HomeMy WebLinkAbout75B - PH 1501 W MACARTHUR BLVDREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
MAY 5, 2008
TITLE:
PUBLIC HEARING - GENERAL PLAN AMENDMENT
NO. 2008-O1, AMENDMENT APPLICATION NO.
2008-02 AND VARIANCE NO. 2008-03 TO ALLOW
TWO NEW RETAIL BUILDINGS AT 1501 WEST
MACARTHUR BOULEVARD - SAPETTO GROUP,
APPLICANT
C TY MANAGER
CLERK OF COUNCIL USE ONLY:
APPROVED
^ As Recommended
^ As Amended
^ Ordinance on 15f Reading
^ Ordinance on 2nd Reading
^ Implementing Resolution
^ Set Public Hearing For_
CONTINUED TO
FILE NUMBER
RECOMMENDED ACTION
1. Approve and adopt the Mitigated Negative Declaration and Mitigation
Monitoring Program, Environmental Review No. 2007-73.
2. Adopt a resolution approving General Plan Amendment No. 2008-01.
3. Adopt an ordinance approving Amendment Application No. 2008-02.
4. Adopt a resolution approving Variance No. 2008-03 as conditioned.
PLANNING COMMISSION ACTION
On March 24, 2008, the Planning Commission recommended that the City
Council approve and adopt the Mitigated Negative Declaration and
Mitigation Monitoring Program, Environmental Review No. 2007-73; adopt a
resolution approving General Plan Amendment No. 2008-O1; adopt an
ordinance approving Amendment Application No. 2008-02 and adopt a
resolution approving Variance No. 2008-03 as conditioned by a vote of 4:0
(Betancourt, Gartner and Munoz absent) to allow the construction of two
new buildings within an existing retail center at 1501 West MacArthur
Boulevard. The Planning Commission made no changes to the recommended
conditions of approval outlined in the attached staff report (Exhibit A).
FISCAL IMPACT
There is no fiscal impact associated with this action.
J y Trevino
Executive Director
Planning and Building Agency
VF:rb
vf/reports/aa08-02&gpa08-O1&va08-03.cc
75B-1
REQUEST FOR
Planning Commission Action
PLANNING COMMISSION MEETING DATE:
MARCH 24, 2008
TITLE:
PUBLIC HEARING - FILED BY THE SAPETTO GROUP
FOR GENERAL PLAN AMENDMENT NO. 2008-01,
AMENDMENT APPLICATION NO. 2008-02 AND
VARIANCE NO. 2008-03 TO ALLOW TWO NEW RETAIL
BUILDINGS AT 1501 WEST MACARTHUR BOULEVARD
Prepared by Vince Fregoso
Executive Director
RECOMMENDED ACTION
Recommend that the City Council:
PLANNING COMMISSION SECRETARY
APPROVED
^ As Recommended
^ As Amended
^ Set Public Hearing For
DENIED
^ Applicant's Request
^ Staff Recommendation
CONTINUED TO
~~-~-
Planning Manage
1. Approve and adopt the Mitigated Negative Declaration and Mitigation
Monitoring Program, Environmental Review No. 2007-73.
2. Adopt a resolution approving General Plan Amendment No. 2008-01.
3. Adopt an ordinance approving Amendment Application No. 2008-02.
4. Adopt a resolution approving Variance No. 2008-03 as conditioned.
DISCUSSION
Request of Applicant
The Sapetto Group, representing MHI Real Company, is requesting a general
plan amendment, amendment application and variance to allow the
construction of two new buildings within an existing retail center at 1501
West MacArthur Boulevard. Specifically, the applicant is requesting a
zone change to rezone the project site to General Commercial (C-2), a
general plan amendment to change the land use designation to General
Commercial (GC) with a floor area ratio (FAR) of 0.50 and a variance to
allow a reduction in the front yard setback.
Property Description
The project site is a 2.57-acre parcel of land located near the northwest
corner of Bristol Street and MacArthur Boulevard. The site is currently
occupied by two buildings constructed in 1978: an 1,800 square foot Der
Weinerschnitzel restaurant with drive-through service and a 10,957 square
. ~. ~
t LL~
General Plan Amendment No. 2008-O1
Amendment Application No. 2008-02
Variance No. 2008-03
March 24, 2008
Page 2
foot retail building. The vacant west section of the site was formerly
occupied by a full service car wash that operated from 1978 until it was
demolished in November 2006.
The site has a General Plan land use designation of Medium Density
Residential (MR-15) and is located within the Two-Family Residential (R-2)
zoning district. The property is surrounded by multi-family residential
uses to the north and west, commercial and multi-family residential to the
south, and office and commercial to the east (Exhibits 1, 2 and 3).
Project Description
The project involves the construction of two new retail buildings within
an existing retail center. The first building will be a one-story,
6,146 square foot structure that will be located immediately west of the
existing retail building. The second building will be approximately
4,200 square feet in size and will be located at the corner of MacArthur
Boulevard and Plaza Drive. This building is planned for restaurant and
similar food related uses and will incorporate an outdoor dining amenity
into its design (Exhibits 4 and 5).
The existing retail building will also be remodeled to match the
architectural design of the two new buildings. A contemporary design
theme has been proposed by the developer, with elements such as stacked
stone veneer, metal awnings and standing seam metal roofing to be
utilized throughout the project (Exhibit 6).
Site improvements are proposed on the site that includes decorative
paving at the vehicle driveways and pedestrian pathways, restriping and
reslurrying of the parking lot, and the replacement of missing plant
materials and the installation of new landscape planters (Exhibit 7).
Analysis of the Issues
The retail center has been at this location since 1978. Additionally, the
site contained the Beacon Bay Car Wash, which operated on the west side of
the site until it was demolished in late 2006. The applicant is proposing
to construct two retail buildings on the vacant site that are intended to
attract community oriented retail uses.
75B-3
General Plan Amendment No. 2008-01
Amendment Application No. 2008-02
Variance No. 2008-03
March 24, 2008
Page 3
The existing Medium Density Residential (MR) general plan designation
prohibits the use of the site for retail purposes. To allow the project
to proceed, three actions are needed. First, a general plan amendment to
General Commercial (GC) is required. Additionally, an amendment
application must also be approved to change the zoning of the subject
property from Two-Family Residential to General Commercial (C-2).
Finally, a variance to allow a reduction in the front yard setback is
needed.
The proposal will assist in supporting various goals and objectives of the
Land Use Element of the General Plan. First, the project will assist in
promoting a balance of land uses that address community needs, as the
residences in the area will be provided with an additional commercial
center to serve the southern area of the City. Second, the project will
promote land uses, such as restaurants and retail uses, which will enhance
the economic and fiscal viability of the City through an increase in
property and sales taxes. Finally, the project will preserve and improve
the character of the surrounding neighborhood through the numerous
improvements proposed for the site including building design, signage,
parking lot enhancements and landscaping (Exhibit 8).
A zone change to commercial is also required for the site. The project
site is located near two major arterial streets that provide ease of
access and egress into the site. Although the site is currently zoned to
allow a Two-Family residential development such as duplexes, the site has
historically been used as a commercial site. Given a need to provide
additional niche retail and restaurant uses that are easily accessible and
walkable from the surrounding residential developments, a zone change is a
viable option for the site. If the zone change is not approved, the
vacant one acre parcel to the west would not be a large enough parcel to
construct a viable residential project.
Finally, the applicant is requesting approval of a variance to reduce
the required building setback along MacArthur Boulevard from 15 feet to
10 feet. Section 41-369 of the Santa Ana Municipal Code requires a 15-
foot landscaped setback where a property abuts a public street.
However, due to a lot size reduction caused by an eight-foot offer to
dedicate on MacArthur Boulevard and the configuration of the existing
building and parking lot on the east side of the parcel, the applicant
has been unable to comply with the setback standard.
75B-4
General Plan Amendment No. 2008-01
Amendment Application No. 2008-02
Variance No. 2008-03
March 24, 2008
Page 4
The City has requested an eight-foot irrevocable offer to dedicate along
MacArthur Boulevard for a future westbound travel/right turn lane at
Plaza Drive. Until this lane is constructed, an 18-foot landscaped
setback will be provided. The application of the zoning code to require
a 15-foot setback would result in an adverse impact to the on-site
circulation pattern of the project and would result in a loss of 23
parking spaces. To mitigate the reduction in the landscape setback, the
applicant is proposing to upgrade the size of the trees within the front
yard setback to a minimum 36-inch box size.
On March 10, 2008, a public hearing on the project was held by the
Planning Commission. At the conclusion of this hearing, the Commission
continued the item to allow staff time to research noise and traffic
related issues. Noise impacts are not expected from the proposed
project since the primary generator of noise (if any) is anticipated to
be from the outdoor dining area adjacent to Building Three. To mitigate
potential noise impacts, this building has been located approximately
150 feet from the residences to the north, with the outdoor seating area
at the south end of the property and away from the residences. Further,
no uses are proposed to operate late in the evening. A conditional use
permit will be required if any retail and/or restaurant use intends to
operate after 12:00 a.m. Traffic related issues were also analyzed for
this project. During the peak morning and evening hours, approximately
130 hourly vehicle trips are expected from the center, which is typical
for this type and size of retail center. To address issues raised
regarding signalization timing at Plaza Drive, the Public Works Agency
verified that the pavement loops on MacArthur Boulevard are properly
operating. Further, the intersection timing of the signals has being
analyzed and the timing refined to optimize overall operations of
MacArthur Boulevard traffic signals while minimizing the waiting time
for vehicles on Plaza Drive. Finally, to address the signage issue
raised at the hearing, staff is requiring the submittal of a sign
program for the center. This will ensure that future signage is
sophisticated and conveys a sense of high quality.
The Gateway Plaza retail center expansion will contribute to the long-
term benefit of the neighborhood. The development of this site will
allow the construction of buildings that are consistent with the goals
and policies of the General Plan. Further, the site will be upgraded
to meet or exceed landscaping development standards. Additionally, the
project, as conditioned, will not create adverse impacts or be
detrimental to the site or neighborhood. Therefore, based upon an
75B-5
General Plan Amendment No. 2008-01
Amendment Application No. 2008-02
Variance No. 2008-03
March 24, 2008
Page 5
analysis of the project and the project's compatibility with the City's
General Plan and applicable development standards, staff recommends that
the Planning Commission recommend that the City Council approve Amendment
Application No. 2008-02, General Plan Amendment No. 2008-01 and Variance
No. 2008-03 as conditioned (Exhibits 9 and 10).
CEQA Compliance
In accordance with the California Environmental Quality Act, a mitigated
negative declaration has been prepared for this project. The Mitigation
Negative Declaration has been circulated for a 20-day public review
period, which will run from March 10 through March 31. The report
identifies potential environmental impacts and identifies mitigation
measures that reduce the impacts to less than significant levels. The
report identified no noise related impacts resulting from the commercial
development and less than significant traffic impacts from the project.
Although an increase in traffic trips will be generated from the site, the
existing arterial highway system (MacArthur Boulevard and Bristol Street)
will not be impacted. Mitigated Negative Declaration and Mitigation
Monitoring Program, Environmental Review No. 2007-73 will be filed for
this project (Exhibit 11).
~~
Vince Fr oso, CP
Principal ner
VF:jm
vf/reports/aa08-02&gpa08-01&va08-03.032408.pc
75B-6
R7-
PRD
a
R1- a
PRD w ,:
6
R7- U
PRD
e
UUUUL_
C
~l~
C i t y
Al GENERAL AGRICULTURAL
-B PARKING MODIFICATION
C1 COMMUNITY COMMERCIAL
Ct-MD COMMUNITY COMMERCIAL-MUSEUM DISTRICT
C2 GENERAL COMMERCIAL
C3 CENTRAL BUSINESS
C3-A CENTRAL BUSINESS-ARTISTS' VILLAGE
C4 PLANNED SHOPPING CENTER
CS ARTERIAL COMMERCIAL
CR COMMERCIAL RESIDENTIAL
o / C o s t a
C-SM SOUTH MAIN STREET COMMERCIAL DISTRICT
-F FLOOR AREA RATIO
GC GOVERNMENT CENTER
M1 LIGHT INDUSTRIAL
M2 HEAVY INDUSTRIAL
MO MILITARY OPERATIONS
O OPEN SPACE
-OZ OVERLAY ZONE
P PROFESSIONAL
PCD PLANNED COMMUNITY DEVELOPMENT
M e s a
PD PLANNED DEVELOPMENT
PRD PLANNED RESIDENTIAL DEVELOPMENT
R1 SINGLE-FAMILY RESIDENCE
R2 TWO-FAMILY RESIDENCE
R3 MULTIPLE-FAMILY RESIDENCE
R4 SUBURBAN APARTMENT
RE RESIDENTIAL ESTATE
SD SPECIFIC DEVELOPMENT
SP SPECIFIC PLAN
AA 08-2/GPA 08-1NA 08-3 ~
GATEWAY PLAZA
1501 WEST MAC ARTHUR BOULEVARD ~
- - = 500 FEET
1" = 1000 FEET
P L A N N I N G A N D B U I L D I N G A G E N C Y
VICINITY MAP
7[^~I~T 1
M U L T I \ \
~~ C O M M E R C I A L
F A IL- 1 L Y
~ J
R E S I D E N T I A L '~ U
W
W ~ ~
~ ~ ~
Q _ ',~,~~~ 8 ~ O
~~
J
a
MAC ARTHUR BOULEVARD
MULTI ;
FAMILY ~
RESIDENTIAL
J
a
C O M M E R C I A L
N
J
N
m
~ ~
AA 08-2/G PA 08-1 NA 08-3
GATEWAY PLAZA ~~,`,
1501 WEST MAC ARTHUR BOULEVARD
P L A N N I N G A N D B U I L D I N G A G E N C Y
LAND USE MAP
EXHIBIT 2
75B-8
M U L T I
~ C M M E R C I A L
F A I L Y
~ J
R E S I D E N T I A L '~ V
W
W ~ ~ N
> t ~ J
Q ~sJ ~'.I ~ ~ ~ N
~
' 4
J 4
}
` - W
a s
MAC ARTHUR BOULEVARD
MULTI ;
FAMILY ~
0
C O M M E R C 1 A L
RESIDENTIAL N
Q
J
a
AA 08-2/G PA 08-1 NA 08-3 ~
GATEWAY PLAZA ~,
1501 WEST MAC ARTHUR BOULEVARD
P L A N N I N G A N D B U I L D I N G A G E N C Y
ZONING MAP
EXHIBIT 3
75B-9
` ~ la ~
viNao~nv~'vrav virrcs'3niaavmdsaavna~noe an av~vw ~~
3;y~ ~~ ~ ~
;n;g^s9 ~~ I ''~' Q
'~=; ~ i13.LNHJ'IIV.L32I Q3SOdO2Id I~ ~ ~ : r~ '
~`s g ~..a sg a n n / I \
€~ syx ll..__ I ao
a483 mg~9 8e a Ba & _- -
a o
°
m amn
"eG9 YA °&
°F _ --
on
e '=z
a
g
I
° ~~--- ~
s ~ °
~ _ ~aox s~L ~ Ie?Bo I`a I~'E IQ°x s€ __ ~ -
e " _»° -
", „ a i
g ~ ~ `~ o ~s9 ~s~g~€&x eE ~~§ s ~ - '. it I _. - /
a8v E o %. eb '^~°" of $°$ g K 2SRE '~ ~- ~/
=`E „ @ ?Sg3 =~~Y4 $Cu Ee Y53~fl dga=y_ ~'~ ; ~~
°dL _ 8 'r xqa ~"~~&a "E"°s`~a A°=o,ny" ~ ; ..,. ~,
"io 2yA °gxa - _`S,~s~ E;xx~Y%~~v p ~d °t__._ _
°F~ A~ a~ Y -E~wy4 °se $.LEr9 .e ~ 5,°`®'ae~`A`
i
I I..
= e~ Sao .ESA::&o a€~ _ s~ °~@~`~„ ~
oo€x ~sv~g~~a~="A%pE€`4°d€d u~.o%°E ~x ~~ ~~ I --- a
~ _ i `1 1~ _
s ~ 0 0 0 0~ o o ~ u i ~ o ~pi~~ ~ ~{~ ~_ ~ ~ o~
~ I
i
~.
iii
-_ sib I
,~ I z~
> I
0 ICI I
m I~
„ _
E
„
~~
m
0
" ~l
u"
.
„ R~ a'
e° ew - ~
„: na OraB ASS 8 ~~ _ ~ _ l~ ii ~~~~~.~ ~~aa~-~~~e
„ ~% ~~ dw
«.~ '° a~nn `~
~ ~~ 3 E"C° m~ & k. s €
~ xaz ~ 4A~ ~r ~ 4 e o ~~
~z .Eon ~~ enp ~5. pySE Y. 4nC ~7
~~6~a ~~ $~~:p o9l ~dgaa ~ ap~E E u LL9_ '~. F
~o ¢a
a
„ w z " mu rtY m ¢ii E`en ¢~' •`pi •' 4v
o. °n - __
eg s~ 8~~~wLLa= s Sig sa I ~ ~
~ `Ua$~s:a~~x~ex-° gg~E~so I.~gga58 ` ,___ ~ `. 7
€~.e~aA€ € I i ~.
w U~^Fm m_€€'F=~E d^ o ~e°p~8 &`~°~~: i e> r
ati an 3o AOS Cx '€;Pe&^mb? 5 } _ g~ i ~ - ~ ti
D U m ,, m e ~, e t
b
-. _ --
~~ 4'I
s :` }-
.. ~ e 2 ~ a
.X
c
._ n "moo s
R ~i ~~~ of ~ ~~ ~" ~Z ~~8 ~ ~__ 1~ _ -__
mm
m
_I m .o>
d~
~ a e
!_~ II~'el~~Is II ~Ih _ ~_ _
°pffi qq
~O 'bk yb~ yy ~ - - ~.LP
m 4&omwrc Ggomr~wa agomzn egomwa ~ - ~r+~
~ E - g B „_ ~ g ~9 _ __- F^ 4X
' _ ~g _
" - u ~ 4
.m
m
0
~ e .. - - -
_ a°
pp n
~9 so fs?
