HomeMy WebLinkAbout23C - SUSAN STREET REHABREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: AUGUST 3, 2009 TITLE: CONTRACT CHANGE ORDER NO. 1; SUSAN STREET REHABILITATION (PROJECT N0.09-1750-C) CLERK OF COUNCIL USE ONLY: APPROVED ^ As Recommended ^ As Amended ^ Ordinance on 15` Reading ^ Ordinance on 2"d Reading ^ Implementing Resolution ^ Set Public Hearing For_ CONTINUED TO ~(di ~~~___.-_ FILE NUMBER CITY MANAGER COMME Approve Change Order No. 1 for Susan Street Rehabilitation from Sunflower Avenue to MacArthur Boulevard for an estimated cost of $183,700. DISCUSSION Change Order Number: Project Description: Contractor: 1 Susan Street Rehabilitation R. J. Noble Company 15505 E. Lincoln Avenue Orange, CA 92865 Original Contract Cost: $593,867.90 Amount of this Change Order: Previously approved Change Order: Total Change Orders: $177,000 29.80 -0- -0- $177,000 29.80 23C-1 Change Order No. 1 Project No. 09-1750-C August 3, 2009 Page 2 This change order is to extend the pavement rehabilitation limits on Susan Street from MacArthur Boulevard northerly to Alton Avenue. The construction bid for Susan Street from Sunflower Avenue to MacArthur Boulevard was $181,132 below the Engineer's estimate. In order to maximize the use of available State Proposition 1B Funds, it is recommended to extend the limits of pavement construction. The added pavement segment of Susan Street from MacArthur Boulevard to Alton Avenue has been identified as a high priority on the City' s Pavement Management System. The contractor will be paid according to actual quantities of work and the agreed unit prices. ESTIMATED COST = $177,000 FISCAL IMPACT The cost for the change order is estimated at $177,000. Funds are available in the State - Proposition 1B Fund (account no. 030-551- 6631) . APPROVED AS TO FUNDS AND ACCOUNTS: aG- James G. oss Executive Director Public Works Agency Francisco Gutierrez Executive Director Finance & Mgmt. Services Agency K:\Construction\RFCA-draft\09-1750-C 2009-08-03 COl.doc 23C-2