HomeMy WebLinkAbout23C - OMNIBUS CONCRETE IMPROVEMENTSREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: NOVEN~ER 2, 2 0 0 9 TITLE: CONTRACT AWARD FOR 2009-2010 OMNIBUS CONCRETE IMPROVEMENTS (PROJECT N0.106716) ~~ _ CI MANAGER RECOMMENDED ACTION 1. Award a contract to C. J. Construction, Inc., the lowest responsible bidder, in accordance with unit bid prices in the estimated amount of $212,562.50 for construction of Omnibus Concrete Improvements. 2. Approve a Funding Analysis with a total estimated construction cost of $245,000. DISCUSSION This project will provide for replacement of damaged and deteriorated concrete sidewalk, curbs, gutters, cross gutters, wheelchair ramps, driveway approaches and concrete pavement at various locations throughout the City. The work will be performed on an as-needed basis. The Notice Inviting Bids was advertised on September 18 and 21, 2009, and bids were opened on October 13, 2009. A summary of the bid invitations mailed, the bids received, and the bid results follows. CLERK OF COUNCIL USE ONLY: APPROVED ^ As Recommended ^ As Amended ^ Ordinance on 1s1 Reading ^ Ordinance on 2nd Reading ^ Implementing Resolution ^ Set Public Hearing For_ CONTINUED TO FILE NUMBER Santa Ana Contractors receiving notices: 9 Contractors requesting bidding documents: 20 Bids received: 10 Bids received from Santa Ana Contractors: 1 NAME OF RESPONSIVE BIDDER CITY BID AMOUNT 1. C. J. Construction, Inc. 2. HYM Engineering, Inc. 3. F. S. Construction 4. Unique Performance Constructi,Q~ J~=~ Santa Fe Springs Bellflower Sylmar Costa Mesa $212,562.50 $249,960.00 $262,150.00 $321,018.75 Contract Award For Omnibus Concrete Improvements November 2, 2009 Page 2 5. D. P. Mangan Inc. dba Pave West 6. Elite Bobcat Service, Inc. 7. J.D.C., Inc. 8. Kormx, Inc. 9. Nobest, Inc. 10. Hardy & Harper, Inc. La Habra Corona Rancho Cucamonga Walnut Garden Grove Santa Ana $323,150.00 $339,479.00 $362,087.50 $381,355.00 $396,725.00 $486,075.00 A total of ten bids were received and all were responsive. The lowest bid was submitted by C. J. Construction, Inc., for $212,562.50, which is above the Engineer's estimate of $201,850. ENVIRONMENTAL IMPACT In accordance with the California Environmental Quality Act, the recommended action is exempt from further review. Categorical Exemption ER No. 2009-134 was filed for this project. FISCAL IMPACT The funding analysis shows a total estimated construction cost of $245,000 for the project (Exhibit 1). Funds are available in the Measure M Street Construction Fund (accounting unit 03217660-66220). ` ~~ George Alvarez Acting Executive Director Public Works Agency K:\Construction\RFCA-draft\1 I-02-09 Omnibus 2009-10 106716 WA.docx APPROVED AS TO FUNDS AND ACCOUNTS: Francisco Gutierrez Executive Director Finance & Mgmt. Services Agency 23C-2 FUNDING ANALYSIS PROJECT NO. 106716 2009 - 2010 OMNIBUS CONCRETE IMPROVEMENTS Construction Contract Contingencies $212, 562 $32,438 TOTAL ESTIMATED CONSTRUCTION COSTS $245,000 Exhibit 1 23C-3 23C-4