- "b n °• n8 a°= °a°a' - 'ooa~ - a°a` Win` - a~m'3'
u _ ___ a 'a _ C _ag°<",. __ '€'a~~ m~°«. ~m_ ~' -- __-'- I
~ ~~ I ~
31 ~
~ z
_ a' Q
~ '! J
= (Z }i;
a'
Q W
- ` ~-
II \, (~
~'
I
e II : ~ i
- II
U
I
~ 1i
`_ . an. . 1 .ova
w&~ ~~'
{~
,:
r
~;
ii
AA 08-2/GPA 08-1/'
VA 08-3
EXHIBIT 4
i i
-- -- -- vi '~tiaa vrna aavn~n a a -- ~ ~ ~
I
~I B A M
~t ~~ Q
TI3.LN3J'Idtl.L32I Q3SOdO~Id ~ i ~~;~
s
V
E y
F ~E 22 1
~ ~ 3
~ w s
w a m v ~
~ ~ a ~
~ a ~ A _ ~ e
e ~ E ~
P E ~~~ u~ g t
_g ~ H ~ E L• E ~ ~ g
a z a .. 8~_ ~, y
w LL u z_~ x ~ s c o
c
,•3-~~ • +'.i
L>
x
~tU,e a --
:v
+..~~
1 -
~..
~~~~. ~).
r,,
FYr~
JY
%.:
Y~4
5 ~•
~~ _ -
~`r-
•',_'...
~ ~-
(`~~
.`a~.a
Gr__ _~_e
C ~ }~ -
O ___
.>
N
W
L
Z
N
C '
O 4 r n~~_.' _ -
C `.
U X
m
C
O
R
W
r
O§
c`
'p ~C
LIl
~I
C
R O
4 - '~ l0
LL N
_ _ r~ I W
C'
v ~
' N
W
Q ~ ~
~
S
~ 0
~
I 4
yt ~
sta
a
x
-
t
~ C ..
m S ~ I. C3 ~ m S
rVIJIt7tT C
a i~omn~
-so do
~` /L-80 t/dJ2-8011b~ '
~ R~ -- so a~ -- ~o
x~ ~~` `~ ~~ k~
x
x~ - „~
o _._ ... D - j ? ~~
_. (U ~ ~
G
- _ _.. N
-, __-.
-_-
~+^'~
__, :.Y
- - - 'j~(
`~ n' Y.
~~~
~~J~
.. h JE _......_
LLL-I_ -- r' ..
z~,-0. `, f 1~1
ar-r
- ~ v
~" - --
ss-r
ffiW
X ~.
7
N
T p i ; r ~c ~- - s p m m o p m a
O
o my_ y_ m a x a w_ m L r
~ a ~ ~ ~ ~ a 3 ~ ~ d S
.2 `- ~ ~ ~ o ~ ~ m 3
3 ~_ ~ 'n ~ 3 _ S n ~ w
~~ 3 Z. C ~ _ 3 q:q
~ ~. tl
m a
~ ~ ~
~ - ~ a
a ~ ~ 3
N 3
3
B
q~
i
~,
i i~_~ `. C
~;~~ j PROPOSED RETAIL CENTER .=~c~
~ ~_so; c
B-12
u yr v a in a nu v I I ~
$ s'S?9 I ~ ~ ~ In
.~,-„~ i
gj,yaxx
9n4i==~ ~' 9i
.3; . „ 2I3.LN3J'IIt+.L3~1 Q3SOdO~Id i ~~
a~~~$ai ~ I ~lli
„o-,6s
E
R
~'
€ ~
~ ~
E
g
E
E
y ~ ~
8 ~ ,~
g a ~ a' r d io ~~
c E ~ u v r C
9 E 3 • $ $ C 5 ~.~
u e ., c _.______________________._~Ta __. _.___
£ ~ $ ~ ~ E d r ~7
~ _ ~ ~ -'$ m
o m
x E _ g s a" g ~
a a ~, .. ~ a
b > ~ $ q ~ E S e E O
g < m ~' ~ ~ v E c E E ~ i M
g _ _ ~ a" ~ r _ ~ 4
_'u ~ y E E 9
.9 b~ ~ .4 ,n - - LL - h - ~ C
g h a x a r m =p $
w ~ ..
a m ~ o w LL u ~_~ Y ~ s m9
L L
„0-,L9
1, ~
`: o.
x~ t
<<z
rr`y~ ,, ,
~;
_.
~~- _ _-
~ ~~
~;
~, --- ggg ~
_ n ri~ 4
~ ~ ; 7 I _ ~'~_..
~ .... '
~ `~ 1
' ~ :: f ~ i __._
~- ~-
- ~ -- __
- .- ~ -
-- ~ _
__
i
W
- - -
r
_.
- ~__ ~'F N
__ m W
~.:
~-- ~ _..
r _ >
C ~ ~ e ~ 'C
_ ` ~
- W 4 ..`~\. a~i4 4r cGb ab
W ~ ~
?N
__
~._
__,~ X75
.~__$
.5. '..:
~:- ~s
': ~
~~~--
€F3!
I
d -1
4~ ~„ ~
-~ _~ ~ 'I
F-
J
Z
J
a
F¢-
LIJ
(7
Z __
Q
a
a
U
a
-'
r . '
,,,~
3 ! ! ! s a s' 33 !f!!
I d K }! t t !! !!!'
t
t 1 1
i i y
~
lii
~ i 1 ~
1
~ ~ i ~ ~ i'
~ !
i l!~II~
~ Il~j
i
i
# if l
l
!
~l 1 .:
F
~~
s~
F,
F>
:k
AA 08-2/GPA 08-1~ ~~~ ~~~ ~ e~ ~~d
VA 08-3
EXHIBIT 7 ' ``
n M~.
• 1 ~
~
+ Z
g
~
,~
~ ~, ~: W
a
a..f a U
, ~
j
t~,:~ ,
~
~ J
-
i
i
~I ~
j
~ i
~A ~
v~''w
' i U
Q
1
~ ',
„y
I
~,
__ - one f '~,
s J
~~a_ is
~~ ~- i+
I .o <s
c',
i
-
i o I A' ...- ~.,.
__ _. o
e
} ~ ~
~\` ~ i6
LAND USE ELEMENT
SANTA ANA GENERAL PLAN
City of Santa Ana
Planning Division
Adopted
February 2, 1998
The following is a chronology of the approved general plan amendments that have been incorporated into this
document since the comprehensive update of the General Plan Land Use Element adopted by Santa Ana City Council
February 2, 1998 (GPA 1997-05):
GPA 2008-01 (Adopfion Date), GPA 2007-02 (June 18, 2007), GPA 2006-01 (October 2, 2006), GPA 2005-01
(December 5, 2005), GPA 2005-02 (October 17, 2005), GPA 2004-01 (April 5, 2005, as passed by the voters of Santa
Ana), GPA 2004-04 (July 19, 2004), GPA 2004-06 (July 6, 2004), GPA 2003-02 (June 16, 2003), GPA 2003-01
(February 18, 2003), GPA 2002-01 (September 3, 2002), GPA 2002-03 (August 19, 2002), GPA 2001-03 (February 19,
2002), GPA 2001-02 (January 7, 2002), GPA 2000-09 (May 7, 2001), GPA 2000-08 (February 5, 2001), GPA 2000-03
(December 4, 2000), GPA 2000-02 (November 20, 2000), GPA 1999-02 (October 18, 1999), GPA 1999-01 (August 16,
1999), GPA 1998-04 (October 5, 1998), GPA 1998-05 (September 21, 1998), GPA 1998-01 (May 4, 1998).
AA 08-2/G PA 08-1 /
7~~5
,-. ~ ~ w !,
., ~ ~ f~ 9 j
N ° m v Y' a X 6
C _ ~ ~ m b W ~
~ ~ ~ ~ ~ ~ m ~
c v~
~ W C N
D L' C U U T
rn ~ ~ s E ~ ~ ~ ~ C ~
~ c 3 a ~ @ ~ ~ V ~ w
~ g 9 ~ ~ ~ ~ ~ ,~ ~ o V~ J
fA S .~. ~ C C O O av O '(•~ ~. ~
~ °J ~ f a~ tv7 rZ+ ~ O ~ i O T
75B-16
N
O N
O O N
O O
O
_a ~~n ouSo .~-,~o v~iYnooo~no
~ ~I~ f
}~ '~A y~
~
V
'
Q
S 3
_
.~. ~ N .- .- ~ ~ ~ ~ ~ ~
~
c
~
~ ~
1
A
A~, T
/
W L A• ~+
L 5
~~
u
'9
e5 ~
Q LL ~
z -
` a Q
Q~ W ~
O
~ LL
~ _ g
A
,
a~
~ 3 E
~
2 S
~ ~
~ ~ ~
`
a 4
s g N ~ , VJ u.. $
~ ~ ~
v
a ~~ ~ m € g ~ g m m
:S
:o
r
~ :
~'~
'osvvia°0 .
°s 'rc' ` ~
f ~ ~ !n
.
oe
n
ov
~
°
~ .~
~ .S
~ n
~
a
A ~ c~o $:~c ~oFCt°'a°qSa~
z ..V~q
°
~
9
~
J •
C , ~~
~ ~~ -.
c~
o
a a
..,
~ F
~^ C
o
v° u~
~
°~~E~
°w
8
U
U
'^ ,
~
O
a
V
?
~ Z
p x
3v
~~ci
a
Vi
a
b
.0 5~,~'~oy4.s S.s€`m~~~rv~Ss~uuu
~
~ .
E
~
$;
c
FG
„
~ t
!
r'
, I i
~ ~
, a` EUZ°i EZ(J~U~OXiimrv~a~tAEf lid
.-r.AY~A ~Eriabdd~N~S~~A ~L~aOT°rvNl~`IN
~
~ i
tz-~
N
Q
/ .
`~A
M
75B-17
LAND USE ELEMENT
• To encourage lot consolidation for optimal site design, the floor area
ratio can be calculated on an area wide basis for contiguous parcels
which are part of a large, multi-structure project.
• To qualify for an area wide floor area ratio calculation, a project must
be integrated in design and function, and the owner/developer must
record deed restrictions limiting the project area to the legally allowed
floor area ratio.
Land Use Designations
The Santa Ana Land Use Plan includes 11 land use designations. These
designations indicate the types and intensity of development to be allowed on
the property which they cover. Generally, the designation also reflects the
predominant development character of the area. As is typical in older,
urbanized communities like Santa Ana, there are some areas where existing
development does not completely reflect the land use designation of the Land
Use Plan. Where these occur the properties are deemed legal conforming
and may continue until such time as the property has been vacant for twelve
months or more. Each land use designation and a brief description are
discussed below.
Residential
The Land Use Plan provides for three distinct residential land use
designations. Residential development is also permitted in two other
designations: District Center and Residential/Industrial. The Santa Ana Land
Use Plan includes the following residential land use designations:
• The Low Density Residential (LR-7) designation applies to those areas
of the City which are developed with lower density residential land
uses. The allowable maximum development intensity is 7 units per
acre. Development in this category is characterized primarily by
single-family homes. This designation applies to a large proportion of
the City (6,474.5 acres) representing 47 percent of the City's total land
area.
• The Low-Medium Density Residential (LMR-11) designation applies to
those sections of the City which are developed with residential uses at
permitted densities of up to 11 units per acre. The land area included
in this designation is approximately 443 433.8 acres. The great
majority of the land designated as Low-Medium Density Residential is
located in the westerly portion of the City, north and south of
First Street. Properties with this designation are typically
characterized by mobile
Revised (Adoption Date)) A~~ B ~ 1 8
LAND USE ELEMENT
home parks, a mixture of duplexes and single family residences, or
small lot subdivisions.
• The Medium Density Residential (MR-15) designation applies to
those sections of the City which are developed with residential
uses at densities of up to 15 units per acre. Development in this
designation is characterized by duplexes, apartments, or a
combination of both. A total of 4a-A 413.2 acres is designated as
Medium Density Residential. The designation applies to areas
located in the vicinity of downtown, areas north and south of
MacArthur Boulevard, and in other areas where there are
established multiple-family development projects.
• The Residential /Industrial designation permits either residential
development up to 15 units per acre or industrial uses. The
designation applies to the Logan neighborhood, which was
established near the turn of the century. Since the 1930s, this
18.5-acre area has developed with a mixture of residential and
industrial uses.
• The District Center designation permits residential development up
to 90 units per acre when it is a component of a mixed-use,
master planned project. In the Metro East District Center
residential density is based on a maximum 3.0 floor area ratio and
the overlay development standards. This category includes
approximately 427 acres and is described in greater detail later in
this section.
Professional and Administrative Office
The Professional/Administrative office (PAO) designation applies to those
areas where professional and/or administrative offices are predominant, or
where such development is being encouraged. Land included in this
designation is found primarily near the Civic Center, and along the First
Street and Tustin Avenue Corridors in close proximity to freeways. There
are other smaller PAO areas in the City such as along North Broadway and
along portions of east and west Seventeenth Street. A total of 621.5
acres is included in this land use designation. The floor area ratio intensity
standard applicable to this land use designation ranges from 0.5 to 1.0.
The Professional and Administrative Office areas are intended to provide a
unique environment for office development in those areas of the City where
office uses are the predominant land use. The purpose for maintaining and
supporting these areas exclusively for office and office-related uses is to
encourage major employment centers at locations which significantly lessen
the impact to the City's local street system. The First Street/Tustin Avenue
Revised (Adoption Date) A-18
75B-19
LAND USE ELEMENT
office corridor between the Santa Ana (I-5) and Costa Mesa (SR-55)
Freeways serves this purpose. In addition, the orderly, well-maintained quality
of existing development supports a continuation of these areas as functional
office/employment centers.
The Professional and Administrative Office designation includes a range of floor
area ratios to differentiate development intensity and character in relation to
adjacent land uses. The areas with a FAR of 0.5 are not major office centers, but
rather have an established character of lower intensity garden office and
professional service uses. These areas are typically adjacent to low density
residential neighborhoods, or are converted residential office uses. Office
development along East Fourth Street, between Grand Avenue and the Santa Ana
Freeway, is typical of this low-rise office character. The PAO area located adjacent to
the Civic Center contains a range of office development intensity which supports the
City's functional role as the government center of the County.
The types of uses typically located in the PAO district include the following:
• Professional and administrative offices/office parks;
• Service activities such as copy centers, courier services, travel agencies, and
restaurants when such uses are an integral component of a planned office
development; and
• Professional uses such as accountants, attorneys, doctors, engineers, and
insurance brokers.
General Commercial Districts
The General Commercial district (GC) applies to commercial corridors in Santa Ana including those
located along Main Street, Seventeenth Street, Harbor Boulevard, and other major arterial
roadways in the City. The intensity standard applicable to this designation is a floor area ratio of
0.5 -1.0, though most General Commercial districts have a FAR of 0.5. A total of ~1-A3 1,113.6 acres
of land is included in this designation.
General Commercial districts are key components in the economic development of the City.
They provide highly visible and accessible commercial development along the City's arterial
transportation corridors. In addition, General Commercial land uses provide important neighborhood
facilities and services, including shopping, recreation, cultural and entertainment activities,
employment, and education. The districts also provide support facilities and services for industrial
areas including office and retail, restaurants and various other services.
A-19
Rev/sed (Adoption Date)
75B-20
LAND USE ELEMENT
Table A-4 indicates the development possible under the build-out of the
Land Use Plan. The build-out for residential land uses considered two
scenarios. Effective build-out for residential development is calculated by
adding the 8,783 units possible in the areas designated as District Center to
the existing 74,588 units presently found in the City. Theoretical build-out for
residential development considered the development possible if all of the
areas designated as residential were developed according to the permitted
Land Use Plan intensities. Since the Land Use Element does not
contemplate the elimination of existing housing in the City, the effective
build-out figure represents a more realistic estimate of future residential
development.
As indicated in Table A-4, four of the non-residential land use designations
have a range in FAR intensities. For the non-residential land use
designations, effective build-out considered the development possible under
the lower range of FAR intensities while theoretical build-out considered the
upper FAR range. Typically, parking and landscaping requirements will
result in significantly less floor area for commercial and industrial
developments than that which is permitted under the General Plan.
As indicated in Table A-4, between ~6 65,212 to 77,820 housing units
are allowed by the Land Use Plan. The additional units which presently exist
in the City beyond the maximum number permitted under the theoretical
build-out scenario are a reflection of the higher density multiple-family
developments constructed in the 1970's and 1980's. However, the purpose
of the Land Use Plan as it applies to the residential areas is to preserve
and maintain the stability of existing neighborhoods, regardless of the
character of development. The intent of the Plan is not to create any
displacement, nor decrease existing development densities. Rather, it is to
ensure a safe, healthy, and livable environment for City residents. Existing
residential development entitlements are protected through this Land Use
Element, applicable Zoning regulations, and sections of the City code
pertaining to legal nonconforming uses.
The Land Use Element's implementation may result in an increase in the
amount of commercial, office, and industrial development in the City. As
indicated in Table A-4 up to 5~a^''~ 55,658,406 square feet of commercial
and office development, and 44,891,128 square feet of industrial
development are possible under the effective capacity parameters of Land
Use Plan.
