HomeMy WebLinkAbout55A - PHASE I OF ALTON AVE OVERCROSSING ROUTE 55REQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
SEPTEMBER 8, 2009
TITLE:
TRANSPORTATION INVESTMENT
GENERATING ECONOMIC RECOVERY
FUNDING APPLICATION FOR PHASE I OF
ALTON AVE. OVERCROSSING AT STATE
ROUTE 55 PROJECT 081730)
f ~''-~G
CITY MANAGER
RECOMMENDED ACTION
Adopt a resolution authorizing:
CLERK OF COUNCIL USE ONLY:
APPROVED
^ As Recommended
^ As Amended
^ Ordinance on 15t Reading
^ Ordinance on 2"d Reading
^ Implementing Resolution
^ Set Public Hearing For
CONTINUED TO
FILE NUMBER
• The Executive Director of the Public Works Agency to submit a grant
application for Phase I of the Alton Avenue Overcrossing at State
Route 55 (SR-55) Project (Project) for Transportation Investments
Generating Economic Recovery (TIGER) Discretionary funds under the
American Recovery and Reinvestment Act (ARRA) of 2009.
• The Mayor to execute the Certification stating that the infrastructure
investment received the full review and vetting required by law; and
it is an appropriate use of taxpayer dollars.
DISCUSSION
The United States Department of Transportation (USDOT) has issued a Notice
of Funding Availability for Supplemental Discretionary Grants for Capital
Investments in Surface Transportation Infrastructure under the American
Recovery and Reinvestment Act of 2009. One and one-half billion dollars are
available nationwide for highways or bridges, public transportation,
passenger and freight rail transportation, and port infrastructure
projects. The ARRA limits grants to $300 million and indicates that
priority will be given to projects that can be completed by February 17,
2012.
The City will be submitting an application for Phase I of the Alton Avenue
Overcrossing at SR-55 project totaling $35,000,000 for the right of way and
construction costs. The proposed improvements will ease traffic congestion
and consist of a new overcrossing at Alton Avenue and the SR-55 connecting,
the cities of Santa Ana and Irvine and widening Alton Avenue between Maple
Street and Halladay Street (Exhibit 1).
55A-1
Transportation Investment Generating
Economic Recovery Funding Application
For Phase I of Alton Ave. Overcrossing
September 9, 2009
Page 2
in October 2005, the City Council approved the Final Environmental Impact
Report for the SR-55/Alton Avenue Overcrossing Project. Santa Ana is the
lead agency on this project which is a cooperative project with the City of
Irvine. In April 2009, the City entered into a professional service
agreement with Huitt-Zollars to provide engineering services, which are
anticipated to be completed in spring 2011.
Given the need of eligibility requirements defined by USDOT, staff
recommends that the City Council adopt the resolution authorizing submittal
of the project application for funding consideration and executing the
Certification. Applications for TIGER Discretionary Grants are due
September 15, 2009 and funds are available early 2010.
ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.
FISCAL IMPACT
If the project application is approved for funding, the City will receive
an estimated $35,fl00,000 through the TIGER Discretionary Grant program,
which does not require matching funds, over two years - FY 10/11 through
FY 11/12.
