CITY COUNCIL MEETING DATE:
AUGUST 3, 2009
TITLE:
CONTRACT AWARD FOR MACARTHUR
BOULEVARD FRONTAGE TO SANTA ANA
RIVER BIKE TRAIL ENHANCEMENT
(PROJECT NO.08- 6033 -M)
l�
1 CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 151 Reading
❑ Ordinance on 2 "d Reading
❑ Implementing Resolution
❑ Set Public Hearing For_
CONTINUED TO
FILE NUMBER
1. Award a contract to Elite Bobcat Service, Inc., the lowest
responsible bidder, in accordance with unit bid prices in the
estimated amount of $42,424.24 for construction of the MacArthur
Boulevard Frontage to Santa Ana. River Bike Trail Enhancement.
2. Approve a Funding Analysis with a total estimated construction cost
of $56,500.
DISCUSSION
The MacArthur Boulevard frontage to Santa Ana River Bike Trail pavement
is deteriorating due to weather, age and heavy usage (Exhibit 1) . The
project provides for pavement reconstruction of the bike trail that is
connected to the main Santa Ana River Bike Trail. Once completed, the
improvements will enhance the functionality, surface drainage, safety
and visual appearance of the bike trail.
The Notice Inviting Bids was advertised on May 20 and 22, 2009, and bids
were opened on July 8, 2009. A summary of the bid invitations mailed,
the bids received, and the bid results follows.
Santa Ana Contractors receiving notices: 15
Contractors requesting bidding documents: 7
Bids received: 3
Bids received from Santa Ana Contractors: 0
23A -1
Contract Award For MacArthur
Blvd. Frontage
August 3, 2009
Page 2
NAME OF RESPONSIVE BIDDER
1. Elite Bobcat Service, Inc.
2. All American Asphalt
3. International Pavement Solutions, Inc
CITY
Corona
Corona
San Bernardino
BID
AMOUNT
$42,424.24
$50,530.00
$62,050.00
A total of three bids were received and all were responsive. The lowest
bid was submitted by Elite Bobcat Services, Inc., for $42,424.24, which
is below the Engineer's estimate of $50,000.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, Categorical
Exemption ER No. 2006 -27 has been approved and filed.
FISCAL IMPACT
The funding analysis shows a total estimated construction cost of
$56,500 for the project (Exhibit 2). Funds are available in the
Transportation Enhancement Activity Fund (account no. 59- 551 - 6631), the
Park Acquisition and Development Fund (account no. 314 - 232 -6631) and the
Roberti Z'Berg- Harris Grant Fund (account no. 161 - 270 - 6631).
James G. Aoss c
Executive Director
Public Works Agency
Gerar o Mouet
Execu ive Director
Parks, Recreation, and
Community Services Agency
APPROVED AS TO FUNDS AND ACCOUNTS:
POO
Francisco Gutierrez
Executive Director
Finance & Mgmt. Services Agency
K:\ Construction \RFCA - draft \08 -03 -09 MacArthur Frontg 08 -6033 ET 30 WD.docx
FUNDING ANALYSIS
PROJECT NO. 08- 6033 -M
MACARTHUR BOULEVARD FRONTAGE TO
SANTA ANA RIVER BIKE TRAIL ENHANCEMENT
Construction Contract $42,424
Contract Administration $1,102
Inspection and Testing $2,800
Survey Staking $1,690
Contingencies $8,484
TOTAL ESTIMATED CONSTRUCTION COSTS $56,500
Exhibit 2
23A -4