City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
July 1, 2025
TOPIC: McFadden Avenue Transit Signal Priority Project
AGENDA TITLE
Construction Contract to Vido Samarzich, Inc. for the McFadden Avenue Transit Signal
Priority Pilot Project (No. 25-6031) (Non -General Fund)
RECOMMENDED ACTION
1. Approve the Project Cost Analysis for a total estimated construction delivery cost
of $1,972,000, which includes $1,577,600 for the construction contract, $236,640
for contract administration, inspection, and testing, and a $157,760 project
contingency for unanticipated or unforeseen work.
2. Award a construction contract to Vido Samarzich, Inc., the lowest responsible
bidder, in accordance with the base bid in the amount of $1,577,600, subject to
change orders, for construction of the McFadden Avenue Transit Priority Pilot
Project (No. 25-6031), for a term beginning July 1, 2025 and authorize the City
Manager to execute the contract.
3. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption
Environmental Review No. ER-2025-42 was filed for Project No. 25-6031.
GOVERNMENT CODE 484308 APPLIES: No
DISCUSSION
The Public Works Agency Engineering Division (PWA) is responsible for the
administration and oversight of all Capital Improvement Projects (CIP) in the City. On
September 17, 2024, City Council awarded a construction contract for Standard Street
and McFadden Avenue Corridor Roadway Improvements project that includes various
street improvements on McFadden Avenue from Harbor Boulevard to Grand Avenue,
such as new sidewalks and pavement restoration.
On October 15, 2024, City Council approved a cooperative agreement with Orange
County Transportation Authority (OCTA) recognizing $3,690,000 in grant funding to
Construction Contract for the McFadden Avenue Transit Signal Priority Project
July 1, 2025
Page 2
construct the McFadden Avenue Transit Signal Priority (TSP) Pilot Project. The grant
funds will allow for the City to construct a TSP Pilot Project including the design and
construction of improvements at 25 bus stops along the McFadden Avenue Corridor.
The McFadden Avenue TSP Pilot Project will be delivered in two phases. On June 3,
2025, City Council awarded a contract for the first phase which is focused on
technology elements, programming, and testing field devices. The recommended
construction contract is the second phase and will construct physical bus stop
improvements including concrete bus pads, bus shelters, and pedestrian level lighting to
improve bus travel time and overall ridership experience.
The McFadden Avenue TSP Pilot Project will supplement the previously approved
street improvements for McFadden Avenue by constructing transit focused
improvements that will benefit the Santa Ana residents who utilize OCTA's Route 66,
one of the highest ridership bus routes in Orange County. The proposed grant funded
improvements will promote transit use and will enhance OC Bus travel time, schedule
reliability, and reduce fuel consumption and emissions while also maintaining traffic flow
and improving corridor safety along McFadden Avenue. The construction of the bus
stop improvements will be coordinated with the ongoing construction of the McFadden
Avenue corridor roadway improvements to minimize disruption.
A copy of construction plans, contracts, specifications, and all related reference
materials (such as The Greenbook) are available for public review at the City's Public
Works Agency, Central Files office located in City Hall.
Grant Funding
The City, in coordination with Orange County Transportation Authority (OCTA), received
a grant from Southern California Association of Governments (SCAG) Regional Early
Action Planning (REAP 2.0) program in the amount of $3,690,000 for the completion of
both phases of this project. The REAP 2.0 program seeks to reduce Vehicle Miles
Traveled, increase housing supply at all affordability levels, affirmatively further fair
housing, and facilitate the implementation of adopted regional and local plans to achieve
these goals. The grant requires that this project be completed by June 30, 2026.
Proiect Advertisement and Contractor Procurement
To provide an opportunity for local vendors to submit bids, the City notified a total of 46
regional vendors via PlanetBids, many of which are Santa Ana based. Furthermore,
staff specifically reached out to Santa Ana vendors to encourage their participation in
bids. A total of three bids were received and one bid was received from a Santa Ana
contractor.
As legally required, a Notice Inviting Bids was advertised in the Orange County Register
newspaper on April 10, 2025 and April 17, 2025. The project was also advertised in
PlanetBids from April 10, 2025 to April 30, 2025. Bids were received electronically via
Construction Contract for the McFadden Avenue Transit Signal Priority Project
July 1, 2025
Page 3
PlanetBids on April 30, 2025. No bid protest was submitted by any of the bidders during
the bid protest period.
