HomeMy WebLinkAboutItem 17 - Amendment to the Bristol-Tolliver Street Urban Greening Project Cost Analysis Public Works Agency
www.santa-ana.org/pw
Item # 17
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
August 19, 2025
TOPIC: Bristol-Tolliver Street Urban Greening Project - Basketball Court
AGENDA TITLE
Amendment to the Bristol-Tolliver Street Urban Greening Project Cost Analysis to add
$115,000 in Residential Development District 4 - Acquisition and Development funds
and $176,000 in Community Development Block Grant Funds for a New Total
Construction Delivery Cost of $4,872,808 and Change Order to add $115,000 to an
Existing Construction Contract with Legion Contractors, Inc., for the Construction of the
Basketball Court at the Project (Project No. 24-6600) (Non-General Fund)
RECOMMENDED ACTION
1. Approve an amendment to the Bristol-Tolliver Street Urban Greening Project
Cost Analysis to add $115,000 in Residential Development District 4 - Acquisition
and Development funds, and $176,000 in Community Development Block Grant
funds for a new total construction delivery cost of $4,872,808.
2. Approve a Change Order to add $115,000 to an existing construction contract
with Legion Contractors, Inc., for the construction of the basketball court at the
Bristol-Tolliver Street Urban Greening Project.
GOVERNMENT CODE §84308 APPLIES: Yes
DISCUSSION
The Public Works Agency is responsible for the administration and oversight of all
Capital Improvement projects in the City. The Bristol-Tolliver Street Urban Greening
Project is currently under construction located on the corner of Bristol Street and Tolliver
Street. This Project includes play equipment and adult fitness equipment with shade
structures, pedestrian pathways, lighting, picnic areas, educational signage, drought
tolerant landscaping, and a stormwater capture and reuse system for the park’s
irrigation. In the Project’s final construction documents, a basketball court was included
as a bid alternate in the amount of $235,000 in anticipation of future funding to be
approved and allocated by the City Council. For that reason, the award of the
construction contract in March 2025 excluded the bid alternate scope of work. During
the Fiscal Year 2025-26 (FY 25-26) budget and Capital Improvement Program (CIP)
adoption process, City Council allocated $115,000 from Park Acquisition and
Development funds (non-federal funds) and $176,000 from Community Development
Block Grant (CDBG) funds (federal funds) for a total of $291,000 for the addition of a
Bristol-Tolliver Park Basketball Court
August 19, 2025
Page 2
5
2
3
9
basketball court (Exhibit 1). The basketball court will provide enhanced recreational
benefits to the community.
On March 18, 2025, City Council awarded a non-federalized construction contract to
Legion Contractors, Inc. (Legion) for the Bristol-Tolliver Street Urban Greening Project.
The project is currently under construction and is to be completed in February 2026.
Staff recommends adding the FY 25-26 budget allocation of $115,000 of local funds to
the existing construction project and executing a change order for the installation of the
concrete pad and electrical portion of the work for the basketball court.
The current construction contract with Legion Contractors, Inc., is not federalized and
therefore cannot utilize the $176,000 of CDBG Federal funds. It will be necessary for
the City to separately bid out and procure a construction contract via a federally
compliant process and award a separate federalized contract for the remaining work to
complete the basketball court, which includes installation of the lighting control panel,
sports lighting, and striping/surfacing. The $176,000 will be sufficient for completing the
scope of work and any unused CDBG funding will be returned to the Community
Development Agency upon completion of the project.
The recommended action will increase the existing construction contact with Legion by
$115,000. As indicated in the Cost Analysis (Exhibit 2) and as summarized in the table
below, $176,000 of CDBG Federal funds are also included in the table below for
completion of the basketball court, for a new total estimated construction delivery cost of
$4,872,808.
