HomeMy WebLinkAboutItem 19 - Cabrillo Park Restroom and Concession Building Improvements Project Public Works Agency www.santa-ana.gov/pwa Item # 19 City of Santa Ana 20 Civic Center Plaza, Santa Ana, CA 92701 Staff Report September 15, 2026 TOPIC: Award of an Agreement for the Cabrillo Park Restroom and Concession Building Improvements Project AGENDA TITLE Agreement with A's Construction to Provide Restroom and Concession Building Design- Build Services at Cabrillo Park (Project No. 27-6004) (General Fund) RECOMMENDED ACTION 1. Authorize the City Manager to execute an agreement with Bruce Anderson Enterprises, Inc. DBA A's Construction to design and build the Cabrillo Park Restroom and Concession Building Improvement Project for an amount not to exceed $650,000, for a term beginning September 15, 2026 and expiring December 31, 2027, with the option for one, one-year extension (Agreement No. A-2026-XXX). 2. Determine that, pursuant to the California Environmental Quality Act, the recommended actions are exempt from further review. Categorical Exemption Environmental Review No. ER 2026-53 will be filed for Project No. 27-6004. GOVERNMENT CODE §84308 APPLIES: Yes DISCUSSION The Public Works Agency oversees the maintenance and improvements of the City's park facilities to ensure they remain safe, functional, and accessible for the public. Cabrillo Park is a neighborhood park in Santa Ana that provides recreational opportunities for residents through amenities including sports fields, playgrounds, picnic areas, walking paths, and a concession and restroom building that supports daily park activities and community use. The existing restroom and concession building at Cabrillo Park has reached the end of its useful life and requires significant improvements to meet current Americans with Disabilities Act (ADA) accessibility standards and current building codes. City Council approved a capital improvement project to upgrade the Cabrillo Park restroom and concession building as part of the fiscal year 2026/27 Budget and Capital Improvement Program. The project includes renovation of the existing 490 square foot restroom and Award of an Agreement for the Cabrillo Park Restroom and Concession Building Improvements Project September 15, 2026 Page 2 625 square foot concession facilities; utility investigations and upgrades; selective demolition, structural, civil, architectural, plumbing, electrical, and mechanical improvements; replacement of approximately 3,800 square feet of adjacent sidewalk; and associated site restoration. The project will also include evaluation of restroom configurations during the design phase to determine the most appropriate layout for accessibility, functionality, maintenance, and long-term community use. Construction activities will be coordinated to minimize disruptions to park patrons and will include temporary public restroom facilities, accessible pedestrian access, and site security throughout construction. Upon completion, the improvements will provide a modern, code-compliant, and accessible facility that enhances the overall functionality and user experience at Cabrillo Park. Request for Proposals (RFP) No. 26-012 was advertised on March 20, 2026 on the City's online bid management and publication system, PlanetBids. A summary of vendor participation and results is as follows: 2,685 Vendors notified 6 Santa Ana vendors notified 105 Vendors downloaded the bid packet 2 Bids received 1 Bid received from Santa Ana vendor Proposals were opened on May 21, 2026 and evaluated. Two proposals were submitted by the RFP deadline and both proposals were determined to be responsive to the specifications and met the City's requirements. A selection committee comprised of Public Works Agency staff reviewed and evaluated the proposals based on the criteria established in the RFP. The final rankings were as follows: Firm ity Rankin A's Construction Santa Ana, CA 1 Lo hmani & Associates, Inc. Playa del Rey, CA 12 Staff recommends awarding an agreement to the highest-ranked firm, A's Construction (Exhibit 1). A's Construction has completed similar public works projects for other agencies, including restroom and ADA renovations for the City of Long Beach and City of Santa Monica, and a community center renovation for the City of Placentia that included new restrooms and a kitchen/concession area, demonstrating relevant experience with restroom, ADA, concession, and other public facility improvements. A's Construction has previously performed work as a prime contractor for the City of Santa Ana within the past two years, including the Civic Center Wayfinding and Bristol-Edinger Parking Lot Resurfacing and Restriping projects, which were satisfactorily completed, and has also served as an on-call PCC and asphalt contractor. The selected firm demonstrated extensive experience with public works construction projects, strong Award of an Agreement for the Cabrillo Park Restroom and Concession Building Improvements Project September 15, 2026 Page 3 technical capabilities, clear communication, and strict adherence to schedule and budget. Project Schedule and Contract Time The project completion date is December 2027, barring unforeseeable conditions such as rain, natural disasters, or other delays beyond the control of the City and of the Contractor. The contract time for this project, from design to construction completion is approximately one-year, as specified in the proposal documents. The actual completion date will depend on the contractor's schedule, material procurement timelines, and any unforeseen delays. The