Revised (Adoption Date) ~ ~~ _
Amended Table A-4
Land Use Plan Build-out Capacities
Intensity/Density Effective Theoretical
Land Use Acres Standards Build-outs Build-out
Mixed Use2 103.5 ac FAR 3.0
Metro East Residential DC 5,551 d.u.
SubTotal 5,551 d.u.
Metro East Commercial DC 3,245,185 s.f. 3,245,185 s.f.
SubTotal 3,245,185 s.f. 3,245,185 s.f.
Residential
Low Density Residential LR-7 6,474.4 ac. 7 d.u./ac 45,321 d.u.
Low Medium Density Residential LMR-11 433.8 ac. 11 d.u./ac 4,772 d.u.
Medium Density Residential
MR-15 443:a-as.
413.2 ac.
4
19
0
15 d.u./ac 4-,~-d-r~.
6,198 d.u.
6
Residential/Industrial3
R/1-15 -
~
-as
9.2 ac.
15 d.u./ac 50-~~:
138 d.u.
District Center4 DC 35.9 ac. 90 d.u./ac 3,232 d.u.
SubTotal 7,366.5 ac.
~ ~-.--o-.-~-ao:
r 77,820 d.u., 59,661 d.u.
59-T~d~
,
Commercial
Professional & Admin. Office PAO 621.5 ac. FAR 0.5-1.0 13,536,270 s.f. 27,072,540 s.f.
General Commercial GC 1,113.6 a.c.
a
19 FAR 0.5-1.0 24,254,426 s.f.
7A 14Q 171 o f 48,508,852 s.f.
A A 77R 7A4 o f
District Center4
DC ---
6
323.2 ac.
FAR 1.0-2.0 e
14,079,332 s.f. ,
28,158,665 s.f.
One Broadway Plaza District Ctrg OBPDC 4.3 ac. FAR 2.9 543,193 s.f. 543,193 s.f.
SubTotal 2,062.6 ac. 52,413,221 s.f.
~~ Boa a~ a ~ s 104,283,249 s.f.
Industrial
Industrial IND 2,280.9 ac. FAR 0.45 44,710,202 s.f. 44,710,202 s.f.
Residential/Industrial3 R/I-15 18.5 ac. FAR 0.45 180,926 s.f. 180,926 s.f.
SubTotal 2,290.1 ac. 44,891,128 s.f. 44,891,128 s.f.
Other -
Institutional5 INS 812.6 ac. FAR 0.2-0.5 7,079,023 s.f. 17,697,557 s.f.
Open Space OS 1,019.0 ac. FAR 0.2 _..8,877,876 s.f. 8,877,876 s.f.
SubTotal 1,831.6 ac. 15,956,899 s.f. 26,575,433 s.f.
Notes:
,Effective capacity for non-residential development assumes development possible under the lower range of FAR intensity standards
with the exception of the Metro East District Center. Residential effective capacity was calculated by adding the 8,783 units possible in
the District Center with the existing 74,588 (Census 2000) housing units.
zThe Metro East District Center allows a range of intensity for mixture of residential and commercial development based on the Metro
East Mixed Use Overlay Zone development standards.
,Land use designation permits both residential and industrial development. Buildout assumed 50% of the land area will be developed
as residential and 50% as industrial development.
,Land use designation permits both residential and commercial development. Buildout assumes 90% of land area will be developed
as commercial and 10% will be developed as residential.
FAR -floor area ratio, d.u. -dwelling units, s.f. -square feet (of floor area). Acreage shown in table does not include roads in
right-0f--way.
BEffective capacity assumes FAR of 0.2
Bland use designation permits high intensity office development with ancillary retail use.
This table has been revised to correspond with the GIS Land Use Map illustrated in Exhibit 2.
Revised (Adoption Dete) ~ C ~3~
Variance No. 2008-03
March 24, 2008
Page 1 of 2
Findings of Fact
A. That because of special circumstances applicable to the subject
property, including size, shape, topography, location or
surroundings, the strict application of the zoning ordinance is
found to deprive the subject property of privileges not otherwise at
variance with the intent and purpose of provisions of this Chapter.
The proposed reduction in the front yard setback will allow the
applicant the ability to construct a new addition to the
Gateway Plaza retail center. Due to the conveyance of land for
the widening of MacArthur Boulevard, the placement of the new
buildings was constrained.
B. That the granting of a variance is necessary for the preservation
and enjoyment of one or more substantial property rights.
The granting of the setback variance will preserve the
property owner's ability to develop the property with a
project that will be consistent with the General Commercial
(C-2) zoning district and with a project that is consistent
with the goals and policies of the General Plan. A condition
of approval has been incorporated that will require
additional, enhanced landscaping along MacArthur Boulevard to
mitigate the loss of setback area.
C. That the granting of a variance will not be materially detrimental
to the public welfare or injurious to surrounding property.
The granting of the setback variance will not be detrimental
to the public welfare or injurious to surrounding property.
The proposed buildings will be buffered by landscaping and
outdoor plaza area and will allow the buildings to be placed
at the rear of the site, thereby reducing the impact to the
adjacent residential uses.
EXHIBIT 9
75B-23
Variance No. 2008-03
March 24, 2008
Page 2 of 2
D. That the granting of a variance will not adversely affect the
General Plan of the City.
The granting of the variance will not adversely affect the
General Plan of the City as retail uses are permitted in the
General Commercial (GC) General Plan land use designation.
Further, the proposed building is consistent with Goals 1, 2
and 3 of the General Plan Land Use Element, which encourage
the City to promote a balance of land uses to address basic
community needs, promote uses that enhance the City's economic
and fiscal viability and improve the character and integrity
of existing neighborhoods.
75B-24
MARCH 24, 2008
PAGE 1 OF 1
Conditions of Approval
Variance No. 2008-03 is approved subject to compliance, to the reasonable
satisfaction of the Planning Manager, with applicable sections of the
Santa Ana Municipal Code, the California Administrative Code, the
California Standards Building Code, and all other applicable regulations.
In addition, it shall meet the following conditions of approval:
The applicant must comply with each and every condition listed below prior
to exercising the rights conferred by this variance.
The applicant must remain in compliance with all conditions listed below
throughout the life of the development project. Failure to comply with
each and every condition may result in the revocation of the variance.
A. Planning Division
1. All proposed site improvements must conform with the Site Plan
Review approval of DP No. 07-19 and the staff report exhibits.
2. Any amendment to this variance must be submitted to the
Planning Division for review. At that time, staff will
determine if administrative relief is available or the
variance must be amended.
3. Prior to issuance of any building permit, a voluntary lot
merger to combine the lots into one parcel shall be recorded.
4. Landscaping along the south property line shall be upgraded to
36-inch box trees.
5. Prior to submittal into building plan check, revise the plans
to show decorative paving will be installed at all project
driveway entries.
B. Police Department
1. Prior to issuance of any building permit, submit a conceptual
lighting plan for the parking lot. Light standards cannot be
located in landscaped areas to avoid conflict with the canopy
growth of trees.
2. The existing parking lot and structures must conform to the
provision of the Building Security Ordinance, including
lighting, doors and window locking devices, and addressing.
~~~
c
MAYOR
Miguel A. Pulido
MAYOR PRO TEM
Carlos Bustamante
COUNCILMEMBERS
Claudia C. Alvarez
P. David Benavides
Michele Martinez
Vincent F. Sarmiento
Sal Tinajero
CITY OF SANTA ANA
PLANNING & BUILDING AGENCY
20 Civic Center Plaza (M-20)
P.O. Box 1988 • Santa Ana, California 92702
(714) 667-2700 . Fax (714) 973-1461
www.santa-ana.org
CITY MANAGER
David N.- Reim
- _ "C~ ATTORNEY
Joseph W. Fletcher
CLERK OF THE COUNCIL
Patricia E. Healy
NOTICE OF INTENT
TO ADOPT A MITIGATED NEGATIVE DECLARATION
This is to inform the general public that the City of Santa Ana proposes to adopt a
Negative Declaration for the following project:
Project Title: Gateway Plaza Retail Center
Project Description: The proposed project consists of the construction of two new retail
buildings totaling 10,400 square feet with related parking and landscape. The buildings
replace a car wash that was previously demolished and will be an addition to an existing
12,900 square foot retail center.
Project Location: 1501 West MacArthur Boulevard
Project Number: AA No. 2008-02, GPA No. 2008-01, Variance No. 2008-03 and
ER No. 2007-73
Public Review Period: March 10, 2008 to March 30, 2008
Hearing Date: April 7, 2008
Hearing Location: City of Santa Ana Council Chambers, 22 Civic Center Plaza
Santa Ana, CA 92702
The Mitigated Negative Declaration and Initial Study as well as all referenced documents
will be available for public review at the City of Santa Ana Planning and Building Agency
located at 20 Civic Center Plaza, Santa Ana, California. Please submit any comments on
the Negative Declaration to the City on or before March 30, 2008. Please direct your
comments to: Vince Fregoso, Principal Planner, City of Santa Ana, P.O. Box 1988, M-20,
Santa Ana, CA, 92702.
If you have any questions or would like any additional information, please contact Vince
Fregoso at (714) 667-2713.
~~
MAYOR
Miguel A. Pulido
MAYOR PRO TEM
Carlos Bustamante
COUNCILMEMBERS
Claudia C. Alvarez
P. David Benavides
Michele Martinez
Vincent F. Sarmiento
Sal Tinajero
CITY OF SANTA ANA
PLANNING & BUILDING AGENCY
20 Civic Center Plaza (M-20)
P.O. Box 1988 • Santa Ana, California 92702
(714) 667-2700 • Fax (714) 973-1461
www.santa-ana.org
MITIGATED NEGATIVE DECLARATION
CITY MANAGER
David N. Ream
CITY ATTORNEY
Joseph W. Fletcher
CLERK OF THE COUNCIL
Patricia E. Healy
Pursuant to the Procedures of the City of Santa Ana for implementation of the California
Environmental Quality Act, the Environmental Evaluator has completed an Initial Study
for the project described below:
Project Number: Amendment Application (AA) No. 2008-02, General Plan
Amendment (GPA) No. 2008-01, Variance No. 2008-03 &
Environmental Review No. 2007-73
Applicant: MHI Real Company
1601 Dove Street, Suite 145, Newport Beach, CA 92660
Project Location /Address: 1501 West MacArthur Boulevard
Project Title /Description: The proposed project consists of the construction of
two new retail buildings within an existing retail center. The first building will be a one-
story, 6,146 square foot structure that will be located immediately west of the existing
retail building. The second building will be approximately 4,200 square feet in size and
will be located at the corner of MacArthur Boulevard and Plaza Drive. This building is
planned for restaurant and similar food related uses and will incorporate an outdoor
dining amenity into its design.
And does hereby find:
That although the proposed project could have a significant effect on the
environment, there will not be a significant effect in this case because of revisions
to the project and mitigation measures paced on the project, and agreed to by the
applicant, reduce each impact to below a level of significance.
~ 3 ~.~
Signature. Date: 7
Principal Plann
This determination is not final until adopted by the decision-making body or
administrative official, and a Notice of Determination is filed.
75~3~~
Environmental Checklist
CEQA Compliance
PLANNING DIVISION
Project Title: Gateway Plaza
Project Numbers: AA 2008-02, GPA 2008-01, VA 2008-03 and ER 2007-73
III. Lead Agency Name and Address: City of Santa Ana
Planning Division (M-20)
P.O. Box 1988, Santa Ana, CA 92702
IV. Contact and Phone Number: Vince Fregoso (714) 667-2713
V. Project Location: 1501 West MacArthur Boulevard
VI. Project Sponsor's Name and Address:
Larry Smith, MHI Real Company, 1601 Dove Street, Suite 145, Newport Beach, CA 92660
VII. General Plan Designation:
Medium Density Residential (MR)
VIII. Zoning:
Two-Family Residential (R-2)
IX. Description of Project:
The proposed project consists of the construction of two new retail buildings within an existing retail center.
The first building will be a one-story, 6,146 square foot structure that will be located immediately west of
the existing retail building. The second building will be approximately 4,200 square feet in size and will
be located at the corner of MacArthur Boulevard and Plaza Drive. This building is planned for restaurant
and similar food related uses and will incorporate an outdoor dining amenity into its design. The existing
retail building will also be remodeled to match the architectural design of the two new buildings. A
contemporary design theme has been proposed by the developer, with elements such as stacked stone
veneer, metal awnings and standing seam metal roofing to be utilized throughout the project. Site
improvements include decorative paving at the vehicle driveways and pedestrian pathways, restriping
and reslurrying of the parking lot, and the replacement of missing plant materials and the installation of
new landscape planters. The project will provide 160 parking spaces and meet the landscape standards for
the zone. As the project currently has residential general plan and zoning designations, a general plan
amendment and zone change to commercial is proposed. Additionally, a variance to allow a reduction in
the front yard setback is requested.
X. Surrounding Land Uses and Setting:
The project site is a partially developed, rectangular shaped parcel located on the northeast corner of
MacArthur Boulevard and Plaza Drive. Vehicular access to the site is from both MacArthur Boulevard
and Plaza Drive, with MacArthur Boulevard listed as major arterial streets in the Circulation Element of
the City's General Plan. The surrounding land uses include residential to the north and west, and
commercial to the south and east.
XI. Other agencies whose approval is required.
No approval is required from outside agencies.
LL\M:\WP51\MISC\Gateway Plaza IS.doc R R Page 1 of 2
75~ 3i~~+
Environmental Checklist
CEQA Compliance
Environmental Factors Potentially Affected:
The environmental factors checked below would be potentially affected by that project, involving at least one
impact that is a "Potentially Significant Impact" as indicated by the checklist on the following pages.
O Aesthetics
O Agricultural Resources
O Air Quality
O Biological Resources
O Cultural Resources
O Geology and Soils
O Hazards and Hazardous Materials
O Hydrology and Water Quality
O Land Use and Planning
Environmental Determination
On the basis of this initial evaluation, I find that:
O Mineral Resources
O Noise
O Population and Housing
O Public Services
O Recreation
O Transportation and Traffic
O Utilities and Service Systems
O Mandatory Findings of Significance
A. ^ The proposed project COULD NOT have a significant effect on the environment and a NEGATIVE
DECLARATION will be prepared.
B. ® Although the proposed project could have a significant effect on the environment, there will not be a significant
effect in this case because revisions to the project have been made by or agreed to by the applicant. A
MITIGATED NEGATIVE DECLARATION will be prepared.
C. ^ The proposed project MAY have a significant effect on the environment and an ENVIRONMENTAL IMPACT
REPORT is required.
D. ^ Although the proposed project could have a significant effect on the environment, because all potentially
significant effects (a) have been analyzed adequately in an earlier EIR (EIR No. -)pursuant to applicable
standards and (b) have been avoided or mitigated pursuant to that earlier EIR, including revisions or mitigation
measures that are imposed upon the project, nothing further is required.
E. ^ Pursuant to Section 15164 of the CEQA Guidelines, an EIR (EIR No. -)has been prepared earlier and only
minor technical changes or additions are necessary to make the previous EIR adequate and these changes do
not raise important new issues about the significant effects on the environment. An ADDENDUM to the EIR
shall be prepared.
F. ^ Pursuant to Section 15162 of the CEQA Guidelines, an EIR (EIR No. -)has been prepared earlier; however,
subsequent proposed changes in the project and/or new information of substantial importance will cause one
or more significant effects no previously discussed. A SUBSEQUENT EIR shall be prepared.
`~ C 3 ~ ~~'
Sig ature Date
Vince Fregoso. Principal Planner
Printed Name
LL\M:\WP51\MISC\Gateway Plaza IS.doc ~ ~~ 3~ ~ Page 2 of 2
Environmental Checklist
CEQA Compliance
Evaluation of Environmental Impacts:
I. A brief explanation is required for all answers except "No Impact" answers that are adequately supported
by the information sources a lead agency cites in the parentheses following each question. A "No
Impact" answer is adequately supported if the referenced information sources show that the impact
simply does not apply to projects like the one involved (e.g., the project falls outside a fault rupture zone).
A "No Impact" answer should be explained where it is based on project-specific factors as well as general
standards (e.g., the project will not expose sensitive receptors to pollutants, based on aproject-specific
screening analysis).
II. All answers must take account of the whole action involved, including off-site as well as on-site,
cumulative as well as project-level, indirect as well as direct, and construction as well as operational
impacts.
III. "Potentially Significant Impact" is appropriate if there is substantial evidence that an effect is significant. If
there are one or more "Potentially Significant Impact" entries when the determination is made, an EIR is
required.
IV. "Less than Significant with Mitigation Incorporated" applies where the incorporation of mitigation
measures has reduced an effect from "Potentially Significant Impact" to a "Less than Significant Impact."
The lead agency must describe the mitigation measures, and briefly explain how they reduce the effect to
a less than significant level.
Issues & Supporting Information Sources
I. Aesthetics -Would the project:
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Impact Incorporated Impact Impact
A. Have a substantial adverse effect on a scenic vista? ^ ^ ^
B. Damage scenic resources, including but not limited ^ ^ ^
to, trees, rock outpourings and historic buildings
within a state highway?
C. Substantially degrade the existing visual character
or quality of the site and its surroundings? ^ ^ ^
D. Create a new source of substantial light or glare
which would adversely affect day or nighttime views
in the area? ^ ^ ® ^
75~~~0
Environmental Checklist
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues & Supporting Information Sources Impact Incorporated Impact Impact
II. Agricultural Resources - In determining whether impacts to agricultural resources are significant
environmental effects, lead agencies may refer to the California Agricultural Land Evaluation and Site
Assessment Model prepared by the California Department of Conservation as an optional model to use in
assessing impacts on agricultural farmland. Would the project:
A. Convert Prime Farmland, Unique Farmland or ^ ^ ^
Farmland of Statewide Importance (Farmland) to
non-agricultural use? (The Farmland Mapping and
Monitoring Program in the California Resources
Agency, Department of Conservation, maintains
detailed maps of these and other categories of
farmland.)