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BASE BID
1
Vido Samarzich, Inc.
Santa Ana, CA
$1,577,600
2
Excel Paving Co.
Long Beach, CA
$1,798,800
NR
Estate Design and Construction
Los Angeles, CA
Non -responsive
A total of three bids were received and two were deemed responsive. Vido Samarzich,
Inc. submitted the lowest responsive base bid in the amount of $1,577,600 (Exhibit 2).
As specified in the bid documents, the lowest bid shall be determined on the basis of
the Base Bid. Based on the bid analysis and a contractor's reference check, staff
recommends awarding the construction contract to Vido Samarzich, Inc. (Exhibit 3).
Vido Samarzich, Inc. has previously performed work as a prime contractor in the City of
Santa Ana within the past five years, including Glenwood Watermain Improvements,
10th Street and Flower Street Improvements, and are currently working on the Standard
and McFadden Bikeway Project. The contractor has performed satisfactorily on these
projects and staff recommends awarding the construction contract to Vido Samarzich,
Inc. for the construction of the Project. (Exhibit 3)
Proiect Delive
To deliver a complete project, in addition to the construction contract, the estimated total
project delivery cost includes a budget allocation for construction administration,
inspection, and testing. Construction administration and inspection may be performed
by either Staff or consultants and includes construction management, inspection of the
Contractor's work to ensure contract compliance, workmanship and quality, materials
testing, and implementation of the labor requirements.
Any of the allocated construction administration funds not spent are considered project
savings and are returned to the respective fund balance upon close out of the project.
As indicated in the Cost Analysis and as summarized in the table below, the estimated
total construction delivery cost of the project is $1,972,000.
Project Item
Total
Construction Contract Bid Amount
$1,577,600
Construction Administration
$125,420
Inspection
$80,457
Testing
$30,763
Project Contingencies
$157,760
TOTAL ESTIMATED CONSTRUCTION DELIVERY COST
$1,972,000
Project Schedule and Contract Time
Construction Contract for the McFadden Avenue Transit Signal Priority Project
July 1, 2025
Page 4
The project completion date is January 31, 2026, barring unforeseeable conditions such
as rain, natural disasters, or other delays beyond the control of the City and of the
Contractor. The contract time for this project is 120 working days, as specified in the bid
documents. Working days are counted in accordance with the City's Standard
Specifications, which exclude weekends, City -observed holidays, and inclement
weather days that prevent work.
The actual completion date will depend on the contractor's schedule, material
procurement timelines, and any unforeseen delays. Based on a typical project timeline,
the estimated project completion is provided below;
Project Milestones
Milestone
Estimated
Completion Date
Notes
Administrative Startup
July 2, 2025
Contract execution, bonds,
insurance
Material Procurement
July 15, 2025
Procurement will take place
concurrently with construction.
Contractor Mobilization
July 15, 2025
Start of construction activities
Project Completion
I January 31, 2026
1 Based on 120 workin da s
Project Phasing
The contractor will be constructing this project in coordination with the McFadden
Avenue Street Improvement project in the following phases:
1. Phase I: Concrete bus pad construction
2. Phase II: Bus shelter and lighting installation
3. Phase III: Installation of bus stop amenities and technology devices
Public Outreach
The project scope overlaps with the existing McFadden Avenue street improvement
project and occur concurrently and having benefited from outreach performed
associated with the street improvement project. The project will impact nearby
businesses and residences. To ensure timely and effective communication, the
following notification measures will be implemented prior to the start of construction:
• Electronic message signs will be installed two weeks in advance of construction
activities to provide early notice of the project's start date,
• A project information sign will be posted at the construction site, including contact
information for public inquiries,
• Residents and businesses within 1,000 feet of the project limits will receive door
hanger or mailed notifications at least two weeks before construction begins
• A second round of notification will be issued 48 hours prior to the start of
construction to residents and business adjacent to the limits of work, and
Construction Contract for the McFadden Avenue Transit Signal Priority Project
July 1, 2025
Page 5
The City will also disseminate information through its official website and social
media platforms to keep the public informed of construction activities, including
any lane closures.