proposed agreement includes a one-year extension option to provide flexibility should additional time be needed to complete the project due to unforeseen conditions. Based on a typical project timeline, the estimated project completion is provided below. Project Milestones Milestone Estimated Notes Completion Date Administrative Startup September 2026 Contract execution, bonds, insurance Design, Plan Check and October 2026 Utility verification and field Permitting research to finalize design. Plan check and permitting process. Material Procurement April 2027 Procurement may take place concurrently with construction. Contractor Mobilization May 2027 Start of construction activities. Project Completion December 2027 Based on 160 working days. The Cabrillo Park Restroom and Concession Building Improvements project was approved by the City Council as part of the Fiscal Year 2026-27 Capital Improvement Program and budget. Funds are budgeted and available to support the project. ENVIRONMENTAL IMPACT Pursuant to the California Environmental Quality Act (CEQA), the recommended actions are exempt from further review pursuant to Section 15301 (b) of the CEQA Guidelines for projects consisting of repair and maintenance of existing public facilities. The proposed project continues to meet these parameters of the CEQA Guidelines, and Categorical Exemption Environmental Review No. ER-2026-53 will be filed for Project 27-6004 (Exhibit 2). Award of an Agreement for the Cabrillo Park Restroom and Concession Building Improvements Project September 15, 2026 Page 4 FISCAL IMPACT Funds are available for expenditure in the Fiscal Year 2026-27. Any remaining balances not expended by the end of the fiscal year will be presented to City Council for approval of carryovers to Fiscal Year 2027-28. Accounting Fiscal Unit—Account Fund Accounting Unit, Amount Year No. Description Account Description Project No. CURRENT BUDGET 01117607-66220 PWA Services, 2026-27 (27-6004) General Fund Improvements Other $650,000 Than Buildings TOTAL $650,000 EXHIBIT(S) 1. Agreement with A's Construction 2. Environmental Determination Submitted By: Rodolfo Rosas, P.E., Acting Executive Director of Public Works Approved By: Alvaro Nunez, City Manager Exhibit 1 AGREEMENT WITH A'S CONSTRUCTION TO PROVIDE DESIGN-BUILD SERVICES FOR CABRILLO PARK RESTROOM AND CONCESSION IMPROVEMENTS THIS AGREEMENT is made and entered into on this 15th day of September,2026 by and between Bruce Anderson Enterprises,Inc., a California corporation,DBA A's Construction("Contractor"), and the City of Santa Ana, a charter city and municipal corporation organized and existing under the Constitution and laws of the State of California ("City"). RECITALS A. On March 20, 2026, City issued Request for Proposal ("RFP") No. 26-012, by which it sought qualified consultants to provide Design-Build Services for Cabrillo Park restroom and concession building improvements. B. Contractor submitted a responsive proposal that was selected by the City. Contractor represents that it is able and willing to provide the services described in the scope of work that was included in RFP 26-012. C. In undertaking the perfonnance of this Agreement, Contractor represents that it is knowledgeable in its field and that any services performed by Contractor under this Agreement will be performed in compliance with such standards as may reasonably be expected from a professional consulting firm in the field. NOW THEREFORE, in consideration of the mutual and respective promises, and subject to the terms and conditions hereinafter set forth, the parties agree as follows: 1. SCOPE OF SERVICES Contractor shall perform during the term of this Agreement, the tasks and obligations including all labor, materials, tools, equipment, and incidental customary work required to fully and adequately complete the services described and set forth in the scope of work that was included in RFP No. 26-012, which is attached hereto as Exhibit A and incorporated by reference. 2. COMPENSATION a. City agrees to pay, and Contractor agrees to accept as total payment for its services for City, the rates and charges identified in Exhibit B, which is attached hereto and incorporated by reference. The total compensation for services provided shall not exceed $650,000 during the term of the Agreement, including any extension periods. The sum is comprised of(1) a base bid amount of$591,000, and (2) a contingency in the amount of$59,000 for additional services at the City's sole discretion. b. Payment by City shall be made within forty-five (45) days following receipt of proper invoice evidencing work performed, subject to City accounting procedures. City and Contractor agree that all payments due and owing under this Agreement shall be made through Automated Clearing House (ACH)transfers. Contractor agrees to execute the Page 1 of 9 City's standard ACH Vendor Payment Authorization and provide required documentation. Upon verification of the data provided, the City will be authorized to deposit payments directly into Contractor's account(s) with financial institutions. Payment need not be made for work which fails to meet the standards of performance set forth in the Recitals which may reasonably be expected by City. 3. TERM This Agreement shall commence on September 15,2026 and expire on December 31,2027, unless terminated earlier in accordance with Section 16, below. The term of this Agreement may be extended for an additional one-year period upon a writing executed by the City Manager and the City Attorney. 