-sAGEICT
CITY COUNCIL
AGENDA
DATE:
MAY 7, 2007
~I~_." AI'I
.- tLHJl
L _-~I [
) ,f
I
PROJECT LOCATION
EXHIBIT 1
TI-E zoo AT PRENTICE PARK PICNIC AREA AND UClHT1NG,
DB..H PARK LAJlD8CAPN3, AM:) celTENNAL PARK PICNIC
SHB.1ERS (PRO.JECT NOS. 06-6378, 06-7905, 06-6378
07-8000)
FUNDING ANALYSIS
PROJECT NOS. 06-6378, 06-7905, 06-6376 AND 07-6000
THE ZOO AT PRENTICE PARK PICNIC AREA AND LIGHTING,
DELHI PARK LANDSCAPING AND CENTENNIAL PARK PICNIC SHELTERS
Construction Contract
Contract Administration
Inspection and Testing
Survey Staking
Contingencies
$673,870
$19,543
$65,000
$16,500
$67,387
TOTAL ESTIMATED CONSTRUCTION COSTS
$842,300
Exhibit 2
238-5
FUNDING ANALYSIS
PROJECT NOS. 06-6378, 06-7905, 06-6376 AND 07-6000
THE ZOO AT PRENTICE PARK PICNIC AREA AND LIGHTING,
DELHI PARK LANDSCAPING AND CENTENNIAL PARK PICNIC SHELTERS
Construction Contract
$673,870
$19,543
$65,000
$16,500
$67,387
Contract Administration
Inspection and Testing
Survey Staking
Contingencies
TOTAL ESTIMATED CONSTRUCTION COSTS
$842,300