ENVIRONMENTAL IMPACT
Pursuant to the California Environmental Quality Act (CEQA), the recommended actions
are exempt from further review pursuant to Section 15301(b) of the CEQA Guidelines
for projects consisting of repair/maintenance of existing public facilities. The proposed
project continues to meet these parameters of the CEQA Guidelines and Categorical
Exemption Environmental Review No. ER-2025-42 was filed for Project 25-6031
(Exhibit 4).
FISCAL IMPACT
As indicated in the Cost Analysis, the estimated total construction delivery cost of the
project is $1,972,000. All funds are available for expenditure in Fiscal Year 2025-26.
Any remaining balances not expended at the end of the fiscal year will be presented to
City Council for approval to carry forward to Fiscal Year 2026-2027. (Exhibit 5).
The proposed contract authorizes staff a maximum of 10% in contingencies for
construction contract change orders. Staff will return to City Council for authorization
and appropriation of additional contingency if necessary.
The following table summarizes the funds budgeted for expenditure to deliver
construction of this project.
Accounting
Fund
Accounting Unit,
Fiscal Year
Unit -
Description
Account Description
Amount
Account #
14717613-
Regional Early Action
2025-26
66220
Street Safety
Planning Grant,
$1,972,000
(25-6031)
Programs
Improvements Other
Than Buildings
Total:
$1,972,000
EXHIBIT(S)
1. Location Map
2. Bid Proposal
3. Construction Contract
4. Environmental Determination
5. Capital Improvement Project Worksheet
Submitted By: Nabil Saba, P.E., Executive Director, Public Works Agency
Approved By: Alvaro Nunez, City Manager
EXHIBIT 1
Exhibit 1
SANTA ANA
�N C)RgN�� \
��0
Project No. 25-6031: Y
umi
1 Q
McFadden Avenue Transit Signal Priority Project
. .
PUBLIC WORKS AGENCY
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 25-6031
MCFADDEN AVENUE TRANSIT SIGNAL PRIORITY PROTECT
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Vido Samarzich, Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Qty
Unit
Unit Price
Amount
Furnish & Install Transit
1
Advertising Shelter
13
25
EA
EA
$20,000.00
$ 260,000.00
$ 150,000.00
2
Furnish & Install Solar Power for
$ 6,000.00
Transit Shelters
a
Furnish & Install Transit Non-
12
I z\
$
Advertising Shelter
19,000.00
228,000.00
4
Furnish & Install Steel Bench
25
EA
$
$
(Including Secure Nuts)
3,500.00
87,500.00
Furnish & Install 32 Gallon Trash
5
Receptacle (Including Secure
25
f "A
5 3,800.00
$ 95,000.00
Nuts & Master Padlock
6
PCC Sidewalk (T=6")*
6,800
SF
$ 17.00
$ 115,600.00
7
Install New Bus Pad*
6,000
SF
$ 42.75
$ 256,500.00
Remove & Salvage Existing
1
EA
$ 4,000.00
$ 4,000.00
Shelter*
9
Remove & Salvage Existing
25
LA
$ 750.00
$ 18,750.00
Bench*
10
Remove & Salvage Existing
25
EA
% 300.00
$ 7,500.00
Trash Receptacle*
$
11
Furnish & Install New Water
6
EA
Meter Frame and Cover
1,500.00
$ 15,000.00
11
9,000.00
15,000.00
S 275,000.00
12
Signing & Striping;
1
LS
13
Furnish and Install Solar Powered
25
EA
Street Light Pole and Foundation
,000.00
P-1 of P-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 25-6031
MCFADDEN AVENUE TRANSIT SIGNAL PRIORITY PROJECT
Item
Description
Qty
Unit
Unit Price
Amount
14
Pothole Street Light Pole
Location
25
EA
$ 1,750.00
$ 43,750.00
15
Construction Permit
I
LS
$ 7,000
$ 7,000
16
Project Advertisement Sign
2
EA
$ 2,500.00
$ 5,000.00
BID ALTERNATES
Item
Description
Qty
Unit
Unit Price
Amount
Furnish and Del Iver Solar
1
Powered Street Light Pole
5
EA
$ 9,500.00
$ 47,500.00
P-2 of P-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 25-6031
MCFADDEN AVENUE TRANSIT SIGNAL PRIORITY PROJECT
TOTAL BASE BID
$ 1,577,600.00
TOTAL ADD ALTERNATE BID
$ 1,625,100.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the " 25%" limit as stated in Section 7-3.5 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within One -Hundred Twenty (120) working days after the commencement date stated in
the Notice to Proceed. Upon issuance of the Notice to Proceed, Contractor shall immediately place
order for long -lead time items (Street Light Poles, Tolar Bus Shelters (Ad & Non -Ad), Solar
Powers, Trash Receptacles, and Benches).