4. PREVAILING WAGES Contractor is aware of the requirements of California Labor Code Section 1720, et seq., and 1770, et seq., as well as California Code of Regulations, Title 8, Section 16000, et seq., ("Prevailing Wage Laws"), which require the payment of prevailing wage rates and the performance of other requirements on"public works" and "maintenance"projects. If the services being performed are part of an applicable "public works" or"maintenance"project, as defined by the Prevailing Wage Laws, and the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. 5. INDEPENDENT CONTRACTOR Contractor shall, during the entire term of this Agreement, be construed to be an independent contractor and not an employee of the City. This Agreement is not intended nor shall it be construed to create an employer-employee relationship, a joint venture relationship, or to allow the City to exercise discretion or control over the professional manner in which Contractor performs the services which are the subject matter of this Agreement; however, the services to be provided by Contractor shall be provided in a manner consistent with all applicable standards and regulations governing such services. Contractor shall pay all salaries and wages, employer's social security taxes, unemployment insurance and similar taxes relating to employees and shall be responsible for all applicable withholding taxes. 6. OWNERSHIP OF MATERIALS This Agreement creates a non-exclusive and perpetual license for City to copy, use, modify, reuse, or sublicense any and all copyrights, designs, and other intellectual property embodied in plans, specifications, studies, drawings, estimates, and other documents or works of authorship fixed in any tangible medium of expression, including but not limited to, physical drawings or data magnetically or otherwise recorded on computer diskettes,which are prepared or caused to be prepared by Contractor under this Agreement ("Documents & Data"). Contractor shall require all subcontractors to agree in writing that City is granted a non-exclusive and Page 2 of 9 perpetual license for any Documents & Data the subcontractor prepares under this Agreement. Contractor represents and warrants that Contractor has the legal right to license any and all Documents & Data. Contractor makes no such representation and warranty in regard to Documents & Data which were provided to Contractor by the City. City shall not be limited in any way in its use of the Documents and Data at any time, provided that any such use not within the purposes intended by this Agreement shall be at City's sole risk. 7. INSURANCE Insurance requirements are attached hereto as Exhibit C and incorporated by reference. 8. INDEMNIFICATION Contractor agrees to defend, and shall indemnify and hold harmless the City, its officers, agents, employees, contractors, special counsel, and representatives from liability: (1)for personal injury, damages,just compensation,restitution,judicial or equitable relief arising out of claims for personal injury, including death, and claims for property damage, which may arise from the negligent operations of the Contractor, its subcontractors, agents, employees, or other persons acting on its behalf which relates to the services described in section 1 of this Agreement; and (2) from any claim that personal injury, damages,just compensation, restitution,judicial or equitable relief is due by reason of the terms of or effects arising from this Agreement. This indemnity and hold harmless agreement applies to all claims for damages,just compensation,restitution,judicial or equitable relief suffered, or alleged to have been suffered,by reason of the events referred to in this Section or by reason of the terms of, or effects, arising from this Agreement. The Contractor further agrees to indemnify, hold harmless, and pay all costs for the defense of the City, including fees and costs for special counsel to be selected by the City, regarding any action by a third party challenging the validity of this Agreement, or asserting that personal injury, damages, just compensation, restitution,judicial or equitable relief due to personal or property rights arises by reason of the terms of, or effects arising from this Agreement. City may make all reasonable decisions with respect to its representation in any legal proceeding.Notwithstanding the foregoing, to the extent Contractor's services are subject to Civil Code Section 2782.8, the above indemnity shall be limited, to the extent required by Civil Code Section 2782.8, to claims that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of the Contractor. 9. INTELLECTUAL PROPERTY INDEMNIFICATION Contractor shall defend and indemnify the City, its officers, agents, representatives, and employees against any and all liability, including costs, for infringement of any United States' letters patent,trademark, or copyright infringement,including costs,contained in the work product or documents provided by Contractor to the City pursuant to this Agreement. 10. RECORDS Contractor shall keep records and invoices in connection with the work to be performed under this Agreement. Contractor shall maintain complete and accurate records with respect to the costs incurred under this Agreement and any services, expenditures, and disbursements Page 3 of 9 charged to the City for a minimum period of three (3) years, or for any longer period required by law, from the date of final payment to Contractor under this Agreement. All such records and invoices shall be clearly identifiable. Contractor shall allow a representative of the City to examine, audit, and make transcripts or copies of such records and any other documents created pursuant to this Agreement during regular business hours. Contractor shall allow inspection of all work, data, documents, proceedings, and activities related to this Agreement for a period of three (3) years from the date of final payment to Contractor under this Agreement. 