B. Conflict with existing zoning for agricultural use or a ^ ^ ^
Williamson Contract?
C. Involve other changes in the existing environment ^ ^ ^
which, due to their location or nature, could
individually or cumulatively result in loss of
Farmland, to non-agricultural use?
III. Air Quality -Where available, the significant criteria established by the applicable air quality management or
pollution control district may be relied upon to make the following determinations. Would the project:
A. Conflict with or obstruct implementation of ^ ^ ^
applicable Air Quality Attainment Plan or
Congestion Management Plan?
B. Violate any stationary source air quality standard or ^ ^ ® ^
contribute to an existing or proposed air quality
violation?
C. Result in a cumulatively considerable net increase ^ ^ ® ^
of any criteria pollutant for which the project region
is non-attainment under an applicable federal or
state ambient air quality standard (including
releasing emission which exceeds quantitative
thresholds for ozone precursors)?
D. Expose sensitive receptors to substantial pollutant ^ ^ ® ^
concentrations?
75~~~ 1
~ i
" '~~ Environmental Checklist
1 !
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues 8~ Supporting Information Sources Impact Incorporated Impact Impact
E. Create objectionable odors affecting a substantial ^ ^ ^
number of people?
IV. Biological Resources -Would the project:
A. Have a substantial adverse impact, either directly ^ ^ ^
or through habitat modifications, on any species
identified as a candidate, sensitive or special
status species in local or regional plans, policies or
regulations or by the California Department of Fish
and Game or U.S. Fish and Wildlife Services?
B. Have a substantial adverse impact on any riparian ^ ^ ^
habitat or natural community identified in local or
regional plans, policies, and regulations or by the
California Department of fish and Game or U.S.
Fish and Wildlife Service?
C. Adversely impact federally protected wetlands ^ ^ ^
(including, but not limited to, marsh, vernal pool,
coastal, etc.) either individually or in combination
with the known or probable impacts of other
activities through direct removal, filling hydrological
interruption, or other means?
D. Conflict with any local policies or ordinances ^ ^ ^
protecting biological resources, such as tree
preservation policy or ordinance?
V. Cultural Resources -Would the project:
A. Cause a substantial adverse change in the ^ ^ ^
significance of a historical resource as defined in
Section 15064.5?
B. Cause a substantial adverse change in the ^ ^ ^
significance of a unique archaeological resource
pursuant to define Section 15064.5?
C. Directly or indirectly disturb or destroy a unique ^ ^ ^
paleontological resource or site?
75~r~32
i i
" '~~ Environmental Checklist
,~
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues 8~ Supporting Information Sources Impact Incorporated Impact Impact
D. Disturb any human remains, including those ^ ^ ^
interred outside of formal cemeteries?
VI. Geology and Soits -Would the project:
A. Expose people or structures to potential
substantial adverse effects, including the risk of
loss, injury, or death involving:
1. Rupture of a known earthquake fault, as ^ ^ ^
delineated on the most recent Alquist-Priolo
Earthquake Fault Zoning map issued by the
State Geologist for the area or based on other
substantial evidence of a known fault?
2. Strong seismic ground shaking? ^ ^ ® ^
3. Seismic-related ground failure, including ^ ^ ® ^
liquefaction?
4. Landslides? ^ ^ ^
B. Would the project result in substantial soil erosion ^ ® ^ ^
or the loss of topsoil?
C. Would the project result in the loss of a unique ^ ^ ^
geologic feature?
D. Is the project located on strata or soil that is ^ ^ ® ^
unstable or that would become unstable as a result
of the project and potentially result in on- or off-site
landslide, lateral spreading, subsidence,
liquefaction, or collapse?
E. Where sewers are not available for the disposal of ^ ^ ^
wastewater, is the soil capable of supporting the
use of septic tanks or alternative wastewater
disposal systems?
75~~~3
Environmental Checklist
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues & Supporting Information Sources Impact Incorporated Impact Impact
VII. Hazardous and Hazardous Materials -Would the project:
A. Create a significant hazard to the public or the ^ ^ ^
environment through the routine transport, use or
disposal of hazardous materials?
B. Emit hazardous emissions or handle hazardous or ^ ^ ^
acutely hazardous materials, substance or waste
within one-quarter mile of an existing or proposed
school?
C. Be located on a site which is located on a list of ^ ^ ^
hazardous materials sites compiled pursuant to
Government Code Section 659662.5 and, as a
result, would it create a significant hazard to the
public or the environment?
D. For a project located within an airport land use ^ ^ ^
plan or where such a plan has not been adopted,
within two miles where of a public airport or public
use airport, would the project result in a safety
hazard for people residing or working in the project
area?
VIII. Hydrology and Water Quality -Would the project:
A. Violate Regional Water Quality Control Board ^ ® ^ ^
water quality standards or waste discharge
requirements?
B. Substantially deplete groundwater supplies or ^ ^ ^
interfere substantially with groundwater recharge
such that there would be a net deficit in aquifer
volume or a lowering of the local groundwater table
level (i.e., the production rate of pre-existing
nearby wells would drop to a level which would not
support existing land uses or planned uses for
which permits have been granted)?
C. Substantially alter the existing drainage pattern of ^ ^ ® ^
the site or area, including through the alteration of
the course of stream or river, or substantially
increase the rate or amount of surface runoff in a
manner which would result in flooding on or off-
site?
75~3~4
Environmental Checklist
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues 8~ Supporting Information Sources Impact Incorporated Impact Impact
D. Create or contribute runoff water which would ^ ^ ® ^
exceed the capacity of existing or planned storm
water drainage systems or provide substantial
additional sources of polluted run-off?
E. Otherwise substantially degrade water quality? ^ ® ^ ^
F. Place housing within a 100-year floodplain, as ^ ^ ^
mapped on a federal Flood Hazard Boundary or
Flood Insurance Rate Map or other flood hazard
delineation map?
G. Place within a 100-year floodplain structures which ^ ^ ^
would impede or redirect flood flows?
H. Expose people or structures to a significant risk of ^ ^ ^
loss, injury, or death involving flooding, including
flooding as a result of the failure of a levee or dam.
I. Result in an increase in pollutant discharges to ^ ® ^ ^
receiving waters? Consider water quality
parameters such as temperature, dissolved
oxygen, turbidity and other typical storm water
pollutants (e.g. heavy metals, pathogens,
petroleum derivatives, synthetic organics,
sediment, nutrients, oxygen-demanding
substances, and trash)
J. Result in significant alteration of receiving water ^ ® ^ ^
quality during or following construction?
K. Could the proposed project result in increased ^ ® ^ ^
erosion downstream?
L. Result in increased impervious surfaces and ^ ® ^ ^
associated increased runoff?
M. Create a significant adverse environmental impact ^ ® ^ ^
to drainage patterns due to changes in runoff flow
rates or volumes?
N. Tributary to an already impaired water body, as ^ ® ^ ^
listed on the Clean Water Act Section 303(d) list: If
so, can it result in an increase in any pollutant of
which the water body is already impaired?
75,~~5
Environmental Checklist
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues 8~ Supporting Information Sources Impact Incorporated Impact Impact
O. Tributary to other environmentally sensitive areas? ^ ® ^ ^
If so, can it exacerbate already existing sensitive
conditions?
P. Have a potentially significant environmental impact ^ ® ^ ^
on surface water quality to either marine, fresh, or
wetland waters?
Q. Have a potentially significant adverse impact on ^ ® ^ ^
groundwater quality?
R. Cause or contribute to an exceedance of ^ ® ^ ^
applicable surface or groundwater receiving water
quality objectives or degradation of beneficial
uses?
S. Impact aquatic, wetland, or riparian habitat? ^ ® ^ ^
IX. Land Use and Planning -Would the project:
A. Physically divide an established community? ^ ^ ^
B. Conflict with any applicable land use plan, policy, ^ ^ ^
or regulation of an agency with jurisdiction over the
project (including, but not limited to the general
plan, specific plan, local coastal program, or zoning
ordinance) adopted for the purpose of avoiding or
mitigating an environmental effect?
C. Conflict with any applicable habitat conservation ^ ^ ^
plan or natural community conservation plan?
X. Mineral Resources -Would the project:
A. Result in the loss of availability of a locally- ^ ^ ^
important mineral resource recovery site
delineated on a local general plan, specific plan, or
other land use plan?
75,6
Environmental Checklist
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues & Supporting Information Sources Impact Incorporated Impact Impact
XI Noise -Would the project result in:
A. Exposure of persons to or generation of noise ^ ^ ® ^
levels in excess of standards established in the
local general plan or noise ordinance, or applicable
standards of other agencies?
B. Exposure of persons to or generation of excessive ^ ^ ® ^
groundborne vibration or groundborne noise
levels?
C. A substantial permanent increase in ambient noise ^ ^ ® ^
levels in the project vicinity above levels existing
without the project?
D. A substantial temporary or periodic increase in ^ ^ ® ^
ambient noise levels in the project vicinity above
levels existing without project?
E. For a project located within an airport land use ^ ^ ^
plan or where such a plan has not been adopted,
within two miles of a public airport or public use
airport, would the project expose people residing or
working in the project area to excessive noise
levels?
XII. Population and Housing -Would the project:
A. Induce substantial population growth in an area, ^ ^ ^
either directly (for example, by proposing new
homes and business) or indirectly (for example,
through extension of roads or other infrastructure)?
B. Displace substantial numbers of existing housing, ^ ^ ^
necessitating the construction of replacement
housing elsewhere?
C. Displace substantial numbers of people, ^ ^ ^
necessitating the construction of replacement
housing elsewhere?
75-~7
L i
" '~ Environmental Checklist
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues & Supporting Information Sources Impact Incorporated Impact Impact
XIII. Public Services
A. Would the project result in substantial adverse
physical impacts associated with the provision of
new or physically altered governmental facilities,
need for new or physically altered governmental
facilities, the construction of which could cause
significant environmental impacts, in order to
maintain acceptable service rations, response
times or other performance objectives for any of
the public service:
1. Fire protection? ^ ^ ® ^
2. Police protection? ^ ® ^ ^
3. Schools? ^ ^ ^
4. Parks? ^ ^ ^
5. Other public facilities? ^ ^ ^
XIV. Recreation
A. Would the project increase the use of existing ^
neighborhood and regional parks or other
recreational facilities such that substantial physical
deterioration of the facility would occur or be
accelerated?
B. Does the project include recreational facilities or ^
require the construction or expansion of
recreational facilities which might have an adverse
physical effect on the environment?
^ ^
^ ^
XV. Transportation /Traffic
A. Cause an increase in traffic which is substantial in ^
relation to the existing traffic load and capacity of
the street system (i.e., result in a substantial
increase in either the number of vehicle trips, the
volume to capacity ration on roads, or congestion
at intersections)?
® ^
751°8
t i
"'~~ Environmental Checklist
i j
CEQA Compliance
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues & Supporting Information Sources Impact Incorporated Impact Impact
B. Exceed, either individually or cumulatively, a level ^ ^ ^
of service standard established by the county
congestion management agency for designated
roads or highways?
C. Result in a change in air traffic patterns, including ^ ^ ^
either an increase in traffic levels or a change in
location that results in substantial safety risks?
D. Substantially increase hazards to a design feature ^ ^ ^
(e.g., sharp curves or dangerous intersections) or
incompatible uses (e.g., farm equipment)?
E. Result in inadequate emergency access? ^ ^ ^
F. Result in inadequate parking capacity? ^ ^ ^
G. Conflict with adopted policies supporting ^ ^ ^
alternative transportation (e.g., bus turnouts,
bicycle racks)?
XVI. Utilities and Service Systems
A. Exceed wastewater treatment requirements of the ^ ^ ^
applicable Regional Water Quality Control Board?
B. Require or result in the construction of new water ^ ^ ^
or wastewater treatment facilities or expansion of
existing facilities, the construction of which could
cause significant environmental effects?
C. Require or result in the construction of new storm ^ ^ ^
water drainage facilities or expansion of existing
facilities, the construction of which could cause
significant environmental effects?
D. Are sufficient water supplies available to serve the ^ ^ ^
project from existing entitlements and resources or
are new or expanded entitlements needed?
75~~~9
Environmental Checklist
CEQA Compliance
E. Result in the determination by the wastewater
treatment provider which serves or may serve the
project that it has adequate capacity to serve the
project's projected demand in addition to the
provider's existing commitments?
Less than
Significant
Potentially with Less Than
Significant Mitigation Significant No
Issues & Supporting Information Sources Impact Incorporated Impact Impact
F. Is the project served by a landfill with sufficient ^ ^ ® ^
permitted capacity to accommodate the project's
solid waste disposal needs?
G. Comply with federal, state and local statutes and ^ ^ ® ^
regulations related to solid waste?
XVII. Mandatory Findings of Significance
A. Does the project have the potential to degrade the ^ ^ ^
quality of the environment, substantially reduce the
habitat of a fish or wildlife species, cause a fish or
wildlife population to drop below self-sustaining
levels, threaten to eliminate a plant or animal
community, reduce the number or restrict the
range of a rare or endangered plant or animal or
eliminate important examples of the major periods
of California history or prehistory?
B. Does the project have impacts that are individually ^ ^ ^
limited but cumulatively considerable?
("Cumulatively considerable" means that the
incremental effects of a project are considerable
when viewed in connection with the effects of past
projects, effects of other current projects and the
effects of probable future projects.)
C. Does the project have environmental effects which ^
will cause substantial adverse effects on human
beings, either directly or indirectly?
^ ^
75,0
Responses to
Environmental Checklist
For CEQA Compliance
The following is an analysis of potential environmental impacts associated with the proposed project
based upon the City of Santa Ana Environmental Checklist. The analysis incorporates by reference
information from the environmental impact report for the Santa Ana General Plan Land Use Element (EIR
No. 97-1 ).
1. Aesthetics-
A. Have a substantial adverse effect on a scenic vista?
B. Damage scenic resources, including but not limited to trees, rock outpourings and historic
buildings within a State highway?
No Impact
According to the City's General Plan Land Use Element FEIR, there are no scenic vistas within the
immediate vicinity of the project site. The Orange Freeway (SR-57), Newport Freeway (SR-55), and
Garden Grove Freeway (SR-22) are the three state highways that can be found in the City of Santa Ana.
The proposed project site is not visible from any of those highways and therefore will not damage or
destroy any scenic resources that are located within the vicinity of these highways.
C. Substantially degrade the existing visual character or quality of the site and its
surrounding?
D. Create a new source of substantial light or glare, which would adversely affect day or
nighttime views in the area?
Less than significant impact
The proposed project will not degrade the visual quality of the site, with impacts anticipated to be
beneficial, not adverse. The project replaces a carwash development with better materials. Major
sources of light and glare in the project area include light from street and parking lot lights, illuminated
signage, headlights from vehicles, security lighting, and indoor lighting. The proposed project will not
introduce substantial new lighting which will be discernable over existing conditions.
II. Agricultural Resources
A. Convert Prime Farmland, Unique Farmland or Farmland of Statewide Importance to non-
agriculture use?
B. Conflict with existing zoning for agriculture use or a Williamson Contract?
C. Involve other changes in the existing environment, which, due to their location or nature,
could individually or cumulatively result in loss of Farmland, to non-agriculture use?
No Impact
Although a portion of the site is vacant, the proposed project will replace a former urban development
(carwash) on the site, which is not in agricultural production. Additionally, according to the California
Department of Conservation Farmland Mapping and Monitoring Program, the City of Santa Ana contains
a limited amount of Prime and Unique Farmlands. Presently, there are no areas in the City that are under
existing Williamson Contracts. Therefore the proposed project will not result in any adverse impacts to
agricultural resources.
751~3t~1
Responses to
Environmental Checklist
For CEQA Compliance
III. Air Quality
A. Conflict with or obstruct implementation of applicable Air Quality Attainment Plan or
congestion Management Plan?
No Impact
The City of Santa Ana is included within the South Coast Air Quality Management District and subject to
the requirements of the Clean Air Act at both the Federal and State level. The South Coast Air Quality
Management Plan (AQMP) is the primary planning document to monitor if air quality standards and
objectives are being achieved in the South Coast Air Basin. The air quality objectives in the AQMP are
based upon population and growth projections provided in the General Plan. A project could be in conflict
with the AQMP if it results in population and growth impacts beyond those identified in the City's General
Plan. The proposed commercial project will not impact the growth projections in the General Plan.
Therefore, approval of the proposed general plan amendment and amendment application would not be
in conflict with the South Coast AQMP.
B. Violate any stationary source air quality standard or contribute to an existing or proposed
air quality violation?
C. Result in a cumulatively considerable net increase of any criteria pollutant for which the
project region is non-attainment under an applicable federal or state ambient air quality
standard?
D. Expose sensitive receptors to substantial pollutant concentrations?
E. Create objectionable odors affecting a substantial number of people?
Less than significant impact
As mentioned previously, the South Coast Air Quality Management District (SCAQMD) regulates air
quality in the South Coast Air Basin. The South Coast Air Basin is currently anon-attainment area for
carbon monoxide, ozone, and particulate matter. The SCAQMD considers an air quality impact to be
significant if it exceeds the thresholds identified below.