Project Item Current
Total
Additional
Funding New Total
Construction Contract Bid Amount $3,808,800 $0 $3,808,800
Construction Administration,
Inspection, and Testing $392,128 $0 $392,128
Basketball Court Change Order (to
be performed under existing
construction contract)
$0 $115,000 $115,000
Remainder of Basketball Court (to be
performed by others under separate
Federal contract) – CDBG funds
$0 $176,000 $176,000
Contingencies $380,880 $0 $380,880
TOTAL ESTIMATED
CONSTRUCTION DELIVERY COST $4,581,808 $291,000 $4,872,808
Staff will issue a Request for Proposals (RFP) to procure a contractor via a federally
compliant process and award a separate federalized contract to utilize the $176,000 of
CDBG federal funding for the remaining work to complete the basketball court. This
Bristol-Tolliver Park Basketball Court
August 19, 2025
Page 3
5
2
3
9
includes installation of the lighting control panel, sports lighting, and striping/surfacing.
This work is anticipated to be completed in February 2026.
ENVIRONMENTAL IMPACT
There is no environment impact associated with this action. CEQA determination for the
project was made under previous City Council Action on March 18, 2025 and Staff filed
Categorical Exemption Environmental Review No. ER-2024-110. The recommended
actions are exempt from further review pursuant to Sections 15303 (Class 3), 15304
(Class 4), and 15332 (Class 32) of the CEQA guidelines as the project constitutes
construction of a limited number of small facilities or structures, minor alterations to land
which do not involve the removal of trees, and an in-fill development project.
FISCAL IMPACT
As indicated in the Cost Analysis, the new total estimated construction delivery cost of
the project is $4,872,808, which includes the construction contract, contract
administration, inspection, testing, an authorized contingency, and separate CDBG
Federal contract to complete the basketball court.
The following table summarizes funds budgeted and available in current FY 25-26 for
expenditure to complete construction of this project.
Fiscal
Year
Accounting Unit -
Account No.
(Project No.)
Fund
Description
Accounting Unit
- Account No.
Description
Amount
2025-26 31413260-66220
(24-6600)
Residential
Development
District 4
Acquisition &
Development –
Improvements
Other Than
Buildings
$115,000
2025-26 13518783-66220
(25-XXXX)
Community
Development
Block Grant
CDBG Programs,
Improvements
Other Than
Building
$176,000
Total $291,000
EXHIBIT(S)
1. Bristol-Tolliver Basketball Court FY 2025-26 CIP Worksheet
2. Cost Analysis
Submitted By: Rudy Rosas, Acting Executive Director of Public Works
Approved By: Alvaro Nuñez, City Manager
CITY OF SANTA ANA FY 25/26CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The Bristol Specific Plan designated the parcel on the corner of
Bristol Street and Tolliver Street as park land. This project will
transform approximately 1.25-acres of vacant, City-owned parcels
into a new neighborhood park. It will include features such as play
equipment, adult fitness equipment and a basketball court.
PROJECT NEED:
This project will enhance recreational opportunities for the community.
PROJECT TITLE:
Bristol & Tolliver Park - Basketball
Court
PROJECT CATEGORY:
City & Park Facility Improvements
Park Facility
LOCATION MAP
AGENCY:DIVISION:CONTACT:DATE:
Public Works Parks, Fleet & Facilities Mike Ortiz, Deputy PW Director / Parks, Fleet, and
Facilities
11-Jul-2025
PROJECT COSTS FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32
Construction 291,000 ------
TOTAL 291,000 ------
SOURCE OF FUNDS FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32
A & D District 4 115,000 ------
CDBG Programs 176,000 ------
TOTAL 291,000 ------
Construction Contract 3,808,800$
Construction Administration 230,000$
75,000$
87,128$
115,000$
176,000$
Contingencies 380,880$
TOTAL ESTIMATED CONSTRUCTION COSTS 4,872,808.00$
CONSTRUCTION OF PROJECT NO. 24-6600: Bristol-Tolliver Street Urban Greening Project
COST ANALYSIS
Inspection
Testing
Basketball Court Change Order (to be performed under existing construction
contract)
Remainder of Basketball Court (to be performed by others under separate Federal
contract)