11. CONFIDENTIALITY If Contractor receives from the City information which due to the nature of such information is reasonably understood to be confidential and/or proprietary, Contractor agrees that it shall not use or disclose such information except in the performance of this Agreement, and further agrees to exercise the same degree of care it uses to protect its own information of like importance, but in no event less than reasonable care. "Confidential Information"shall include all nonpublic information. Confidential information includes not only written information, but also information transferred orally, visually, electronically, or by other means. Confidential information disclosed to either party by any subsidiary and/or agent of the other party is covered by this Agreement. The foregoing obligations of non-use and nondisclosure shall not apply to any information that(a) has been disclosed in publicly available sources; (b)is, through no fault of the Contractor disclosed in a publicly available source; (c) is in rightful possession of the Contractor without an obligation of confidentiality; (d) is required to be disclosed by operation of law; or (e) is independently developed by the Contractor without reference to information disclosed by the City. 12. CONFLICT OF INTEREST CLAUSE a. Contractor covenants that it presently has no interests and shall not have interests,direct or indirect,which would conflict in any manner with performance of services specified under this Agreement. b. No immediate family members of either the Mayor, City Council Member, or any appointed City Official, including appointed board and commission members, as defined under the City's Municipal Code, whose position with the City shall award or influence the award of this Agreement, or any competing contract or amendment thereof, shall be employed in any capacity by the Contractor or have any other direct or indirect financial benefit or interest in this Agreement. c. The section also prohibits the awarding of any agreement, contract, grant, or any amendment to those awards, to any former full-time employee for one-year from date of employee separation except for any CalPERS retiree as authorized by City Council resolution d. The Contractor must comply with all conflict of interest laws, ordinances, and regulations now in effect or hereafter to be enacted during the term of this Agreement. The Contractor warrants that it is not now aware of any facts which conflict with the Page 4 of 9 prohibitions defined above. If the Contractor hereafter becomes aware of any facts that might reasonably be expected to create a conflict of interest, it must immediately make full written disclosure of such facts to the City. Full written disclosure must include, but is not limited to, identification of all persons implicated and a complete description of all relevant circumstances. Failure to comply with the provisions of this paragraph will be a material breach of this Agreement. e. Contractor covenants that none of its directors, officers, employees, or agents shall participate in selecting or administrating any subcontract supported(in whole or in part) by City funds stemming from the Agreement where the awarding of the subcontract has any direct or indirect financial benefit or interest to any individual, as defined in subsections (b) and(c) above. 13. NON-DISCRIMINATION Contractor shall not discriminate because of race, color, creed, religion, sex,marital status, sexual orientation, gender identity, gender expression, gender, medical conditions, genetic information, or military and veteran status, age, national origin, ancestry, or disability, as defined and prohibited by applicable law, in the recruitment, selection, teaching, training, utilization, promotion, termination or other employment related activities or any services provided under this Agreement. Contractor affirms that it is an equal opportunity employer and shall comply with all applicable federal, state and local laws and regulations. 14. EXCLUSIVITY AND AMENDMENT This Agreement represents the complete and exclusive statement between the City and Contractor, and supersedes any and all other agreements, oral or written, between the parties. In the event of a conflict between the terms of this Agreement and any attachments hereto, the terms of this Agreement shall prevail. This Agreement may not be modified except by written instrument signed by the City and by an authorized representative of Contractor. The parties agree that any terms or conditions of any purchase order or other instrument that are inconsistent with, or in addition to, the terms and conditions hereof, shall not bind or obligate Contractor or the City. Each party to this Agreement acknowledges that no representations, inducements, promises or agreements, orally or otherwise, have been made by any party, or anyone acting on behalf of any party, which is not embodied herein. 