REJECTION OF BIDS FOR ADAMS ? As Recommended
PARK BASKETBALL COURT ? As Amended
? Ordinance on 15t Reading
RENOVATION (PROJECT NO. 107504) ? ordinance on 2"d Reading ~
? Implementing Resolution
? Set Public Hearing For
~ CONTINUED TO
~n-z<:..~:/ ~ I ' - FILE NUMBER
CITY MANAGER
RECOMMENDED ACTION
Reject all bids for the Adams Park Basketball Court Renovation.
DISCUSSION
The existing basketball court at Adams Park has severe cracking and erosion of existing surface
that inhibits the use of the facility (Exhibit 1). The project entails resurfacing and re-striping of six
existing basketball courts. Additionally, volleyball and hopscotch are to be re-striped within the
basketball courts.
The Notice Inviting Bids was advertised on February 17 and 19, 2010, and bids were opened on
March 9, 2010. A summary of the bid invitations mailed, the bids received, and the bid results
follows.
Santa Ana Contractors receiving notices: 18
Contractors requesting bidding documents: 15
Bids received: 9
Bids received from Santa Ana Contractors: 2
23B-1
Rejection of Bids For Adams
Park Basketball Court Renovation
April 5, 2010
Page 2
NAME OF RESPONSIVE BIDDER CITY BID AMOUNT
1. Caliber Paving Company, Inc. Santa Ana $69,925.00
2. Century Paving, Inc. La Mirada $76,561.00
3. ACE CD, Inc. La Verne $80,752.85
4. Panorama General Engineering, Inc. Upland $80,999.99
5. Hardy & Harper, Inc. Santa Ana $89,840.50
6. KM Consulting Crestline $105,532.60
7. Malibu Pacific Tennis Courts, Inc. Westlake Village $118,612.50
8. 4-Con Engineering, Inc. Riverside $148,990.00
9. Hunter General Engineering, Inc. Oceanside $149,952.42
A total of nine bids were received and all were responsive. The lowest bid was submitted by
Caliber Paving Company, for $69,925 which is below the Engineer's estimate of $98,825. The
project is funded with Community Development Block Grant funds, but was inadvertently
advertised without the federal requirements associated with this funding. Therefore, staff
recommends that all bids be rejected and the project be re-advertised with the federal
requirements.
ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.
FISCAL IMPACT
There is no fiscal impact associated with this action.
Q r--
Raul Godinez II
Executive Director
Public Works Agency
Gerardo Mouet
Executive Director
Parks, Recreation, and Community
Services Agency
RGNVA
Exhibit 1: Project Location Map
23B-2
EDINGER AVE
~
~
N
H
Z
w
J
Q
U
N
W
W
Z
w ST. GERTRUDE
U
PROJECT SITE
WARNER AVE
EXHIBIT 1 3~~o~NORANG~cG
O 2
0 ~ <
SANTA ANA TITLE: ~ ; ~
PWA ciTY couNCi~ REJECTION OF BIDS FOR
AGENOA~ATE: ADAMS PARK BASKETBALL COURT RENOVATION
APRIL 5, so~o (PROJECT NO. 107504)
PUBLIC VYORKS AGENCY
23B-3 I',
i
23B-4