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $1,650 per calendar day.
Name of Firm Vida Samarz
Signature of BIDDER
Title Vice President
Inc.
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partriers composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
Corporation: Vido Samarzich, Inc.
President: Vido Samarzich
Vice President: Vido L. Samarzich
Secretary; Monika Samarzich
P-3 of P-19
EXHIBIT 3
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT 25-6031
MCFADDEN AVENUE TRANSIT SIGNAL PRIORITY PROJECT
This CONSTRUCTION CONTRACT is made and entered into this 1" day of July, 2025 by and between
the City of Santa Ana, California, a charter city and municipal corporation organized and existing under
the Constitution and laws of the State of California (hereinafter "CITY"), and Vido Samarzich, Inc.
(hereinafter "CONTRACTOR").
WITNESSETH:
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows:
CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and
expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction
of the City Engineer of the CITY, the McFadden Avenue Transit Signal Priority Project (hereinafter
referred to as the "WORK OF IMPROVEMENT") identified in and in accordance with the Contract
Documents prepared by the City's Public Works Agency and approved by the City Council.
2. The complete Construction Contract consists of the "Contract Documents" as defined by the Standard
Specifications for Public Works Construction and which include the following:
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Technical Provisions and Project Plans
• Community Workforce Agreement
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the WORK
OF IMPROVEMENT the sum total amount not to exceed One Million Five Hundred Seventy -Seven
Thousand Six Hundred Dollars and No Cents ($1,577,600), as set forth and identified in the BID
PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A," and in accordance
with Section 2-7.1 of the Greenbook: Standard Specifications for Public Works Construction.
The BID PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual amount of
work will correspond therewith, but reserves the right to increase or decrease the amount of any
class or portion of the work or to omit portions of the work as may be deemed necessary or
advisable.
Page 1 of 3
4. CONTRACTOR agrees to complete the WORK OF IMPROVEMENT within the time specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A") including
commencing construction within the timeframe therein specified after issuance of a Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the WORK
OF IMPROVEMENT a salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage determinations for this work in accordance with applicable State
and Federal law.
6. If applicable, the CONTRACTOR shall adhere to the CITY'S Community Workforce Agreement
(CWA), a pre -hire collective bargaining agreement, which establishes the labor relations policies and
procedures for CONTRACTOR to follow in the crafts persons employed to complete the WORK OF
IMPROVEMENT as more fully described in the CWA. The CWA may be found on the City's website
at: http://www.santa-ana.ora//pwa/documents/CWA.pdf
7. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY,
one in the amount of One Hundred Percent (100%) of the Contract price, to guarantee the faithful
performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100%)
of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment
Bond). This Contract shall not become effective until such bonds are supplied to and approved by the
CITY.
8. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention
payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond
shall also be required as a condition of project acceptance. For projects up to Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of Ten Thousand Dollars ($10,000)
or Twenty Percent (20%) of the final contract price. For projects above Five Hundred Thousand
Dollars ($500,000), the Warranty Bond amount shall be the greater of One Hundred Thousand Dollars
($100,000) or Ten Percent (10%) of the final contract price.
9. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and
Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY.
10. INDEMNIFICATION.
To the fullest extent allowed by law, CONTRACTOR and its Subcontractors hereby agree to defend,
indemnify, and hold harmless CITY, its City Council, boards and commissions, officers, agents,
employees, representatives and volunteers (hereinafter collectively referred to as "Indemnitees"),
through legal counsel acceptable to CITY, from and against any liability, claims, actions, costs,
damages or losses, including reasonable costs and attorney's fees, for injury, including death to any
person or damage to any property, arising directly or indirectly from, or in any manner relating to, any
of the following:
(i) Performance or nonperformance of the Work of Improvement by CONTRACTOR or its
Subcontractors of any lower tier;
(ii) Performance or nonperformance by CONTRACTOR or its Subcontractors of any lower tier,
of any of the obligations under the Contract Documents;
Page 2 of 3
(iii) The construction activities of CONTRACTOR or its Subcontractors of any lower tier, either
on the project site or on other properties;
(iv) The payment or nonpayment by CONTRACTOR of any of its Subcontractors of any lower
tier, for Work of Improvement performed on or off the project site; and
(v) Any personal injury, property damage or economic loss to third persons related to and arising
from the performance or nonperformance by CONTRACTOR or its Subcontractors of any
lower tier, of the Work of Improvement.