15. ASSIGNMENT Inasmuch as this Agreement is intended to secure the specialized services of Contractor, Contractor may not assign, transfer, delegate, or subcontract any interest herein without the prior written consent of the City and any such assignment, transfer, delegation or subcontract without the City's prior written consent shall be considered null and void. Nothing in this Agreement shall be construed to limit the City's ability to have any of the services which are the subject to this Agreement performed by City personnel or by other Contractors retained by City. 16. TERMINATION Page 5 of 9 This Agreement may be terminated by the City upon thirty (30) days written notice of termination. In such event, Contractor shall be entitled to receive and the City shall pay Contractor compensation for all services performed by Contractor prior to receipt of such notice of termination, subject to the following conditions: a. As a condition of such payment, the Executive Director may require Contractor to deliver to the City all work product(s) completed as of such date, and in such case such work product shall be the property of the City unless prohibited by law, and Contractor consents to the City's use thereof for such purposes as the City deems appropriate. b. Payment need not be made for work which fails to meet the standard of performance specified in the Recitals of this Agreement. 17. WAIVER No waiver of breach, failure of any condition, or any right or remedy contained in or granted by the provisions of this Agreement shall be effective unless it is in writing and signed by the party waiving the breach, failure, right or remedy. No waiver of any breach, failure or right, or remedy shall be deemed a waiver of any other breach, failure, right or remedy, whether or not similar, nor shall any waiver constitute a continuing waiver unless the writing so specifies. 18. JURISDICTION-VENUE This Agreement has been executed and delivered in the State of California and the validity, interpretation, performance, and enforcement of any of the clauses of this Agreement shall be determined and governed by the laws of the State of California. Both parties further agree that Orange County, California, shall be the venue for any action or proceeding that may be brought or arise out of, in connection with or by reason of this Agreement. 19. PROFESSIONAL LICENSES Contractor shall, throughout the tenn of this Agreement, maintain all necessary licenses, permits, approvals, waivers, and exemptions necessary for the provision of the services hereunder and required by the laws and regulations of the United States, the State of California, the City of Santa Ana and all other governmental agencies. Contractor shall notify the City immediately and in writing of its inability to obtain or maintain such permits, licenses, approvals, waivers, and exemptions. Said inability shall be cause for termination of this Agreement. 20. NOTICE Any notice, tender, demand, delivery, or other communication pursuant to this Agreement shall be in writing and shall be deemed to be properly given if delivered in person or mailed by first class or certified mail, postage prepaid, or sent by fax or other telegraphic communication in the manner provided in this Section, to the following persons: To City: Page 6 of 9 City Clerk City of Santa Ana 20 Civic Center Plaza(M-30) P.O. Box 1988 Santa Ana, CA 92702-1988 Fax: (714) 647-6956 With courtesy copies to: Executive Director, Public Works Agency City of Santa Ana 20 Civic Center Plaza(M-21) P.O. Box 1988 Santa Ana, California 92702 Fax: (714) 647-5635 To Contractor: A's Construction Attn: Andres Aguilar, President 1662 W. McFadden Avenue Santa Ana, CA 92704 A party may change its address by giving notice in writing to the other party. Thereafter, any communication shall be addressed and transmitted to the new address. If sent by mail, communication shall be effective or deemed to have been given three (3) days after it has been deposited in the United States mail, duly registered or certified, with postage prepaid, and addressed as set forth above. If sent by fax, communication shall be effective or deemed to have been given twenty-four (24)hours after the time set forth on the transmission report issued by the transmitting facsimile machine, addressed as set forth above. For purposes of calculating these time frames, weekends, federal, state, County or City holidays shall be excluded. 21. CALIFORNIA AIR RESOURCES BOARD (GARB) COMPLIANCE Contractor shall comply, and shall ensure all subcontractors comply, with all applicable requirements of the most current version of the regulations imposed by California Air Resources Board ("CARB") including, without limitation, all applicable terms of Title 13, California Code of Regulations Division 3, Chapter 9 and all pending amendments ("Regulation"). Throughout the Project, and for three (3) years thereafter, Contractor shall make available for inspection and copying any and all documents or information associated with Contractor and its subcontractors' fleets including, without limitation, the Certificates of Reported Compliance ("CRCs"), fuel/refueling records, maintenance records, emissions records, and any other Page 7 of 9 information the Contractor is required to produce, keep or maintain pursuant to the Regulation upon two (2) calendar days' notice from the City. Contractor shall be solely liable for any and all costs associated with compliance with the Regulation as well as for any and all penalties, fines, damages, or costs associated with any and all violations, or failures to comply with the Regulation. Contractor shall defend, indemnify and hold harmless the City, its officials, officers, employees and authorized volunteers free and harmless from any claims, liabilities, costs, penalties or interest arising out of any failure or alleged failure to comply with the Regulation. 