EMISSION THRESHOLDS OF SIGNIFICANCE
Project
Pollutant Construction Tonsl Operations
PoundslDa Quarter Pounds/Da
Carbon Monoxide 550 24.75 550
Reactive Organic
Com ounds 75 2.5 55
Nitro en Oxides 100 2.5 55
Particulate Matter
150 6.75 150
Long-Term Operational Air Quality Impacts
The primary source of long-term operational emissions associated with the proposed project would be
generated by vehicle travel to and from the project site. A relatively minor amount of gaseous emissions
would also occur from natural gas and electricity usage. The proposed project is consistent with the
City's General Plan and would not exceed the air pollutant emission projections established in the
General Plan Land Use Element EIR.
7aE~~2
Responses to
Environmental Checklist
For CEQA Compliance
ort-term onstructe Relate Air uality Impacts
Construction operations associated with the proposed project could potentially result in short-term
increases in particulate matter, and to a lesser degree increases in carbon monoxide and ozone. Peak
day construction emissions for most pollutants arising from construction of the proposed project would
occur during the grading and demolition phases.
Using the South Coast Air Quality Management District CEQA Air Quality Handbook as a general
guideline, the threshold for potentially significant short-term air quality impacts would involve the grading
of 1,309,000 square feet of area and the demolition of 23,214,000 cubic feet of building area. The
proposed project would require no demolition and re-grading of 43,465 square feet of lot area only. The
amount of grading and demolishing activities for the proposed project would be considerably less than the
threshold of significance outlined in the CEQA Air Quality Handbook. While the construction related
emissions associated with the proposed project would not exceed the thresholds established by the
SCAQMD, the emissions could be a nuisance to other existing land uses in the nearby vicinity of the
project site. To minimize short-term construction related to air impacts within the project area, the
following project enhancement measure shall be implemented.
Project Enhancement Measure
During construction, the contractor would be required to comply with SCAQMD Fugitive Dust Rule 403 to
suppress dust generated by construction operations. To ensure compliance with SCAQMD Fugitive Dust
Rule 403, grading plans and demolition plans for the proposed project shall reflect the following notes:
All material excavated or graded will be sufficiently watered to prevent excessive
amounts of dust.
2. All clearing and earthwork activities shall cease during period of high winds (winds
greater than 25 mph averaged over one hour) or during Stage 1 or Stage 2 smog
episodes.
3. Streets surrounding the project site shall be cleaned at the end of each day of
construction.
4. All material transported offsite shall either be sufficiently watered or securely covered to
prevent excessive amounts of dust.
5. The amount of area disturbed by clearing and earthwork activities shall be minimized at
all times.
6. Equipment engines shall be maintained in good condition and in proper tune according to
manufacturer's specifications.
7. To the extent feasible, gasoline powered equipment shall be used for onsite and offsite
construction activities.
In addition, it has been determined that implementation of the proposed project would not result
significant long-term or short-term air quality impacts. Therefore, the proposed project area would not be
exposed to substantial concentrations of air quality pollutants. Finally, the proposed project is a retail
land use and would not generate significant long-term operational odors. Construction equipment and
operations associated with the proposed project could potentially result in odor impacts. However, the
odors would be short-term and would not be considered significant.
75~~>~3
Responses to
Environmental Checklist
For CEQA Compliance
IV. Biological Resources
A. Have a substantial adverse impact, either directly or through habitat modifications, on any
species identified as a candidate, sensitive or special status species in local or regional
plans, policies or regulations or by the California Department of Fish and game or U.S.
Fish and Wildlife Services?
B. Have a substantial adverse impact on any riparian habitat or natural community identified
in local or regional plans, policies, and regulations or by the California Department of Fish
and Game or U.S. Fish and Wildlife Service?
C. Adversely impact federally protected wetlands either individually or in combination with
the known or probable impacts of other activities through direct removal, filling
hydrological interruption, or other means?
D. Conflict with any local policies or ordinances protecting biological resources, such as tree
preservation policy or ordinance?
No Impact
The City of Santa Ana General Plan Land Use Element EIR indicates that Santa Ana is predominantly
built-out and that all sizable expanses of undisturbed native vegetation have been eliminated. Approval
and implementation of the proposed project will not result in impacts to any on-site biological resource.
V. Cultural Resources
A. Cause a substantial adverse change in the significance of a historical resource as defined
in Section 15064.5?
No Impact
According to the National Register of Historical Structures and the City of Santa Ana Local List of
Historical Properties, there are no historical structures located on the project site. Therefore,
implementation of the proposed project would not result in significant impacts to any historic resource.
B. Cause a substantial adverse change in the significance of a unique archaeological
resource pursuant to Section 15064.5?
C. Directly or indirectly disturb or destroy a unique paleontogical resource or site?
D. Disturb any human remains, including those interred outside of formal cemeteries.
No Impact
According to the City's General Plan Land Use Element EIR, there are no known or recorded
archaeological or paleontological resources on or within the vicinity of the project site. Additionally, the
project site is partially developed and vacant. The probability for the discovery of unknown cultural
resources would be low. Therefore, implementation of the proposed project would not result in impacts to
unknown cultural resources.
754
Responses to
Environmental Checklist
For CEQA Compliance
VI. Geology and Soils
A-1. Rupture of a known earthquake fault, as delineated on the most recent Alquist-Priolo
earthquake Fault Zoning Map issued by the State geologist for the area or based on other
substantial evidence of a known fault?
No Impact
According to the City's General Plan Land Use Element EIR, the project site is not located within a
current Alquist-Priolo Earthquake Fault Zone. Therefore, the potential for surface rupture due to faulting
occurring beneath the site during the design life of the proposed project would be considered low.
A-2. Strong Seismic Ground shaking?
Less Than Significant Impact
The project site is situated within a highly active seismic region of Southern California. A total of 38
active faults have been identified within an approximate 60-mile radius of the project site. The
Newport/Inglewood Fault located approximately 13 miles south from the City of Santa Ana is considered
to be one of the most dominant faults in regard to potential seismic shaking impacts. The project site
could potentially be subject to a maximum credible horizontal ground acceleration of 0.30g from a
magnitude 6.9 earthquake along the Newport/Inglewood fault zone. A seismic event of this scale could
potentially result in significant damage to the project site. However, the risks at the project site are similar
to many other areas in the Southern California region. To minimize potential seismic shaking impacts,
the proposed project would be subject to Seismic Safety Standards of the California Standards Building
Code. Compliance with the Code would reduce potential impacts associated with seismic shaking activity
to a level that would be less than significant.
A-3. Seismic-related ground failure, including liquefaction?
Less Than Significant Impact
Soil liquefaction occurs when loose soil deposits below the water table are subject to large ground
accelerations generated from seismic events. According to the City's General Plan Land Use Element
EIR, the project site is located in an area that is characterized with high-very high liquefaction hazard
potential. To minimize potential liquefaction impacts, the proposed project would be subject to Seismic
Shaking Standards of the California Standards Building Code. Compliance with the Code would reduce
potential liquefaction impacts to a level considered less than significant.
A-4. Landslides
No Impact
The project site is flat without any topographical relief. According to the City's General Plan, there are no
landslide planes on the project site. Therefore, implementation of the proposed project would not result in
adverse impacts in regards to landslides.
B. Would the project result in substantial soil erosion or the loss of topsoil?
Less than Significant With Mitigation Incorporated
75~~,~5
Responses to
Environmental Checklist
For CEQA Compliance
rosion re ers to the removal o soi rom exposed be roc su aces y water or win e e ects o
erosion are intensified with an increase in slope, the narrowing of runoff channels and by the removal of
groundcover, which leaves the soil exposed. Construction operations for the proposed project would
require excavation of onsite soils. The uncovered soils on the project site could potentially result in
erosion and sedimentation impacts to onsite and offsite drainage facilities. This potential impact could
increase during periods of rain. To minimize potential erosion impacts, the proposed project would be
required to employ the following Best Management Practices during construction operations.
Mitigation Measure
Prior to the issuance of grading permits, the project developer shall provide proof of coverage
under NPDES General Construction Activity Storm Water Permit that includes: (a) A copy of the
project's permit issued by the State Water Resource Control Board that identifies the permit
number, (b) Two copies of the Storm Water Pollution Prevention Plan.
Submit and have approved a surface drainage/utility plan that depicts all applicable "Site Design"
structural "Source Control° and "Treatment Control" Best Management Practices (BMPs) in
accordance with the Orange County Drainage Area Management Plan (DAMP) and the City of
Santa Ana Local Implementation Plan (LIP).
Submit for approval a surface drainage/grading/erosion control plan. The plan is to include
existing and proposed elevations at and adjacent to all property lines. Drainage routed to the
street must be directed beneath the sidewalk and through the curb.
C. Would the project result in the loss of a unique geological feature?
No Impact
According to the City's General Plan Land Use Element EIR, the project site does not contain any unique
geologic features. Therefore, implementation of the proposed project would not result in adverse impacts
to any unique geologic feature.
D. Is the project located on strata or soil that is unstable or that would become unstable as a
result of the project and potentially result in on-or off-site landslide, lateral spreading,
subsidence, liquefaction or collapse?
Less Than Significant Impact
According the City's General Plan Land Use Element EIR, the project site is located on soils that have
high shrink/swell potential, possible corrosion potential to uncoated steel and low corrosion potential to
concrete. The soil conditions on the project site would not provide a constraint that would prevent the
development of the proposed project. As part of the City's development review process, a geotechnical
study would be prepared to identify geotechnical design recommendations to ensure the long-term
geotechnical stability of the project site.
E. Where sewers are not available for the disposal of wastewater is the soil capable of
supporting the use of septic tanks or alternative wastewater disposal systems?
No Impact
The project site is an improved building site with an improved sewer system. In terms of geological
stability, the project will not require the expansion of additional sewer facilities.
75~3~6 6
Responses to
Environmental Checklist
For CEQA Compliance
VII. Hazards and Hazardous Materials
A. Create a significant hazard to the public or the environment through the routine transport,
use or disposal of hazardous materials?
B. Emit hazardous emissions or handle hazardous or acutely hazardous materials, substance
or waste within one-quarter mile of an existing or proposed school?
C. Be located on a site which is located on a list of hazardous material sites compiles
pursuant to Government Code Section 659662.5 and, as a result, would it create a
significant hazard to the public or the environment?
No Impact
Approval of the proposed retail development would have no impact on transport or disposal of hazardous
material in that the proposed project would not involve activities that would emit hazardous or acutely
hazardous material. Additionally, according to the City of Santa Ana Fire Department and the City's
General Plan, the project site is not included on a list of hazardous material sites. Implementation of the
proposed project would not create a significant hazard to the public or the environment.
D. For a project located within an airport land use plan or where such a plan has not been
adopted, within two miles where a public airport or public use airport, would the project
result in a safety hazard for people residing or working in the project area?
No Impact
According to the City's General Plan Land Use Element EIR and the Orange County Airports Environs
Land Use Plan, Santa Ana is not located within any aircraft accident potential zones, nor is the proposed
project located within a John Wayne Airport Planning Area. Additionally, there are no private airstrips in
the City. Therefore, approval of the proposed project would not increase the potential for safety hazards
for people residing in or working within the City.
VIII. Hydrology and Water Quality
A. Violate Regional Water Quality Control Board water quality standards or waste discharge
requirements?
E. Otherwise substantially degrade water quality?
Resulting an increase in pollutant discharges to receiving waters?
J. Result in significant alteration of receiving water quality during or following construction.
K. Could the proposed project result in increased erosion downstream?
L. Result in increased impervious surfaces and associated runoff?
M. Create a significant adverse environmental impact to drainage patterns due to changes in
runoff flow rates or volumes.
N. Tributary to an already impaired water body, as listed on the Clean Water Act Section
303(d) list. If so, can it result in an increase in any pollutant of which the body is already
impaired?
7~3t~7
Responses to
Environmental Checklist
For CEQA Compliance
O. Tributary to other environmentally sensitive areas? If so, can it exacerbate already existing
sensitive conditions?
P. Have a potentially significant environmental impact or surface water quality to either
marine, fresh or wetland waters?
Q. Have a potentially significant adverse impact on the groundwater quality?
R. Cause or contribute to an exceedance of applicable surface or groundwater receiving
water quality objectives or degradation of beneficial uses?
S. Impact aquatic, wetland or riparian habitat?
Less Than Significant With Mitigation Incorporated
The City of Santa Ana is included within four watersheds, San Diego Creek, Santa Ana River, Talbert and
Westminster. Each of these watershed areas are under the jurisdiction of the Santa Ana Regional Water
Quality Control Board and subject to the objectives, water quality standards and Best Management
Practice requirements established in the Santa Ana River Basin Plan and Orange County Drainage Area
Management Plan. The City of Santa Ana implements the goals, objectives and requirements of the
Basin Plan and Drainage Area Management Plan through the City's Local Implementation Plan.
Storm water flows from the project site would be conveyed to an underground storm drain before
ultimately discharging into Santa Ana River watershed. The Santa Ana Regional Water Quality Control
Board has identified Santa Ana River as impaired by nutrients, sediments, metals and pesticides.
The primary source of potential adverse water quality impacts associated with the construction and
operation of the proposed project would be from nuisance flows. Nuisance flows is defined as runoff that
occurs during periods that are not usually associated with rainfall, and are most commonly produced from
landscapirig irrigation, leaking pipes, and water used to wash off surfaces tributary to the street. Since
nuisance flows usually originates in the street, they commonly contain many common pollutants found in
streets such as oil and grease and sediment. Additionally, surface water runoff generated from the
project site during construction operations could be degraded potentially resulting in adverse water quality
impacts to downstream receiving waters.
Mitigation Measures
• Prior to issuance of grading permits, the project developer shall provide proof of coverage under
NPDES General Construction Activity Storm Water Permit that includes; (a) A copy of the
project's permit issued by the State Water Resource Control Board that identifies the permit
number, (B) Two copies of the Storm Water Pollution Prevention Plan.
• Prior to issuance of grading permits, the project developer shall submit and have approved a
surface drainage/utility plan that depicts all applicable Site Design, Structural Source Control and
Treatment Control Best Management Practices in accordance with the Orange County Drainage
Area Management Plan and the City of Santa Ana Local Implementation Plan.
• Provide two copies of the Water Quality Management Plan that would include the following:
Site Assessment
7~~~8
Responses to
Environmental Checklist
For CEQA Compliance
b. ite design Best Management Practices P
c. Applicable Routine Source Control BMP
Selecting and sizing the Treatment Control BMP
e. Mechanisms by which funding for long-term operation and maintenance of all structural
BMP will be provided
Operation and Maintenance Plan to describe the long-term operation and maintenance
requirements of all applicable structural BMP and to identify the entity in charge of
implementation
• The proposed project would be subject to City of Santa Ana Federal Clean Water Protection
Enterprise Fees.
B. Substantially deplete groundwater supplies or interfere substantially with groundwater
recharge such that there would be a net deficit in aquifer volume or a lowering of the local
groundwater table level.
No Impact
The proposed project would not interfere with ground water recharge because the project area is not
located in an area that is known to recharge the ground water system. Additionally, construction
operations for the proposed project would not encroach onto the underground water basin.
Implementation of the proposed project would not result in significant impacts to any underground water
supplies.
C. Substantially alter the existing drainage pattern of the site or area, including through the
alteration of the course of stream or river, or substantially increase the rate or amount of
surface runoff in a manner, which would result in flooding on or off-site?
D. Create or contribute runoff water which would exceed the capacity of existing or planned
storm water drainage systems or provide substantial additional sources of polluted run-
off?
Less than Significant Impact
The project site is located within an urbanized area with improved drainage facilities. The proposed
project would not introduce additional impervious surfaces unto the project site. There would be no
significant increase in the surface water flows generated from the project site because the site is currently
imperious and the project would just replace similar materials.
F. Place housing within a 100-year floodplain, as mapped on a federal Flood Hazard
Boundary or Flood Insurance Rate Map or other flood hazard delineation map?
G. Place within a 100-year floodplain structures which would impede or redirect flood flows?
H. Place housing within a 100-year floodplain, as mapped on a federal Flood Hazard
Boundary or Flood Insurance Rate Map or other flood hazard delineation map?
No Impact
7~~~~49 9
Responses to
Environmental Checklist
For CEQA Compliance
The City of Santa Ana is a participant in the National Flood Insurance Program {NFIP). Communities
participating in the NFIP must adopt and enforce minimum floodplain management standards, including
identification of flood hazards and flood risks. Participation in the NFIP allows communities to purchase
low cost insurance protection against losses from flooding. The published Flood Insurance Rate Maps
(FIRM) for the project site is included on Community Panel No. 06059C0259H. The project site is located
entirely in Zone X, which is defined as areas beyond the limits of the 100-year flood and 500-year flood.
Implementation of the proposed project would not significantly increase the potential for flood risks.
IX. Land Use and Planning
A. Physically divide an established community?
C. Conflict with any applicable habitat conservation plan or natural community plan?
No Impact
The project site is currently developed with a commercial development oriented towards one arterial
street. The new development will continue the existing development pattern and will not divide existing
neighborhoods. The proposed project is located in an urbanized setting and no locally designated
species or natural communities are known to exist in the project area. The site is not part of any habitat
conservation plan or natural community preservation plan.
B. Conflict with any applicable land use plan, policy, or regulation of an agency with
jurisdiction over the project adopted for the purpose of avoiding or mitigating an
environmental effect?
No impact
The General Plan land use designation and zoning for the site are residential but has been historically
used as commercial. The proposed project includes a general plan amendment and zone change to
allow the properties to be redesignated to be consistent with the existing development as well as allow
retail uses on a major arterial street. The proposed project will continue the existing development pattern
and will not create a conflict with any applicable land use plan, policy or regulations adopted for the
purpose of avoiding or mitigating an environmental effect.
