Loading...
HomeMy WebLinkAbout23A - HARBOR BLVD, SEGERSTROMREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: June 18, 2007 TITLE: ~~ CLERK OF COUNCIL USE ONLY: APPROVED ^ As Recommended ^ As Amended ^ Ordinance on 1s` Reading ^ Ordinance on 2nd Reading ^ Implementing Resolution ^ Set Public Hearing For CONTINUED TO FILE NUMBER RECOMMENDED ACTION J~; 1. Award a contract to Freeway Electric, the lowest responsible bidder, in accordance with unit bid prices in the estimated amount of $352,000 for traffic management on Harbor Boulevard, Segerstrom Avenue and Edinger Avenue. 2. Approve a Funding Analysis with a total estimated construction cost of 5439,900. DISCUSSION This project provides for installation of video detections, traffic loops, traffic signal upgrades, and traffic signal interconnects on Harbor Boulevard, Segerstrom Avenue and Edinger Avenue (Exhibit 1). The project will allow staff to communicate with traffic signals, monitor traffic volume and speed, and make adjustments as necessary to traffic signal timing based on real time traffic conditions. The Notice Inviting Bids was advertised on May were opened on May 30, 2007. A summary of the the bids received, and the bid results follows. Santa Ana Contractors receiving notices: 0 Contractors requesting bidding documents: 6 Bids received: 4 Bids received from Santa Ana Contractors: 0 9 and 11, 2007, and bids bid invitations mailed, 23A-1 HARBOR BOULEVARD, SEGERSTROM AVENUE AND EDINGER AVENUE TRAFFIC MANAGEMENT (PROJECT NOS. 06-1719, 06-1720 AND 06- 1721) Harbor, Segerstrom, Edinger Traffic Management June 18, 2007 Page 2 NAME OF BIDDER CITY BID AMOUNT 1. Freeway Electric Riverside $352,000 2. Christopher R. Morales, Inc. City of Industry $365,000 3. Republic ITS, Inc. Novato $468,000 A total of four bids were received and all but one were responsive. KDC Inc., failed to submit addendum number two that revises the contract bid items, thereby making their bids non-responsive. The lowest bid was submitted by Freeway Electric for $352,000, which is above the Engineer's estimate of $288,000. ENVIROHI~7ENTAL IMPACT After completion of Environmental Review Nos. 2006-112, 2006-183 and 2006-184, a Categorical Exemption will be filed for these projects pursuant to the California Environmental Quality Act. FISCAL IMPACT The funding analysis shows a total estimated construction cost of $439,900 for the project (Exhibit 2). Funds are available in the Measure M Street Construction Fund (account no. 32-551-6631) the Selected Street Construction Fund (account no. 59-551-6631) and the Transportation system Improvement Area E & F Funds (account nos. 34-631-6631 and 35-631-6631). APPROVED AS TO FUNDS AND ACCOUNTS: James G. Rags Francisco Gutierrez Executive Director Executive Director M Public Works Agency Finance & Mgmt. Services Agency K:\Construction\RFCA-draft\2007\06-18-07 06-1719 Harbor Segerstrom Edinger Award.doc 23A-2 EXHIBIT 1 SANTA ANA ~' City Council HARBOR BLVD, SEGERSTROM AVE AND EDINGER AVE P~ WA ^ Agenda Date: TRAFFIC MANAGEMENT AND INTERCONNECT CONDUIT ,,,~,~„~,~,,,~,,,,, PR OB-1719, 1720 & 1721 June 18, 2007 23A-3 FUNDING ANALYSIS PROJECT NOS. 06-1719, 06-1720 AND 06-1721 HARBOR BOULEVARD, SEGERSTROM AVENUE AND EDINGER AVENUE TRAFFIC MANAGEMENT Construction Contract $352,000 Contract Administration $21,600 Inspection and Testing $31,200 Survey Staking $35,200 TOTAL ESTIMATED CONSTRUCTION COSTS $439,900 Exhibit 2 23A-4