APPROVED AS TO FUNDS AND ACCOUNTS:
+~~
George A arez Francisco Gutierrez
Acting Executive Director Executive Director
Public Works Agency Finance & Management Services Agency
55A-2
S~4NTA0~4NA
w
a
U
N
LEGEND:
If __ __~ PROJECT LIMITS
EXHIBIT 1 /,?%,
~~ crrY coutvci~ T~-E~ TIGER FUND APPLICATION FOR
AGENDA oaTE~ PHASE I OF ALTON AVENUE
" ~' SEPTEMBER 8, 2009
V OVERCROSSING AT SR-55
""~' ' " (PROJECT NO. 081730)
RESOLUTION NO. 2009-
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF SANTA ANA AUTHORIZING THE
SUBMITTAL OF AN APPLICATION FOR FUNDING
THROUGH THE AMERICAN RECOVERY AND
REINVESTMENT ACT -TRANSPORTATION
INVESTMENT GENERATING ECONOMIC
RECOVERY PROGRAM
Iss8/20/09
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA
ANA AS FOLLOWS:
Section 1: The City Council of the City of Santa Ana hereby finds,
determines and declares as follows:
A. Congress, through the American Recovery and Reinvestment Act of
2009 ("ARRA") has authorized the U. S. Department of Transportation
("DOT") to administer the Transportation Investment Generating
Economic Recovery ("TIGER") program, to fund capital investments in
surface transportation projects; and
B. The TIGER program provides one and one-half billion dollars for
highways and bridges, public transportation, passenger and freight rail
transportation, and port infrastructure projects. The ARRA limits
grants to $20 to $300 million and indicates that priority will be given to
projects that can be completed by February 17, 2012; and
C. The Santa Ana Public Works Agency has recommended that the City
submit an application for TIGER funds totaling $35,000,000, to fund
right-of-way and construction costs for Phase I of the Alton Avenue
Overcrossing at SR-55 project; and
D. The Alton Avenue Overcrossing project has been included in the
Regional Transportation Improvement Program (RTIP) administered by
the Orange County Transportation Authority.
Section 2: The City Council of the City of Santa Ana has fully reviewed
and vetted Phase I of the Alton Avenue Overcrossing at SR-55 project and
certifies that the project is an appropriate use of taxpayer dollars.
Section 3: The City Council of the City of Santa Ana authorizes the
Executive Director of the Public Works Agency to submit an application to the
U.S. Department of Transportation, in the amount of thirty five million dollars
($35,000,000), to complete Phase I of the Alton Avenue Overcrossing at SR-55
project.
55A-5
Section 4: The City Council appoints the City Manager, or the
Executive Director of the Public Works Agency or his designee, as agent for the
City of Santa Ana to conduct all negotiations, execute and submit all documents,
including the required Notice of Intention to submit application, as well as
applications, agreements, amendments, payment requests and so on, which may
be necessary for the completion of the project.
Section 5: This Resolution shall take effect immediately upon its
adoption by the City Council, and the Clerk of the Council shall attest to and
certify. the vote adopting this Resolution.
ADOPTED this day of 2009.
Miguel A. Pulido
Mayor
APPROVED AS TO FORM:
Joseph W. Fletcher, City Attorney
By:
Laura Sheedy
Assistant City Attorney
AYES: Councilmembers
NOES: Councilmembers
ABSTAIN Councilmembers
NOT PRESENT Councilmembers
CERTIFICATE OF ORIGINALITY
I, Maria D. Huizar, Clerk of the Council, do hereby certify the attached Resolution
No. to be the original resolution adopted by the City Council of
the City of Santa Ana on , 2009.
Date:
Clerk of the Council
City of Santa Ana
55A-6
CERTIFICATION UNDER SECTION 1511 OF
THE AMERICAN RECOVERY AND REINVESTMENT ACT
Pursuant to Title XV, subtitle A, section 1511 of the American Recovery and
Reinvestment Act (Pub. L. 111-5 (Feb.l7, 2009) ("ARRA"), I, Miguel A. Pulido, Mayor
of the City of Santa Ana, hereby certify that the infrastructure investment funded by
ARRA has received the full review and vetting required by law and that I accept
responsibility that such investment is an appropriate use of taxpayer dollars. I further
certify that the specific information required by section 1511, concerning such investment
(a description of the investment, the estimated total cost and the amount of ARRA funds
to be used) is provided on the Southern California Association of Governments Regional
Transportation Improvement Program (RTIP) and is available to the public at
http://www.scag.ca qov/rtip/rtip2008/approved htm.
I understand that the City of Santa Ana may not receive ARRA infrastructure investment
funding unless this certification is made and posted.
55A-7