X. Mineral Resources
A. Result in the loss of availability of a locally important mineral resource recovery site
delineated on a local general plan, specific plan or other land use plan?
No Impact
According to the City's Updated General Plan Land Use Element EIR, there are no areas in Santa Ana
that are designated significant Mineral Aggregate Resource Areas. Therefore, implementation of the
proposed project would not result in the loss of any regionally or locally important mineral resource.
XI. Noise
A. Exposure of persons to or generation of noise levels in excess of standards established in
local general plan or noise ordinance, or applicable standards of other agencies.
7~~3~0 10
Responses to
Environmental Checklist
For CEQA Compliance
C. A substantial permanent increase in ambient noise levels in the project vicinity above
levels existing without the project.
Less Than Significant Impact
The project site is subject to noise standards and guidelines in the General Plan Noise Element and
Municipal Code Noise Ordinance. The primary purpose of the City of Santa Ana Noise Element is to
"Prevent significant increases in noise levels in the community and minimize the adverse effects of
currently-existing noise sources." In accordance with the Noise Element, the City has adopted noise
standards and guidelines for land use planning. These guidelines for exterior noise levels are presented
in Table N-1.
Table N-1
Ci Of Santa Ana Land Use Gu idelines For Exterior Noise
Land Use Noise Level dBA CNEL or Ldn
Desirable Maximum Maximum Acce table
Low Densit Residential 55 65
Medium Densit Residential 60 65
Hi h Densit Residential 65 70
Schools 60 70
Commercial, Office 65 75
Industrial 70 75
A significant noise impact would occur if a proposed land uses does not comply with the General Plan
noise standards identified in Table N-1, or when a proposed land use results in an 3dB increase to
existing noise levels when the existing noise level is at least 65 d6 CNEL.
The operation of the proposed project would not significantly increase noise levels within the project site.
A significant increase in noise would be a 3dB increase over existing noise levels. Typically, a 3db
increase in noise levels occurs when existing traffic volumes are doubled. The proposed project would
not double existing traffic volumes within the project area. Therefore, implementation of the proposed
project would not result in a 3db increase to existing noise levels within the project area.
B. Exposure of persons to or generation of excessive groundborne vibration or groundborne
noise levels.
D. A substantial temporary or periodic increase in ambient noise levels in the project vicinity
above levels existing without project.
Less Than Significant Impact
The construction of the proposed project would involve conventional construction equipment resulting in
less than significant ground borne vibration impacts. No mitigation measures are necessary.
Implementation of the proposed project would result in short-term construction related noise impacts.
Short-term noise impacts would result from site preparation, excavation, grading, and other construction
operations. The construction-related short-term noise levels would be higher than the existing or ambient
noise levels in the project area today, but would no longer occur once construction of the project is
complete.
7~~1 tt
Responses to
Environmental Checklist
For CEQA Compliance
T e Municipa ode recognizes that some orms o noise are require or urban eve opment an
maintenance and are difficult to control. Section 18-314(e) exempts noise sources associated with
construction, repair, remodeling, or grading of any real property, provided said activities do not take place
between the hours of 8:00 p.m. and 7:00 a.m. on weekdays, including Saturday, or any time on Sunday
or a federal holiday. Compliance with Noise Ordinance would reduce construction noise impacts to a
level considered less than significant.
E. For a project located within an airport land use plan or where such a plan has not been
adopted, within two miles of a public airport or public use airport, would the project
expose people residing or working in the project area to excessive noise levels?
No impact
There are no public airports in the City of Santa Ana; however, John Wayne International Airport is
located one-mile southwest of city limits. The proposed project is located within atwo-mile radius of the
airport. According to the Santa Ana General Plan Draft Environmental Impact Report, no area of the City
of Santa Ana is within the noise impact area or 65 CNEL of John Wayne International Airport. Therefore,
people residing or working in the project area will not be exposed to excessive noise levels. No impact is
anticipated.
XII. Population and Housing
A. Induce substantial population growth in an area, either directly or indirectly through
extension of roads or other infrastructure.
B. Displace substantial numbers of existing housing, necessitating the construction of
replacement housing elsewhere.
C. Displace substantial numbers of people, necessitating the construction of replacement
housing elsewhere?
No Impact
The proposed project would replace an existing commercial development with another commercial use.
Implementation of the proposed project would not increase the population within the project area or
displace existing households within the project area. The proposed project is consistent with the General
Plan and local and regional growth projections for the project area.
XIII. Public Services
Fire Protection: Less than Significant Impact
The City of Santa Ana Fire Department will provide fire protection and emergency services to the project
site. The City maintains ten fire stations throughout the City. The stations are situated where no location
in the City is outside of an approximate 1.5 radius of a fire station. Additionally, the City maintains a
Mutual Aid Agreement for fire protection services with the neighboring Cities of Fountain Valley, Garden
Grove, Tustin, Irvine and Costa Mesa. According to the City of Santa Ana Insurance Service
Organization, the City has a low fire risk rating.
Fire Station No. 6 is located at the corner of MacArthur Boulevard and Towner Street and is
approximately %2 mile from the project site. According to the Santa Ana Fire Department, implementation
of the proposed project would not increase the demand for fire protection services over current levels of
demand within the project area and that under existing levels of manpower and equipment the Fire
Department would be able to provide an adequate level of service.
7 ° ~2 12
Responses to
Environmental Checklist
For CEQA Compliance
Police Protection: Less than Significant With Mitigation Incorporated
The Santa Ana Police Department would provide police protection services for the proposed project.
According to the Santa Ana Police Department, implementation of the extended hours of operation may
potentially increase the demand for police protection services over current levels of manpower and
equipment. In order to minimize the potential impacts associated with the extended hours of operation, the
Police Department is recommending the following mitigation measures:
Mitigation Measures:
• The existing building and parking lot must conform to the provisions of Chapter 8, Article II,
Division 3 of the Santa Ana Municipal Code (Building Security Ordinance). These code
conditions will require that the existing project's lighting, door/window locking devices and
addressing be upgraded to current code standards. Lighting standards cannot be located in
required landscape planters.
• The applicant shall be responsible for maintaining the premises free of graffiti. All graffiti shall be
removed within 24 hours of occurrence.
Schools, Parks, Other Facilities: No Impact
Implementation of the proposed project would not generate demand for additional school services above
the current conditions, nor would it generate demand for additional park services. No adverse impacts to
schools, parks or other public services would occur.
XIV. Recreation
A. Would the project increase the use of existing neighborhood and regional parks or other
recreational facilities such that substantial physical deterioration of the facility would
occur or be accelerated?
B. Does the project include recreational facilities or require the construction or expansion of
recreational facilities, which might have an adverse physical effect on the environment.
No Impact
Implementation of the proposed project would not generate additional demands on existing recreation
facilities or require the construction of new recreation facilities. No adverse impacts to recreation services
and facilities would occur.
XV. TransportationlTraffic
A. Cause an increase in traffic, which is substantial in relation to the existing traffic load and
capacity of the street system?
Less than Significant Impact with mitigation incorporated
The implementation of the proposed project would increase vehicle trips in the project area in that the
project replaces land zoned for residential uses. According to projected trip generation prepared by the
City of Santa Ana Traffic Division, an additional 2,000 trips may be anticipated from the commercial
development, with only 130 trips in the peak a.m. hour and 120 in the peak p.m. hour. In order to mitigate
the traffic projections for the proposed project, the following mitigation measures are proposed:
7~~~~3 13
Responses to
Environmental Checklist
For CEQA Compliance
Mitigation Measures:
• Provide an irrevocable offer to dedicate eight feet of right-of-way along the project frontage to
allow an ultimate street centerline to property line width of 60 feet.
• Provide a 25 foot by 25 foot dedication for a corner cutoff/handicap ramps at the northeast corner
of MacArthur Boulevard and Plaza Drive.
• Record reciprocal ingress/egress easements between the project site and the properties to the
east.
B. Exceed, either individually or cumulatively, a level of service standard established by the
county congestion management agency for designated roads or highways?
No Impact
The proposed project will not result in an increase in traffic that will affect the level of service standard for
MacArthur Boulevard or Bristol Street, the two arterial streets in the immediate vicinity. No impact is
anticipated.
C. Result in a change in air traffic patterns, including either an increase in traffic levels or a
change in location that results in substantial safety risks?
No Impact
There are no public airports in the City of Santa Ana; however, John Wayne International Airport is
located one-mile southwest of city limits. The proposed project is located within atwo-mile radius of the
airport. The maximum height of the building is 32 feet. No impact is anticipated.
D. Substantially increase hazards to a design feature
No Impact
Through the City's development review process, the City's Public Works Agency has determined that
implementation of the proposed project would not increase traffic hazards within the project area.
E. Result in inadequate emergency access
No Impact
As part of the City's development review process, the proposed project was reviewed by the Police
Department and the Fire Department to ensure adequate emergency access. No adverse emergency
access impacts would be associated with the proposed project.
F. Result in inadequate parking capacity
No Impact
The project's parking requirement, based on the City of Santa Ana parking code is 152 parking stalls.
The project will contain 160 parking stalls; therefore the project complies, and exceeds, the City's parking
requirement.
7 ~ iC ^ 14
Responses to
Environmental Checklist
For CEQA Compliance
G. Conflict with adopted policies supporting alternative transportation
No Impact
The proposed project would not be in conflict with any City policies regarding alternative modes of
transportation. Nor would implementation of the proposed project displace any existing modes of public
transportation provided within the project area.
XVI. Utilities and Service Systems
A. Exceed wastewater treatment requirements of the applicable Regional Water Quality
Control Board?
B. Require or result in the construction of new water or wastewater treatment facilities or
expansion of existing facilities, the construction of which could cause significant
environmental effects?
C. Require or result in the construction of new storm water drainage facilities or expansion
of existing facilities, the construction of which could cause significant environmental
effects?
D. Are sufficient water supplies available to serve the project from existing entitlements and
resources or are new or expanded entitlements needed?
E. Result in the determination by the wastewater treatment provider, which serves or may
serve the project that it has adequate capacity to serve the project's projected demand in
addition to the providers existing commitments.
No Impact
The Orange County Sanitation District (OCSD) regulates wastewater treatment for the City of Santa Ana.
The proposed project will not cause any violation of those standards set forth by the OCSD.
The City of Santa Ana and OCSD would provide wastewater service to the proposed project. The project
area is currently improved with wastewater sewer facilities. Implementation of the project wtluld not
increase wastewater demands in the project area over current condition. The wastewater demands of
the project would be accounted for in the City's Urban Water Management Plan. Additionally,
implementation of the project would not increase the amount of surface water runoff currently generated
from the project site. The project would not require the construction of new drainage facilities.
The City of Santa Ana Water Department would provide domestic water service for the proposed project.
Implementation of the proposed project would not increase water demand within the project area over the
current condition. The proposed project is consistent with the General Plan and water demands are
accounted for in the City's Urban Water Management Ptan.
F. Is the project served by a landfill with sufficient permitted capacity to accommodate the
project's solid waste disposal needs?
G. Comply with federal, state and local statutes and regulations related to solid waste?
Less Than Significant Impact
75~~5 15
Responses to
Environmental Checklist
For CEQA Compliance
The ity o ants na woul prove a soli waste collection services to t e project site. olid waste is
transported to the Environmental Service transfer station in Irvine, and then taken to the Bowerman
Landfill. The Bowerman Landfill is permitted to accept 8,500 tons per day and is anticipated to close in
year 2024.
The California Integrated Waste Management Act of 1989 (AB 939) mandates all cities and counties in
California to divert fifty percent of solid waste generated from landfill disposal. As part of the General
Plan, the City of Santa Ana has prepared a Source Reduction and Recycling Element, which describe
how the City :complies with the mandates of AB 939. In order to comply with the requirements of AB 939,
the City has implemented several waste reduction programs including green waste programs, source
reduction programs, and recycling programs.
The proposed project would not significantly increase the demand for solid waste disposal. Compliance
with the City's recycling program would reduce long-term solid waste disposal service impacts to a level
considered less than significant.
XVII. Mandatory Findings of Significance
A. Does the project have the potential to degrade the quality of the environment,
substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife
population to drop below self-sustaining levels, threaten to eliminate a plant or animal
community, reduce the number or restrict the range of a rare or endangered plant or
animal or eliminate important examples of the major periods of California history or
prehistory.
No Impact
Implementation of the proposed project would not substantially reduce the habitat of fish or wildlife
species, in that no fish, wildlife populations or cultural resources are known to exist on the project site.
Additionally, it is unlikely that unknown cultural resources would be discovered on the project site as it
has previously been developed.
B. Does the project have impacts that are individually limited but cumulatively considerable?
No Impact
Implementation of the proposed project would not result in cumulative impacts to the environment. The
proposed project would comply with the applicable requirements of the California Standards Building
Code, conditions of approval and mitigation measures, which provide specific requirements that would
avoid any significant cumulative impacts within the project area.
C. Does the project have environmental effects, which will cause substantial adverse effects
on human beings either directly or indirectly?
No Impact
Construction and operation of the proposed project would not involve any activities that would cause
substantial adverse effects on human beings, either directly or indirectly. Mitigation measures have been
identified to reduce potential impacts to the environment and human beings to a level considered less
than significant.
7v~~~6 t6
Responses to
Environmental Checklist
For CEQA Compliance
XVIII. References
City of Santa Ana Updated General Plan Land Use Element February 1998.
City of Santa Ana Updated General Plan Land Use Element Environmental Impact, January, 1998, SCH
97071058
City of Santa Ana Zoning Ordinance, December 1998
City of Santa Ana Urban Design Element, July 6, 1998
City Santa Ana Local Register of Historic Structures
National Register of Historic Structures
Flood Insurance Rate Map Community Panel No. 06059C0259H
City of Santa Ana Development Review Committee, August 2007
South Coast Air Quality Management District CEQA Air Quality Handbook, 1993
California Environmental Quality Act Statues and Guidelines, January 1999
Site Visit by Vince Fregoso, Principal Planner, February 2008
Integrated Waste Management Solid Waste Generation Rate
City of Santa Ana 2000 Urban Water Management Plan
XX.PREPARERS
Vince Fregoso, City of Santa Ana Principal Planner
7 ~L~df-3~ ~ 17
GATEWAY PLAZA
MITIGATION MONITORING PLAN
ENVIRONMENTAL REVIEW NO. 2007-73
MITIGATION MEASURE AGENCY APPROVAL
Prior to issuance of Gradin Permit and durin construc tion
• During construction, the contractor shall comply Public Works
with SCAQMD Fugitive Dust Rule 403 to
suppress dust generated by construction
operations. To ensure compliance with
SCAQMD Fugitive Dust Rule 403, grading
plans and demolition plans for the proposed
project shall reflect the following notes:
o All material excavated or graded will be
sufficiently watered to prevent excessive
amounts of dust.
o All clearing and earthwork activities shall cease
during period of high winds (winds greater than
25 mph averaged over one hour) or during Stage
1 or Stage 2 smog episodes.
o Streets surrounding the project site shall be
cleaned at the end of each day of construction.
o All material transported offsite shall either be
sufficiently watered or securely covered to
prevent excessive amounts of dust.
o The amount of area disturbed by clearing and
earthwork activities shall be minimized at all
times.
o Equipment engines shall be maintained in good
condition and in proper tune according to
manufacturer's specifications.
o To the extent feasible, gasoline powered
equipment shall be used for onfite and offsite
construction activities.
• The project developer shall provide proof of
coverage under NPDES General Construction
Activity Storm Water Permit that includes: (a) A
copy of the project's permit issued by the State
Water Resource Control Board that identifies the
permit number, (b) Two copies of the Storm
Water Pollution Prevention Plan.
75B-58
• Submit and have approved a surface
drainage/utility plan that depicts all applicable
"Site Design" structural "Source Control" and
"Treatment Control" Best Management Practices
(BMPs) in accordance with the Orange County
Drainage Area Management Plan (DAMP) and
the City of Santa Ana Local Implementation
Plan (LIP).
• Submit for approval a surface
drainage/grading/erosion control plan. The plan
is to include existing and proposed elevations at
and adjacent to all property lines. Drainage
routed to the street must be directed beneath the
sidewalk and through the curb.
• Provide two copies of the Water Quality
Management Plan that include the following:
o Site Assessment
o Site design Best Management Practices (BMP)
o Applicable Routine Source Control BMP
o Selecting and sizing the Treatment Control BMP
o Mechanisms by which funding for long-term
operation and maintenance of all structural BMP
will be provided
o Operation and Maintenance Plan to describe the
long-term operation and maintenance
requirements of all applicable structural BMP
and to identify the entity in charge of
implementation
• The proposed project would be subject to City of
Santa Ana Federal Clean Water Protection
Ente rise Fees.
Prior to the issuance of a Buildin Permit
• Provide an irrevocable offer to dedicate eight Public Works
feet of right-of--way along the project frontabge
to allow an ultimate street centerline to property
line width of 60 feet.
• Provide a 25 foot by 25 foot dedication for
corner cutoff/handicap ramps at the northeast
corner of MacArthur Boulevard and Plaza Drive.
• Record reciprocal ingress/egress easements
between the project site and the properties to the
east.
75B-59
The buildings and parking lot must conform to Police
the provisions of Chapter 8, Article II, Division
3 of the Santa Ana Municipal Code (Building
Security Ordinance). These code conditions
will require that the existing project's lighting,
door/window locking devices and addressing be
upgraded to current code standards. Lighting
standards cannot be located in required
landscape planters.
The applicant shall be responsible for
maintaining the premises free of graffiti. All
graffiti shall be removed within 24 hours of
occurrence.