(vi) The indemnity obligations of Subcontractors provided by this Section shall be included in all
subcontract documents issued by CONTRACTOR.
Nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in
favor of CONTRACTOR against CITY or any other Indemnitee.
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and
year first above written.
ATTEST:
JENNIFER L. HALL
City Clerk
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By:
e Nellesen
Assistant City Attorney
RECOMMENDED FOR APPROVAL:
Digitally signed by
Nabil Saba
Nahil Saba Da e:2 25.06.16
08:45:35-07'00'
NABIL SABA, PE
Executive Director
Public Works Agency
CITY OF SANTA ANA
ALVARO NUNEZ
City Manager
CONTRACTOR:
Vido Samarzich, Inc.
NAME: Vido L. Samarzich
TITLE: Vice President
Page 3 of 3
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 25-6031
MCFADDEN AVENUE TRANSIT SIGNAL PRIORITY PROTECT
BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Vido Samarzich, Inc.
REQUIREMENT:
The undersigned bidder declares that they have carefully examined the location of the proposed
work, that they have examined the Contract Documents in its entirety and hereby proposes to
furnish all material and do all the work required to complete the said work in accordance with said
plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following
schedule:
Item
Description
Qty
Unit
Unit Price
Amount
Furnish & Install Transit
1
Advertising Shelter
13
25
EA
EA
$20,000.00
$ 260,000.00
$ 150,000.00
2
Furnish & Install Solar Power for
$ 6,000.00
Transit Shelters
a
Furnish & Install Transit Non-
12
I z\
$
Advertising Shelter
19,000.00
228,000.00
4
Furnish & Install Steel Bench
25
EA
$
$
(Including Secure Nuts)
3,500.00
87,500.00
Furnish & Install 32 Gallon Trash
5
Receptacle (Including Secure
25
f "A
5 3,800.00
$ 95,000.00
Nuts & Master Padlock
6
PCC Sidewalk (T=6")*
6,800
SF
$ 17.00
$ 115,600.00
7
Install New Bus Pad*
6,000
SF
$ 42.75
$ 256,500.00
Remove & Salvage Existing
1
EA
$ 4,000.00
$ 4,000.00
Shelter*
9
Remove & Salvage Existing
25
LA
$ 750.00
$ 18,750.00
Bench*
10
Remove & Salvage Existing
25
EA
% 300.00
$ 7,500.00
Trash Receptacle*
$
11
Furnish & Install New Water
6
EA
Meter Frame and Cover
1,500.00
$ 15,000.00
11
9,000.00
15,000.00
S 275,000.00
12
Signing & Striping;
1
LS
13
Furnish and Install Solar Powered
25
EA
Street Light Pole and Foundation
,000.00
P-1 of P-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 25-6031
MCFADDEN AVENUE TRANSIT SIGNAL PRIORITY PROJECT
Item
Description
Qty
Unit
Unit Price
Amount
14
Pothole Street Light Pole
Location
25
EA
$ 1,750.00
$ 43,750.00
15
Construction Permit
I
LS
$ 7,000
$ 7,000
16
Project Advertisement Sign
2
EA
$ 2,500.00
$ 5,000.00
BID ALTERNATES
Item
Description
Qty
Unit
Unit Price
Amount
Furnish and Del Iver Solar
1
Powered Street Light Pole
5
EA
$ 9,500.00
$ 47,500.00
P-2 of P-19
CITY OF SANTA ANA
PROPOSAL
PROJECT NO.: 25-6031
MCFADDEN AVENUE TRANSIT SIGNAL PRIORITY PROJECT
TOTAL BASE BID
$ 1,577,600.00
TOTAL ADD ALTERNATE BID
$ 1,625,100.00
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the
right to award the Base Bid, and any, all, or none of the add -alternate bid items (if any).