22. COMMUNITY WORKFORCE AGREEMENT Contractor shall adhere to the City's Community Workforce Agreement(CWA), apre-hire collective bargaining agreement, which establishes the labor relations policies and procedures for Contractor to follow in the crafts persons employed to complete the Project as more fully described in the CWA. The CWA may be found on the City's website at: CWA City of Santa Ana 12-20- 2023 23. MISCELLANEOUS PROVISIONS a. Each undersigned represents and warrants that its signature herein below has the power, authority and right to bind their respective parties to each of the terms of this Agreement, and shall indemnify City fully, including reasonable costs and attorney's fees, for any injuries or damages to City in the event that such authority or power is not, in fact, held by the signatory or is withdrawn. b. The Agreement is the final and complete agreement and any prior or contemporaneous agreements for similar services between the Parties is superseded by this Agreement. This shall not apply where the Parties are currently engaged and Contractor is providing services not contemplated by this Agreement. C. All Exhibits referenced herein and attached hereto shall be incorporated as if fully set forth in the body of this Agreement. [signatures on following page] Page 8 of 9 IN WITNESS WHEREOF, the parties hereto have executed this Agreement the date and year first above written. ATTEST: CITY OF SANTA ANA Jennifer L. Hall Alvaro Nunez City Clerk City Manager APPROVED AS TO FORM: SONIA R. CARVALHO CONTRACTOR: City Attorney By:/ //Ojv� Z�� �1 Kyle ellesen By:Andres Aguilar Assistant City Attorney Title:President RECOMMENDED FOR APPROVAL: /&(OG o Rosas Rodolfo Rosas(Aug 31,2026 14:04:29 PDT) Rodolfo Rosas, P.E. Acting Executive Director Public Works Agency Page 9 of 9 EXHIBIT A w � CITY OF SANTA ANA EXHIBIT 1 - SCOPE OF SERVICES INTRODUCTION/PROJECT The City of Santa Ana (CSA) is soliciting proposals from qualified firms to provide Progressive Design-Build services for the renovation of the existing Cabrillo Park restrooms and concession room to bring the facilities into compliance with current ADA accessibility standards and applicable building codes.The project will also include associated site improvements, utility work,and replacement of approximately 3,800 square feet of surrounding sidewalk. For purposes of this Request for Proposals(RFP),any reference to"Consultant" or"Contractor"shall be interpreted to mean the Progressive Design-Builder(DB)team.This interpretation is intended solely for the purposes of this solicitation and shall not modify or limit any definitions contained in the resulting Agreement. The scope of work includes, but is not limited to, utility investigations (including sewer, water, and electrical systems); civil and structural engineering services; preparation of plans, specifications, and cost estimates; selective demolition of the existing restroom facilities; and construction of the renovated restroom and concession facilities. Work will include installation of structural elements, lighting, plumbing systems and fixtures, restroom accessories, and interior and exterior building finishes.The project will also include utility connections,site restoration,replacement of approximately 3,800 square feet of adjacent sidewalk,and completion of related site improvements necessary to support the renovated facilities. Existing as-built drawings for the facility and associated utilities may be incomplete or unavailable. The Design-Build team shall be responsible for conducting field verification, investigations, and necessary documentation to confirm existing conditions and utilities required to complete the design and construction of the project. It is expected that selected Design-Builder will provide comprehensive services for the planning, design, and construction of Cabrillo Park restrooms and concession building in two phases under a single Progressive Design-Build Agreement. Phase I—Preconstruction Services will include, but are not limited to: A. EXISTING FACILITY ASSESSMENT AND RESTROOM CONFIGURATION EVALUATION. As part of the design and investigation services, the Design-Build team shall conduct a comprehensive assessment of the existing restroom building, structural systems, utilities and spatial layout to determine feasible renovation approaches. The DB team shall evaluate the existing facility conditions, operating needs of the park, anticipated user demand,accessibility requirements and applicable building and plumbing codes. a. Based on this assessment the DB team shall analyze and present restroom configuration options, including but not limited to: • Single-user/all-gender restroom stalls • Traditional separate men's and women's restroom facilities b. The DB team shall evaluate each option in terms of code compliance,ADA accessibility, operation efficiency, maintenance considerations,safety,construction feasibility within the existing building footprint, lifecycle costs,and community usability.The analysis shall also consider fixture count requirements, circulation, privacy,security,and potential impacts to utilities and building systems. The DB Team shall present the findings and recommended approach to the City, including concept layouts,cost implications,and operational considerations,to assist the City in determining the most appropriate restroom configuration for the Cabrillo Park facility and the surrounding community.The final configuration shall be determined in coordination with the City prior to advancing into final design. w � CITY OF SANTA ANA B. EXISTING DRAWINGS. The Design-Build team shall be responsible for conducting field verification, investigations,and necessary documentation to confirm existing conditions and utilities required to complete the design and construction of the project. C. PROJECT COORDINATION. The Consultant shall be fully responsible for the overall management and coordination for the project,which includes, but is not limited to project development team meetings, liaison with affected agencies, and utility companies. Prepare progress reports and schedule, secure permits for all field studies and any other required permits from other agencies. Other agencies include, but are not limited to PWA/Park Maintenance Division and Planning& Building Agency. D. RECORDS RESEARCH. Research all information pertinent to the project including, but not limited to existing field conditions, as-built/record drawings, right-of-way data and all future improvement plans adjacent to or affecting the project site. The selected firm shall identify all existing and proposed facilities within the projects limits and highlight any potential conflicts. E. UTILITY COORDINATION a. General: The Consultant shall be responsible for all utility coordination efforts, including but not limited to; coordination with SCE for any electrical service connections,water service connections for restroom fixtures, irrigation and sewer connections for toilet,sink and floor drains. b. Electrical:The existing restroom building currently houses lighting control panels and an electric meter which provides service for the building and park lighting. c. Sewer: Consultant shall review the sewer coverage requirement conduct survey, per Section F, to determine existing invert elevations at point of connection,and adequacy of existing sewer line flow. This information, along with as-built drawings will determine building elevation and affect final site plan. F. PRELIMINARY DESIGN. The consultant shall organize a kick-off meeting with City staff to discuss the project background, site layout, potential elements and issues, park maintenance standards (a preliminary list is included as an attachment to this RFP Scope of Work), project schedule, and review of existing information. The Consultant shall provide the design, construction, and delivery of renovated restrooms and concession stand, including coordination to ensure conformance with project requirements. G. SURVEY.On-the-ground field topographical survey work is required for the Consultant(and/or the Consultant's Subconsultant) to identify existing horizontal and vertical features, and sewer elevations needed for the project. H. CIVIL ENGINEERING PLANS. The consultant shall be responsible for the preparation of any civil engineering plans required for this project including, but not limited to,the following; Horizontal and Vertical Control plan, On-site Grading and Drainage plan and Site Utility Plan. These plans should identify and address building elevations, utility connections, sewer flow, grade issues, and matching existing site conditions. Plans shall be reviewed and approved by CSA prior to implementation of work. Engineering design shall be compatible and in accordance with the CSA Standard Plans and the latest version of the "Greenbook" Standard Special Provisions for Public Works Construction. I. SITE, LANDSCAPE AND IRRIGATION PLANS. Site improvements around perimeter shall be coordinated with civil engineering plans, which reflect survey information. The consultant shall be responsible for the preparation of any landscape architectural plans relating these site improvements including, the following; concrete hardscape (replacement of cracked and damaged concrete panels in surrounding restroom area to ensure ADA pathway requirements are met), landscape (as applies), irrigation modifications (as applies), Consultant shall ensure grade changes meet ADA requirements but at same time,strive to design layout which minimizes ramping and handrails. Plans shall be reviewed and approved by CSA prior to implementation of work. w � CITY OF SANTA ANA J. ELECTRICAL PLANS.The consultant shall be responsible for the preparation of any electrical plans required for this project including, but not limited to,the following; incorporation of SCE design, electrical panel upgrades, relocation of existing panels, controllers,switchgear,etc. K. FINAL PLANS The Consultant shall submit final signed plans and calculations as electronic files(CADD and .pdf) for CSA review and approval and then submit to planning and building department. Phase II—Construction Services will include, but not limited to: Following completion of Phase 1 services and upon written authorization from the City, the Design-Build (DB) Team shall proceed with Phase 2— Final Design and Construction. During this phase, the DB Team shall work collaboratively with the City to finalize the design,establish the construction scope,and develop a Guaranteed Maximum Price(GMP)or negotiated construction price,as determined by the City. A key objective of Phase 2 will be to identify and implement the most cost-effective construction approach necessary to renovate the existing restroom and concession facilities so that they meet all applicable building codes, accessibility requirements under the Americans with Disabilities Act(ADA),and other regulatory requirements.The DB Team shall work with the City to evaluate design options, construction methods, and scope alternatives to determine the minimum construction investment necessary to achieve full code and ADA compliance