3
75B-60
KO- 4/29/08
RESOLUTION NO. 2008-
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA APPROVING AND ADOPTING THE
MITIGATED NEGATIVE DECLARATION AND MITIGATION
MONITORING PROGRAM (ENVIRONMENTAL REVIEW NO.
2007-73) AND AMENDING THE GENERAL PLAN OF THE
CITY OF SANTA ANA TO MODIFY THE LAND USE
ELEMENT (GPA NO. 2008-01)
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines
and declares as follows:
A. The Applicant is requesting adoption and approval of the Mitigated
Negative Declaration and Mitigation Monitoring Program, Environmental
Review No. 2007-73, General Plan Amendment No. 2008-01, Amendment
Application No. 2008-02 and Variance No. 2008-03 to reduce the required
building setback along MacArthur Boulevard from fifteen (15) feet to ten (10)
feet to allow the construction of two new buildings within an existing retail
center at 1501 West MacArthur Boulevard.
B. On March 24, 2008, the Planning Commission held a duly noticed public
hearing and voted by a vote of 4:0 (Betancourt, Gartner and Munoz
absent) to recommend that the City Council:
1. Approve and adopt the Mitigated Negative Declaration and
Mitigation Monitoring Program, Environmental Review No. 2007-73.
2. Adopt a resolution approving General Plan Amendment No. 2008-
01.
3. Adopt an ordinance approving Amendment Application No. 2008-
02.
4. Adopt a resolution approving Variance No. 2008-03 as conditioned.
C. On May 5, 2008, the City Council of the City of Santa Ana held a duly
noticed public hearing and at that time considered all testimony, written
Resolution No. 2008-XXX
Page 1 of 4
75B-61
and oral.
D. General Plan Amendment No. 2008-01 has been filed with the City of
Santa Ana to modify the Land Use Element to change the property located
at 1501 West MacArthur Boulevard from Medium Density Residential (MR)
to General Commercial (GC).
E. The Council finds that General Plan Amendment No. 2008-01 is consistent
with the General Plan, including but not limited to its policies and goals of:
Promote the balance of land uses to address basic community
needs. Land Use Element Goal No. 1.0.
2. Promote land uses which enhance the City's economic and fiscal
viability. Land Use Element Goal No. 2.0.
3. Support land uses with provide community and regional economic
and service benefits. Land Use Element Policy No. 4.3.
F. The Council finds that the City's general plan is designed, as it must be, to
accommodate a wide range of competing interests -including those of
developers, neighborhoods and homeowners, prospective homebuyers,
environmentalists, current and prospective business owners, jobseekers,
taxpayers, and providers and recipients of all types of city-provided
services -and to present a clear and comprehensive set of principles to
guide development decisions. The City's general plan sets forth these
guiding principles. Once in place, it is the province of this Council to
examine the specifics of a proposed project to determine whether it would
be in harmony with the policies stated in the general plan.
G. The City Council has weighed and balanced the general plan's policies,
both new and old, and has determined that based upon this balancing that
General Plan Amendment No. 2008-01 is consistent with the purpose of
the general plan.
H. Amendment Application No. 2008-02, and Variance No. 2008-03 also
came before the City Council on May 5, 2008 for public hearing. This
resolution incorporates by reference, as though fully set forth herein, the
ordinance and resolution in support of this resolution and the findings
made herein.
Section 2. The City Council has reviewed and considered the information
contained in the initial study and the mitigated negative declaration and mitigation
monitoring program for Environmental Review No. 2007-73 prepared with respect to this
Project. It is determined that, as required pursuant to the California Environmental Quality
Act ("CEQA") and the State CEQA Guidelines, a mitigated negative declaration and
Resolution No. 2008-XXX
Page 2 of 4
75B-62
mitigation monitoring program adequately addresses the expected environmental impacts
of this Project. On the basis of this review, the City Council finds that there is no evidence
from which it can be fairly argued that the project will have a significant adverse effect on
the environment. The City Council hereby certifies and approves the mitigated negative
declaration and mitigation monitoring program and directs that the Notice of Determination
be prepared and filed with the County Clerk of the County of Orange in the manner
required by law.
Section 3. The City Council hereby, approves General Plan Amendment No.
2008-01. The pages changed in the Land Use Element (Exhibit A) are attached hereto
and incorporated herein by this reference as though fully set forth. This decision is
based upon the evidence submitted at the above said hearing, which includes but is not
limited to: the Request for Council Action dated May 5, 2008 and exhibits attached
thereto and the public testimony written and oral, all of which are incorporated herein by
this reference.
Section 4. This resolution shall not be effective unless and until Ordinance No.
NS-2765 becomes effective. If said ordinance is for any reason held to be invalid or
unconstitutional by the decision of any court of competent jurisdiction, or otherwise does
not go into effect for any reason, then this resolution shall be null and void and have no
further force and effect.
Section 5. The City Council expressly reserves the right to modify, amend or
repeal this resolution at any time by adoption of a subsequent resolution.
Section 6. The Clerk of the Council shall attest to and certify the vote adopting
this Resolution.
ADOPTED this day of , 2008.
Miguel A. Pulido
Mayor
APPROVED AS TO FORM:
Joseph W. Fletcher, City Attorney
Resolution No. 2008-XXX
Page 3 of 4
75B-63
By:
Kylee O. Otto
Assistant City Attorney
AYES: Councilmembers
NOES: Councilmembers
ABSTAIN: Councilmembers
NOT PRESENT: Councilmembers
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, PATRICIA E. HEALY, Clerk of the Council, do hereby attest to and certify the
attached Resolution No. 2008-X:XX to be the original resolution adopted by the City
Council of the City of Santa Ana on
Date:
Clerk of the Council
City of Santa Ana
Resolution No. 2008-XXX
Page 4 of 4
75B-64
LAND USE ELEMENT
SANTA ANA GENERAL PLAN
City of Santa Ana
Planning Division
Adopted
February 2, 1998
The following is a chronology of the approved general plan amendments that have been incorporated into this
document since the comprehensive update of the General Plan Land Use Element adopted by Santa Ana City Council
February 2, 1998 (GPA 1997-05):
GPA 2008-01 (May 5, 2008), GPA 2007-02 (June 18, 2007), GPA 2007-01 (March 19, 2007), GPA 2006-01 (October 2,
2006), GPA 2005-01 (December 5, 2005), GPA 2005-02 (October 17, 2005), GPA 2004-01 (April 5, 2005, as passed by
the voters of Santa Ana), GPA 2004-04 (July 19, 2004), GPA 2004-06 (July 6, 2004), GPA 2003-02 (June 16, 2003),
GPA 2003-01 (February 18, 2003), GPA 2002-01 (September 3, 2002), GPA 2002-03 (August 19, 2002), GPA 2001-03
(February 19, 2002), GPA 2001-02 (January 7, 2002), GPA 2000-09 (May 7, 2001), GPA 2000-08 (February 5, 2001),
GPA 2000-03 (December 4, 2000), GPA 2000-02 (November 20, 2000), GPA 1999-02 (October 18, 1999), GPA 1999-
01 (August 16, 1999), GPA 1998-04 (October 5, 1998), GPA 1998-05 (September 21, 1998), GPA 1998-01 (May 4,
1998).
a ~_ ~ c Y
C ~ ~ p
~ ~ ~
C ~ ~ a ~ a X S
a lL
o a D -- ~ ~ ,
c
N f E a S m v
~ g~ g~ v 9~ ~ Q b J
-~ ~J 7 f 2~ lyJ Z ? O ~ a p
rn
75B-66
O W ~ ~ V a In N ~
N O O O O O O 4 .-~In O1A0OiAoo~rvov>ov~ian ooov~o •FJ \ iI~ I
w~I
V~
OCO.-N~ ^ '^
W a~ V'
~
b O ..
L LL
~ .@
N LL Q. ~
W ~
O
m
a ^
c m
~~
~ ^
°
~ N
~ ^'
W ~
(n ~ ~ Q ~
~
~
.$ g o
,. m~
c ~ .~ a
en E C
E ~~ a
: ~ ~ ~ 5
a ~ ~~' ~ ~ ~
A :~,Ve s g
z ~
N $ N
~ ~ > U) LL ~
Q ~ ~
~ ~+ a ,
d~
~~
~ ~
°J o`
e v
o ~ ~
8 p~ s
~ v J
W F ~ ~+
~ ~ u~uT~ '~$agtgm ~f1Ei
~ ~ y ~`~ ~ ~~~~~g~aa8'
s g ? ~E~~~Og~
3c~=
~~
N~i~~;~ ~
g~
~ .. ~
&
~ ~ fn .
~ C p
J N )
g~ m ..
O lV Ov .~. y
yoo
o
.. O ~
d ~m`E U3[~9
~y=xw3UV¢G_w ^ K ~" ~ ~
~s
~ O
n cU7 z ~ ~
c
g59g gggggg p
? ~ a ~UZi~xU~0
0X ~
~n va'>g m~
~fa~ ~ f
~
0
r
i
NNN ~ ~ ® I
.~
My\
75B-67
LAND USE ELEMENT
• To encourage lot consolidation for optimal site design, the floor area
ratio can be calculated on an area wide basis for contiguous parcels
which are part of a large, multi-structure project.
• To qualify for an area wide floor area ratio calculation, a project must
be integrated in design and function, and the owner/developer must
record deed restrictions limiting the project area to the legally allowed
floor area ratio.
Land Use Designations
The Santa Ana Land Use Plan includes 11 land use designations. These
designations indicate the types and intensity of development to be allowed on
the property which they cover. Generally, the designation also reflects the
predominant development character of the area. As is typical in older,
urbanized communities like Santa Ana, there are some areas where existing
development does not completely reflect the land use designation of the Land
Use Plan. Where these occur the properties are deemed legal conforming
and may continue until such time as the property has been vacant for twelve
months or more. Each land use designation and a brief description are
discussed below.
Residential
The Land Use Plan provides for three distinct residential land use
designations. Residential development is also permitted in two other
designations: District Center and Residential/Industrial. The Santa Ana Land
Use Plan includes the following residential land use designations:
• The Low Density Residential (LR-7) designation applies to those areas
of the City which are developed with lower density residential land
uses. The allowable maximum development intensity is 7 units per
acre. Development in this category is characterized primarily by
single-family homes. This designation applies to a large proportion of
the City (6,474.5 acres) representing 47 percent of the City's total land
area.
• The Low-Medium Density Residential (LMR-11) designation applies to
those sections of the City which are developed with residential uses at
permitted densities of up to 11 units per acre. The land area included
in this designation is approximately 433.8 acres. The great majority
of the land designated as Low-Medium Density Residential is located
in the westerly portion of the City, north and south of First
Street. Properties with this designation are typically characterized
by mobile
Revised (May 5, 2008) A-'r/ 5 B~ V 8
LAND USE ELEMENT
home parks, a mixture of duplexes and single family residences, or
small lot subdivisions.
• The Medium Density Residential (MR-15) designation applies to
those sections of the City which are developed with residential
uses at densities of up to 15 units per acre. Development in this
designation is characterized by duplexes, apartments, or a
combination of both. A total of 413.2 acres is designated as Medium
Density Residential. The designation applies to areas located in the
vicinity of downtown, areas north and south of MacArthur
Boulevard, and in other areas where there are established multiple-
family development projects.
• The Residential /Industrial designation permits either residential
development up to 15 units per acre or industrial uses. The
designation applies to the Logan neighborhood, which was
established near the turn of the century. Since the 1930s, this
18.5-acre area has developed with a mixture of residential and
industrial uses.
• The District Center designation permits residential development up
to 90 units per acre when it is a component of a mixed-use,
master planned project. In the Metro East District Center
residential density is based on a maximum 3.0 floor area ratio and
the overlay development standards. This category includes
approximately 427 acres and is described in greater detail later in
this section.
Professional and Administrative Office
The Professional/Administrative office (PAO) designation applies to those
areas where professional and/or administrative offices are predominant, or
where such development is being encouraged. Land included in this
designation is found primarily near the Civic Center, and along the First
Street and Tustin Avenue Corridors in close proximity to freeways. There
are other smaller PAO areas in the City such as along North Broadway and
along portions of east and west Seventeenth Street. A total of 621.5
acres is included in this land use designation. The floor area ratio intensity
standard applicable to this land use designation ranges from 0.5 to 1.0.
The Professional and Administrative Office areas are intended to provide a
unique environment for office development in those areas of the City where
office uses are the predominant land use. The purpose for maintaining and
supporting these areas exclusively for office and office-related uses is to
encourage major employment centers at locations which significantly lessen
the impact to the City's local street system. The First Street/Tustin Avenue
Revised (May 5, 2008)
A-18
75B-69
LAND USE ELEMENT
office corridor between the Santa Ana (I-5) and Costa Mesa (SR-55)
Freeways serves this purpose. In addition, the orderly, well-maintained quality
of existing development supports a continuation of these areas as functional
office/employment centers.
The Professional and Administrative Office designation includes a range of floor
area ratios to differentiate development intensity and character in relation to
adjacent land uses. The areas with a FAR of 0.5 are not major office centers, but
rather have an established character of lower intensity garden office and
professional service uses. These areas are typically adjacent to low density
residential neighborhoods, or are converted residential office uses. Office
development along East Fourth Street, between Grand Avenue and the Santa Ana
Freeway, is typical of this low-rise office character. The PAO area located adjacent to
the Civic Center contains a range of office development intensity which supports the
City's functional role as the government center of the County.
The types of uses typically located in the PAO district include the following:
• Professional and administrative offices/office parks;
• Service activities such as copy centers, courier services, travel agencies, and
restaurants when such uses are an integral component of a planned office
development; and
• Professional uses such as accountants, attorneys, doctors, engineers, and
insurance brokers.
General Commercial Districts
The General Commercial district (GC) applies to commercial corridors in Santa Ana including those
located along Main Street, Seventeenth Street, Harbor Boulevard, and other major arterial
roadways in the City. The intensity standard applicable to this designation is a floor area ratio of
0.5 -1.0, though most General Commercial districts have a FAR of 0.5. A total of 1,113.6 acres of land
is included in this designation.
General Commercial districts are key components in the economic development of the City.
They provide highly visible and accessible commercial development along the City's arterial
transportation corridors. In addition, General Commercial land uses provide important neighborhood
facilities and services, including shopping, recreation, cultural and entertainment activities,
employment, and education. The districts also provide support facilities and services for industrial
areas including office and retail, restaurants and various other services.
A-19
Revised (May 5, 2008)
75B-70
LAND USE ELEMENT
Table A-4 indicates the development possible under the build-out of the
Land Use Plan. The build-out for residential land uses considered two
scenarios. Effective build-out for residential development is calculated by
adding the 8,783 units possible in the areas designated as District Center to
the existing 74,588 units presently found in the City. Theoretical build-out for
residential development considered the development possible if all of the
areas designated as residential were developed according to the permitted
Land Use Plan intensities. Since the Land Use Element does not
contemplate the elimination of existing housing in the City, the effective
build-out figure represents a more realistic estimate of future residential
development.
As indicated in Table A-4, four of the non-residential land use designations
have a range in FAR intensities. For the non-residential land use
designations, effective build-out considered the development possible under
the lower range of FAR intensities while theoretical build-out considered the
upper FAR range. Typically, parking and landscaping requirements will
result in significantly less floor area for commercial and industrial
developments than that which is permitted under the General Plan.
As indicated in Table A-4, between 65,212 to 77,820 housing units are
allowed by the Land Use Plan. The additional units which presently exist in
the City beyond the maximum number permitted under the theoretical build-
out scenario are a reflection of the higher density multiple-family
developments constructed in the 1970's and 1980's. However, the purpose
of the Land Use Plan as it applies to the residential areas is to preserve
and maintain the stability of existing neighborhoods, regardless of the
character of development. The intent of the Plan is not to create any
displacement, nor decrease existing development densities. Rather, it is to
ensure a safe, healthy, and livable environment for City residents. Existing
residential development entitlements are protected through this Land Use
Element, applicable Zoning regulations, and sections of the City code
pertaining to legal nonconforming uses.
The Land Use Element's implementation may result in an increase in the
amount of commercial, office, and industrial development in the City. As
indicated in Table A-4 up to 55,658,406 square feet of commercial and office
development, and 44,891,128 square feet of industrial development are
possible under the effective capacity parameters of Land Use Plan.
Revised (May 5, 2008)
7~~-71
Amended Table A-4
Land Use Plan Build-out Capacities
Intensity/Density Effective Theoretical
Land Use Acres Standards Build-out, Build-out
Mixed Use2 103.5 ac FAR 3.0
Metro East Residential DC 5,551 d.u.
SubTotal 5,551 d.u.
Metro East Commercial DC 3,245.185 s.f. 3,245,185 s.f.
SubTotal 3,245,185 s.f. 3,245,185 s.f.
Residential
Low Density Residential LR-7 6,474.4 ac. 7 d.u./ac 45,321 d.u.
Low Medium Density Residential LMR-11 433.8 ac. 11 d.u./ac 4,772 d.u.
Medium Density Residential MR-15 413.2 ac. 15 d.u./ac 6,198 d.u.
Residential/Industrial3 R/1-15 9.2 ac. 15 d.u./ac 138 d.u.
District Centera DC 35.9 ac. 90 d.u./ac 3,232 d.u.
SubTotal 7,366.5 ac. 77,820 d.u., 59,661 d.u.
Commercial
Professional & Admin. Office PAO 621.5 ac. FAR 0.5-1.0 13,536,270 s.f. 27,072,540 s.f.
General Commercial GC 1,113.6 a.c. FAR 0.5-1.0 24,254,426 s.f. 48,508,852 s.f.