* The quantity for this bid item is shown for bid comparison only. This bid item shall not be
subject to the " 25%" limit as stated in Section 7-3.5 of the Standard Specifications. The actual
amount for this item will be dictated by the actual quantity used, and the Agency reserves the
right to increase or decrease the quantity of this item accordingly.
t This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.
TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES
The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown
above, within One -Hundred Twenty (120) working days after the commencement date stated in
the Notice to Proceed. Upon issuance of the Notice to Proceed, Contractor shall immediately place
order for long -lead time items (Street Light Poles, Tolar Bus Shelters (Ad & Non -Ad), Solar
Powers, Trash Receptacles, and Benches).
The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard
Specifications, shall be $1,650 per calendar day.
Name of Firm Vida Samarz
Signature of BIDDER
Title Vice President
Inc.
(If an individual, so state. If a firm or co -partnership, state the firm name and give the names of
all individual co-partriers composing the firm. If a corporation, state legal name of corporation,
and names of President, Secretary, Treasurer and Manager, thereof.)
Corporation: Vido Samarzich, Inc.
President: Vido Samarzich
Vice President: Vido L. Samarzich
Secretary; Monika Samarzich
P-3 of P-19
EXHIBIT 4
OF ()
ORANGE COUNTY
CLERK -RECORDER
CEQA FILING COVER SHEET
202585000394
FILED
April 30, 2025
CLERK - REC'C RT)ER.
ley �.-
Depuly clerk
So- 041So12.o..S-0309
THIS SPACE FOR CLERIC'S USE ONLY
Complete and attach this form to each CEQA Notice filed with the County Clerk -Recorder
TYPE OR PRINT CLEARLY
Project Title
25-6013 MCFADDEN AVENUE TSPP
Check Document being Filed:
Environmental Impact Report (EIR)
Mitigated Negative Declaration (MIND) or Negative Declaration (ND)
Notice of Exemption (NOE)
❑ Other (Please fill in type):
FILED IN THE OFFICE OF THE ORANGE
COUNTY CLERK -RECORDER ON 04/30/2025
Posted 0413012025 Removed
Returned to agency on
DEPUTY 428
Filing fees are due at the time a Notice of Determination/Exemption Is filed with our office.For more Information
on filing fees and No Effect Determinations, please refer to California Code of Regulations, Title 14, section 753.5.
MAYOR
Valerie Amezcua
MAYOR PRO TEM
Benjamin Vazquez
COUNCILMEMBERS
Phil Bacerra
Johnathan Ryan Hernandez
Jessie Lopez
David Penaloza
Thai Viet Phan
PUBLIC WORKS AGENCY
20 Civic Center Plaza (M-36)
P.O. BOX 1988 • Santa Ana, California 92702
(714) 647-5690 • Fax (714) 647-5823
www.santa-ana.org
NOTICE OF EXEMPTION
CITY MANAGER
Alvaro Nuiez
CITY ATTORNEY
Sonia R. Carvalho
CLERK OF THE COUNCIL
Jennifer L. Hall
From the Requirements of the California Environmental Quality Act (CEQA)
Fee Exemption per California Government Code Section 6103
To: COUNTY CLERK From: City of Santa Ana
County of Orange Public Works Agency
P.O. Box 238 20 Civic Center Plaza (M-36)
Santa Ana, CA 92702 Santa Ana, CA 92702
Project Title: 25-6013 McFadden Avenue TSPP
Project Number(s): 25-6031
Project Location: McFadden Avenue (Harbor Blvd to Grand Ave)
City: Santa Ana County: Orange ER Number: ER-2025-42 Date of Approval: 06/17/2025
Project Description: Scope of work includes relocating bus stop locations from near -side to far -side of the signalized
intersections, add new bus shelters, add or upgrade lighting at bus stop locations, add new trash cans and
benches, install new bus pads and signing and striping.
Applicant Name: City of Santa Ana, Public Works Agency
Applicant Address: 20 Civic Center Plaza M-36
Santa Ana, CA92702
Name of Public Agency Approving Project: City Council
Name of Agency Carrying Out Project: Public Works Agency
Exempt Status:
❑ Ministerial (Sec. 15268)
❑ Declared Emergency (Sec. 15269 (a))
❑ Emergency Project (Sec. 15269 (b through e))
❑ General Rule (Sec. 15061(b)(3)1(5))
❑ Statutory Exemption:
0 Categorical Exemption: 15301(b)
Reason(s) Why Project is Exempt From CEQA:
15301(b) consists of repair/maintenance of existing public facilities.
City Contact: Sam rfth`' Chenelia Title: Assistant Engineer
Signature:
FILED
APR 3 0 2025
HUGH NGUYIEN, CLERK -RECORDER
BY: 1A L DEPUTY
Telephone: (714) 647-5033 r
Date: � 1501 Z 5-
State of California - Department of Fish and Wildlife
2025 ENVIRONMENTAL DOCUMENT PILING FEE
CASH RECEIPT
DFW 753.5a (REV. 01101125) Previously DFG 753.5a -
U-7--J
P_nnt I Save
RECEIPT NUMBER:
30-04130/2025-0309
STATE CLEARINGHOUSE NUMBER (liapplfcable)
SEE INSTRUCTIONS ON REVERSE. TYPE OR PRINT CLEARLY.
LEADAGENCY LEAD AGENCY EMAIL DATE
CITY OF SANTA ANA 04/30/2025
COUNTY/STATE AGENCY OF FILING DOCUMENT NUMBER
ORANGE COUNTY 202565000394
PROJECT TITLE
25-6013 MCFADDEN AVENUE TSPP
PROJECT APPLICANT NAME PROJECT APPLICANT EMAIL PRONE NUMBER
CITY OF SANTA ANA, PUBLIC WORKS AGENCY (714) 647-5033
PROJECT APPLICANTADDRESS CITY STATE ZIP CODE
20 CIVIC CENTER PLAZA M-36 SANTA ANA CA 92702
PROJECT APPLICANT {Check appropriate box)
❑K Local Public Agency ❑ School District ❑ Other Special District ❑ State Agency ❑ Private Entity
CHECK APPLICABLE FEES:
❑ Environmental Impact Report (EIR) $ 4,123.50 $
❑ Mitigated/Negative Declaration (MND)(ND) $ 2,968.75 $
❑ Certified Regulatory Program (CRP) document - payment. due directly to CDFW $ 1,401.75 $
M Exempt from fee
EI Notice of Exemption (attach)
❑ CDFW No Effect Determination (attach)
❑ Fee previously paid (attach previously issued cash receipt copy)
❑ Water Right Application or Petition Fee (State Water Resources Control Board only) $ 850.00 $
❑ County documentary handling fee $ 50.00 $
❑ Other $
PAYMENT METHOD:
❑ Cash ❑ Credit ❑ Check ❑ Other TOTAL RECEIVED $ 0.00
SIGNATURE AGENCY OF FILING PRINTED NAME AND TITLE
X Melissa Gomez Deputy Clerk
ORIGINAL -PROJECT APPLICANT COPY -CDFWIASD COPY - LEAD AGENCY COPY - COUNTYCLrRK DFW753.5ajR9Y.M12025}
PROJECT TITLE:
McFadden Avenue Transit Signal
Priority Pilot
PROJECT CATEGORY:
Traffic Improvements
Traffic Improvements
LOCATION MAP
N
AGENCY:
Public Works
EXHIBIT 5
CITY OF SANTA ANA FY 24/25CIP
PITAL IMPROVEMENT PROJECT WORKSHEET
PROJE T DESCRIPTION:
Project will provide transit improvements along McFadden Avenue
between Harbor Boulevard and Grand Avenue including new
concrete bus pads, bus stop relocations, new bus shelters, street
lighting, real-time bus arrival information, and Transit Signal Priority.
PROJECT NEED:
The McFadden Avenue Transit Signal Priority (TSP) Pilot Project will
enhance the City's planned improvements for McFadden Avenue by
providing innovative transit improvements, including transit signal
priority, bus shelters and real-time bus arrival signage. The project will
improve transit for populations dependent on buses and similar modes
of transportation.
PROJECT COSTS FY 24125 FY 25126 FY 26127 FY 27128 FY 28129 FY 29130 FY 30131
Construction 3,414,900 - - - - - -
Engineering 275,100
TOTAL 3,690,000
SOURCE OF FUNDS FY 24125 FY 25126 FY 26127 FY 27128 FY 28129 FY 29130 FY 30131
3,690,000 - - - - -
DIVISION:
Traffic Enaineerina
TOTAL 3,690,000
CONTACT:
Cesar Rodriguez, Senior Civil Engineer
DATE:
17-Sep-2024