District Centera DC 323.2 ac. FAR 1.0-2.0 14,079,332 s.f. 28,158,665 s.f.
One Broadway Plaza District Ctrs OBPDC 4.3 ac. FAR 2.9 543,193 s.f. 543,193 s.f.
SubTotal 2,062.6 ac. 52,413,221 s.f. 104,283,249 s.f.
Industrial
Industrial IND 2,280.9 ac. FAR 0.45 44,710,202 s.f. 44,710,202 s.f.
Residential/Industrial3 R/I-15 18.5 ac. FAR 0.45 180,926 s.f. 180.926 s.f.
SubTotal 2,290.1 ac. 44,891,128 s.f. 44,891,128 s.f.
Utner
Institutionals INS 812.6 ac. FAR 0.2-0.5 7,079,023 s.f. 17,697,557 s.f.
Open Space OS 1,019.0 ac. FAR 0.2 8,877,876 s.f. 8,877,876 s.f.
SubTotal 1,831.6 ac. 15,956,899 s.f. 26,575,433 s.f.
Notes:
,Effective capacity for non-residential development assumes development possible under the lower range of FAR intensity standards
with the exception of the Metro East District Center. Residential effective capacity was calculated by adding the 8,783 units possible in
the District Center with the existing 74,588 (Census 2000) housing units.
zThe Metro East District Center allows a range of intensity for mixture of residential and commercial development based on the Metro
East Mixed Use Overlay Zone development standards.
stand use designation permits both residential and industrial development. Build-out assumed 50% of the land area will be developed
as residential and 50% as industrial development.
4Land use designation permits both residential and commercial development. Build-out assumes 90% of land area will be developed
as commercial and 10% will be developed as residential.
FAR -floor area ratio, d.u. -dwelling units, s.f. -square feet (of floor area). Acreage shown in table does not include roads in
right-of-way.
sEffective capacity assumes FAR of 0.2
stand use designation permits high intensity office development with ancillary retail use.
This table has been revised to correspond with the G/S Land Use Map illustrated in Exhibit 2.
Revised (May 5, 2008) A-31
75B-72
ORDINANCE NO. NS-2765
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA REZONING THE PROPERTY LOCATED AT
1501 WEST MACARTHUR BOULEVARD FROM TWO-
FAMILY RESIDENTIAL (R-2) TO GENERAL COMMERCIAL
(C-2) (AA NO.2008-02)
THE CITY COUNCIL OF THE CITY OF SANTA ANA DOES ORDAIN AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana does hereby find, determine
and declare as follows:
A. The Applicant is requesting adoption and approval of the Mitigated Negative
Declaration and Mitigation Monitoring Program, Environmental Review No.
2007-73, General Plan Amendment No. 2008-01, Amendment Application
No. 2008-02 and Variance No. 2008-03 to reduce the required building
setback along MacArthur Boulevard from fifteen (15) feet to ten (10) feet to
allow the construction of two new buildings within an existing retail center at
1501 West MacArthur Boulevard.
B. On March 24, 2008, the Planning Commission held a duly noticed public
hearing and voted by a vote of 4:0 (Betancourt, Gartner and Munoz absent)
to recommend that the City Council:
1. Approve and adopt the Mitigated Negative Declaration and Mitigation
Monitoring Program, Environmental Review No. 2007-73.
2. Adopt a resolution approving General Plan Amendment No. 2008-01.
3. Adopt an ordinance approving Amendment Application No. 2008-02.
4. Adopt a resolution approving Variance No. 2008-03 as conditioned.
C. On May 5, 2008, the City Council of the City of Santa Ana held a duly
noticed public hearing and at that time considered all testimony, written and
oral.
D. Amendment Application No. 2008-02 has been filed with the City of Santa
Ana to rezone the property located at 1501 West Macarthur Boulevard from
Two-Family Residential (R-2) to General Commercial (C-2).
E. Amendment Application No. 2008-02 is consistent with the General Plan,
including but not limited to its goals and policies:
75B-73
Promote the balance of land uses to address basic community
needs. Land Use Element Goal No. 1.0.
2. Promote land uses which enhance the City's economic and fiscal
viability. Land Use Element Goal No. 2.0.
3. Support land uses with provide community and regional economic
and service benefits. Land Use Element Policy No. 4.3.
F. The City Council has weighed and balanced the general plan's policies and
has determined that based upon this balancing that the project at 1501 West
Macarthur Boulevard is consistent with the purpose of the general plan.
G. The City Council also adopts as findings all facts presented in the Request
for Council Action dated May 5, 2008 accompanying this matter. For these
reasons, and each of them, Amendment Application No. 2008-02 is hereby
found and determined to be consistent with the General Plan of the City of
Santa Ana and otherwise justified by the public necessity, convenience, and
general welfare.
H. Mitigated Negative Declaration and Mitigation Monitoring Program,
Environmental Review No. 2007-73, General Plan Amendment No. 2008-01,
and Variance No. 2008-03 came before the City Council on May 5, 2008 for
public hearing. This ordinance incorporates by reference, as though fully set
forth herein, the resolutions and the Mitigated Negative Declaration and
Mitigation Monitoring Program in support of this ordinance and the findings
made herein.
Section 2. The real property located at 1501 West Macarthur Boulevard is
hereby rezoned from Two-Family Residential (R-2) to General Commercial (C-2).
(AA No. 2008-02) Amended Sectional District Map number 35-5-10 showing the above
described change in use district designation, is hereby approved and attached hereto as
Exhibit "A" and incorporated by this reference as though fully set forth herein. This
decision is based upon the evidence submitted at the above said hearing, which
includes but is not limited to: the Request for Council Action dated May 5, 2008 and
exhibits attached thereto and the public testimony written and oral, all of which are
incorporated herein by this reference.
Section 3. If any section, subsection, sentence, clause, phrase or portion of this
ordinance is for any reason held to be invalid or unconstitutional by the decision of any
court of competent jurisdiction, such decision shall not affect the validity of the remaining
portions of this ordinance. The City Council of the City of Santa Ana hereby declares that
it would have adopted this ordinance and each section, subsection, sentence, clause,
phrase or portion thereof irrespective of the fact that any one or more sections,
subsections, sentences, clauses, phrases, or portions be declared invalid or
unconstitutional.
75B-74
ADOPTED this
day of , 2008.
APPROVED AS TO FORM:
Joseph W. Fletcher
City Attorney
By:
Kylee O. Otto
Assistant City Attorney
AYES:
NOES:
ABSTAIN:
NOT PRESENT
Councilmembers
Councilmembers
Councilmembers
Councilmembers
Miguel A. Pulido
Mayor
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, PATRICIA E. HEALY, Clerk of the Council, do hereby attest to and certify the
attached Ordinance No. NS- to be the original ordinance adopted by the City
Council of the City of Santa Ana on ,and that said ordinance was
published in accordance with the Charter of the City of Santa Ana.
Date:
Clerk of the Council
City of Santa Ana
75B-75
2]-5-10
~ JU
26-5-10
SD-4
W ~
J~I SD-6 R1-PRD
;~I
~ ~. I
I~==--, ~
i
W
~ ~
R1 ~ `SD-44
i 1 `~'~ i t=
II I~ a
I 1
343-10 SANTA ANA CITY LIMITS 1'- __--~
1
SUNFLOWE
City
SOUTH LINE SECT. 26-5-f0
SD-4
-see.-e~,1 I 1
n \\ I 1 \ 1
~\ \'I ~I
ISD-7i~ ~ R1-PRD ±~~?
- I I Su~+Ee~ ,~ R4
i 1 1 n'IIND 19A'~~'B~
1 I! ~1
l i iir Iii \ l i m
l`_f~ II ~~ it I
~I I I 15 I I ---- .
R2-PRD
R4
26-5-10 25-5-10
36-5-10
- C2 C4
I
I
C2 y
J
O
N
m
~ ~ I NO RESOLUTION NO., ORDINANCE N0. OR DATE OF ADOPTION IS SHOWN FOR THIS MAP
SINCE IT IS AN ORIGINAL RECORD OF THE SANTA ANA CITY DISTRICT CLASSIFICATION FOR
ALL PROPERTIES INCLUDED HEREON
Ai GENERALAGRICULTURAL C-SM SOUTH MAIN STREET COMMERCIAL DISTRICT PD PLANNED DEVELOPMENT
-B PARKING MODIFICATION -F FLOOR AREA RATIO PRD PLANNED RESIDENTIAL DEVELOPMENT
C7 COMMUNITY COMMERCIAL GC GOVERNMENT CENTER R7 SINGLE-FAMILY RESIDENCE
C7-MD COMMUNITY COMMERCIAL-MUSEUM DISTRICT M7 LIGHT INDUSTRIAL
C2
GENERAL COMMERCIAL
M2
HEAVY INDUSTRIAL R2 TWO-FAMILY RESIDENCE
C3
CENTRAL BUSINESS
MO
MIL
T R3 MULTIPLE-FAMILY RESIDENCE
I
ARY OPERATIONS R4 SUBURBAN APARTMENT
C3-A CENTRAL BUSINESS-ARTISTS' VILLAGE O OPEN SPACE RE RE
ID
C4
PLANNED SHOPPING CENTER
-OZ
OVERLAY ZONE
SD S
ENTIAL ESTATE
SP
C5
ARTERIAL COMMERCIAL
P
PROFESSIONAL ECIFIC DEVELOPMENT
CR
COMMERCIAL RESIDENTIAL
PCD
PLANNED COMMUNITY DEVELOPMENT SP SPECIFIC PLAN
SCALE IN FEET
0 1000
6O- MINIMUM FRONTAGE
-6000 MINIMUM LOTAREA
THIS MAP LS THE OFFICIAL SECTIONAL
DISTRICT MAP OF THE CITY OF SANTAANA.
As AuTHOerzeD BY cm couNCa
RESOLUTION NO. ]b163, DATE01f-1B-]4, I
HEREBY ATTEST THAT THIS MAP IS ATRUE
COPY OF THE ORIGINAL SECTIONAL DISTRICT
MAP N0. 955~id
Signed _
JAV TREVINO
E%ECUTIVE DIREC70R
PUNNING 8 BUILDING AGENCY
Cenifirafe Da4 October 15 2007
• • , • ~ ~ ~
~ PREPARED BY THE PLANNING DIVISION - CITY OF SANTA ANA, CALIFORNIA
REVISED Y7/08
I SD-48 CR
SD-
48
~ __ __ ~_~
KO-4/29/08
RESOLUTION NO. 2008-
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTA ANA APPROVING VARIANCE NO. 2008-03 AS
CONDITIONED TO ALLOW A REDUCTION IN THE
REQUIRED BUILDING SETBACK ALONG MACARTHUR
BOULEVARD FROM FIFTEEN FEET TO TEN FEET FOR
THE PROPERTY LOCATED AT 1501 WEST MACARTHUR
BOULEVARD
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS
FOLLOWS:
Section 1. The City Council of the City of Santa Ana hereby finds, determines
and declares as follows:
A. The Applicant is requesting adoption and approval of the Mitigated
Negative Declaration and Mitigation Monitoring Program, Environmental
Review No. 2007-73, General Plan Amendment No. 2008-01, Amendment
Application No. 2008-02 and Variance No. 2008-03 to reduce the required
building setback along MacArthur Boulevard from fifteen (15) feet to ten
(10) feet to allow the construction of two new buildings within an existing
retail center at 1501 West MacArthur Boulevard.
B. On March 24, 2008, the Planning Commission held a duly noticed public
hearing and voted by a vote of 4:0 (Betancourt, Gartner and Munoz
absent) to recommend that the City Council:
1. Approve and adopt the Mitigated Negative Declaration and
Mitigation Monitoring Program, Environmental Review No. 2007-73.
2. Adopt a resolution approving General Plan Amendment No. 2008-
01.
3. Adopt an ordinance approving Amendment Application No. 2008-
02.
4. Adopt a resolution approving Variance No. 2008-03 as conditioned.
C. On May 5, 2008, the City Council of the City of Santa Ana held a duly
noticed public hearing and at that time considered all testimony, written
and oral.
D. Mitigated Negative Declaration and Mitigation Monitoring Program,
Environmental Review No. 2007-73, General Plan Amendment No. 2008-
01,and Amendment Application No. 2008-02 came before the City
Council on May 5, 2008 for public hearing. This resolution incorporates by
Resolution No. 2007-081
Page 1 of 5
75B-77
reference, as though fully set forth herein, the ordinance and resolution
and the Mitigated Negative Declaration and Mitigation Monitoring Program
in support of this resolution and the findings made herein.
E. Variance No. 2008-03 has been filed with the City of Santa Ana seeking to
reduce the required building setback along MacArthur Boulevard from
fifteen (15) feet to ten (10) feet. Section 41-369 of the Santa Ana
Municipal Code requires a 15-foot landscaped setback.
F. Santa Ana Municipal Code Section 41-638 authorizes the City Council to
grant a variance upon making certain findings.
That because of special circumstances applicable to the subject
property, including size, shape, topography, location or
surroundings, the strict application of the zoning ordinance is found
to deprive the subject property of privileges not otherwise at
variance with the intent and purpose of provisions of this Chapter.
The proposed reduction in the front yard setback will allow
the applicant the ability to construct a new addition to the
Gateway Plaza retail center. Due to the conveyance of land
for the widening of MacArthur Boulevard, the placement of
the new buildings was constrained.
2. That the granting of a variance is necessary for the preservation
and enjoyment of one or more substantial property rights.
The granting of the setback variance will preserve the
property owner's ability to develop the property with a project
that will be consistent with the General Commercial (C-2)
zoning district and with a project that is consistent with the
goals and policies of the General Plan. A condition of
approval has been incorporated that will require additional,
enhanced landscaping along MacArthur Boulevard to
mitigate the loss of setback area.
3. That the granting of a variance will not be materially detrimental to
the public welfare or injurious to surrounding property.
The granting of the setback variance will not be detrimental
to the public welfare or injurious to surrounding property.
The proposed buildings will be buffered by landscaping and
outdoor plaza area and will allow the buildings to be placed
at the rear of the site, thereby reducing the impact to the
adjacent residential uses.
4. That the granting of a variance will not adversely affect the General
Plan of the City.
The granting of the variance will not adversely affect the
General Plan of the City as retail uses are permitted in the
Resolution No. 2008-
Page 2 of 5
75B-78
General Commercial (GC) General Plan land use
designation. Further, the proposed building is consistent
with Goals 1, 2 and 3 of the General Plan Land Use
Element, which encourage the City to promote a balance of
land uses to address basic community needs, promote uses
that enhance the City's economic and fiscal viability and
improve the character and integrity of existing
neighborhoods.
Section 2. The City Council after conducting the public hearing hereby
approves Variance No. 2008-03 as conditioned in Exhibit "A" attached hereto and
incorporated herein to reduce the required building setback along MacArthur Boulevard
from fifteen (15) feet to ten (10) feet for the property located at 1501 West MacArthur
Boulevard. This decision is based upon the evidence submitted at the above said
hearing, which includes but is not limited to: the Request for Council Action dated May
5, 2008 and exhibits attached thereto and the public testimony written and oral, all of
which are incorporated herein by this reference.
Section 3. This resolution shall not be effective unless and until Ordinance No.
NS-2765 becomes effective. If said ordinance is for any reason held to be invalid or
unconstitutional by the decision of any court of competent jurisdiction, or otherwise does
not go into effect for any reason, then this resolution shall be null and void and have no
further force and effect.
ADOPTED this day of 2008.
Miguel A. Pulido
Mayor
APPROVED AS TO FORM:
Joseph W. Fletcher, City Attorney
By:
Kylee O. Otto
Assistant City Attorney
AYES: Councilmembers:
NOES: Councilmembers:
Resolution No. 2007-081
Page 3 of 5
75B-79
ABSTAIN: Councilmembers:
NOT PRESENT: Councilmembers:
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, PATRICIA E. HEALY, Clerk of the Council, do hereby attest to and certify the
attached Resolution No. to be the original resolution adopted by the City
Council of the City of Santa Ana on
Date:
Patricia E. Healy
Clerk of the Council
City of Santa Ana
Resolution No. 2008-
Page 4 of 5
75B-80
Conditions for Approval for Variance No. 2008-03
Variance No. 2008-03 is approved subject to compliance, to the reasonable satisfaction of
the Planning Manager, with applicable sections of the Santa Ana Municipal Code, the
California Administrative Code, the California Standards Building Code, and all other
applicable regulations. In addition, it shall meet the following conditions of approval:
The applicant must comply with each and every condition listed below rior to exercising
the rights conferred by this variance.
The applicant must remain in compliance with all conditions listed below throughout the life
of the development project. Failure to comply with each and every condition may result in
the revocation of the variance.
A. Planning Division
All proposed site improvements must conform with the Site Plan Review
approval of DP No. 07-19 and the staff report exhibits.
2. Any amendment to this variance must be submitted to the Planning
Division for review. At that time, staff will determine if administrative relief
is available or the variance must be amended.
3. Prior to issuance of any building permit, a voluntary lot merger to combine
the lots into one parcel shall be recorded.
4. Landscaping along the south property line shall be upgraded to 36-inch box
trees.
5. Prior to submittal into building plan check, revise the plans to show
decorative paving will be installed at all project driveway entries.
B. Police Department
Prior to issuance of any building permit, submit a conceptual lighting plan
for the parking lot. Light standards cannot be located in landscaped areas
to avoid conflict with the canopy growth of trees.
2. The existing parking lot and structures must conform to the provision of the
Building Security Ordinance, including lighting, doors and window locking
devices, and addressing.
Exhibit A
Resolution No. 2008-
Page 5 of 5
75B-81
75B-82