while maintaining functionality,durability,and safety of the facility. As part of this process,the DB Team shall prepare detailed construction cost estimates and cost analyses to support decision- making.The DB Team shall also develop and submit a comprehensive Schedule of Values(SOV) identifying and itemizing the projected construction costs associated with the project. At a minimum, the Schedule of Values shall include cost breakdowns for major construction components, including but not limited to: L. SCHEDULE OF VALUES: a. Item Description Qty Unit Unit Price Amount Demolition 1 Asbestos Abatement 1 LS $ $ 2 Remove flooring 1 LS $ $ 3 Remove walls 1 LS $ $ 4 Remove doors 1 LS $ $ 5 Remove restroom appliances 1 LS $ $ Concrete (Interior) 6 Saw cut concrete slab (Restroom 4200 SF $ $ building) 7 New concrete slab (Restroom 4200 SF $ $ building) (9) CITY OF SANTA ANA Item Description Qty Unit Unit Price Amount 8 Saw cut concrete slab (Concession 5,260 SF building) 9 New concrete slab (Concession 5,250 SF building) Metal 10 Framing 1 LS $ $ Rough Carpentry/Framing 11 Rough carpentry 1 LS $ $ Thermal and Moisture Protection 12 Wall insulation 1 LS $ $ Doors &Windows 13 Doors 1 LS $ $ 14 Windows 1 LS $ $ Finishes 15 Drywall partitions 1 LS $ $ 16 Drywall ceiling finish 1 LS $ $ 17 Flooring finishes 1 LS $ $ 18 Paint 1 LS $ $ Specialties 19 Restroom Accessories 1 LS $ $ Plumbing 20 Water Closets 1 LS $ $ 21 Lav sinks 1 LS $ $ 22 Rough piping 1 LS $ $ (9) CITY OF SANTA ANA Item Description Qty Unit Unit Price Amount 23 Waste line 1 LS $ $ 24 Vent line 1 LS $ $ 25 Plumbing demo/cap 1 LS $ $ HVAC 26 HVAC Improvements 1 LS $ $ Electrical 27 Power 1 LS $ $ 28 New lighting 1 LS $ $ 29 Demo existing electrical 1 LS $ $ Site work Improvements 30 Landscape 1 LS $ $ 31 Irrigation 1 LS $ $ 32 Concrete sidewalk improvements 4275 SF $ $ M. CONSTRUCTION:SELECTIVE DEMOLITION,RENOVATION,SITE WORK,AND UTILITY CONNECTION a. Consultant is responsible for a design-build project,to deliver a set of renovated restrooms and concession building as described in this scope of Work, which includes selective demolition, site work, utility work, utility connections,and final site work. b. Construction schedule shall minimize park facilities closure. c. Consultant to provide temporary fencing around the area of work, taking care to ensure that there are accessible path of travel(s) from the parking lot to park equipment and sport courts for public use. The Consultant shall prepare a fencing layout and plan identifying fence locations, limits, and general configuration in accordance with project requirements. d. Consultant shall provide site security cameras after working hours while the project is actively under construction,ensuring a physical presence 24/7 while sites are in transition. e. Consultant shall provide temporary portable restrooms, including handwashing stations, for the public, while restroom facilities are closed for use. Portable restrooms are to receive routine maintenance as required to be acceptable for public use,at a minimum 3 days a week.Portable restrooms shall be accessible to the public throughout the duration of the project. f. The Consultant shall prepare and deliver to the City the final as-built plans incorporating field marked prints supplied by the City. Upon completion of construction, the City will submit field-marked prints to w � CITY OF SANTA ANA Consultant. Consultant shall incorporate all changes to the plans electronically with all necessary revision notations and submit to the City. g. Work will be subject to regular PWA inspections. h. Commissioning,testing,and project close-out. N. COMMUNITY WORKFORCE AGREEMENT (CWA) REQUIRMENTS The consultant shall be responsible for adhering to the requirements of the CWA agreement between the City of Santa Ana and Los Angeles/Orange Counties Building and Construction Trades Council and the Signatory Craft Councils and Unions.Refer to Exhibit IV:Community Workforce Agreement for the full agreement details. PAYMENT AND INVOICING: Phase 1-Design The City will compensate the Design-Build(DB)Team for Phase 1 Preconstruction and Design Services on a cost-reimbursable basis with a Not-to-Exceed (NTE)amount,as negotiated and approved by the City. Phase 1 services shall include, but are not limited to, project management,site investigations, utility verification,architectural and engineering design, preparation of plans and specifications,constructability reviews,cost estimating,development of design alternatives,and preparation of a proposed Guaranteed Maximum Price(GMP) and Schedule of Values(SOV) for Phase 2 construction services.The DB Team shall submit monthly invoices documenting actual labor hours,billing rates,subconsultant costs,and reimbursable expenses incurred during the performance of Phase 1 services.Compensation shall include a negotiated Design-Builder fee or markup, as approved by the City. Total compensation for Phase 1 services shall not exceed the authorized Not-to-Exceed amount unless otherwise approved in writing by the City. Phase 2—Final Design and Construction Services Upon completion of Phase 1 services and upon written authorization from the City,the DB Team may proceed with Phase 2 Final Design and Construction Services. Prior to commencing construction, the DB Team shall submit a Guaranteed Maximum Price (GMP) proposal to the City for review and approval.The GMP shall include all costs necessary to complete the project, including but not limited to labor, materials, equipment, subcontractor costs, general conditions, overhead, profit, allowances, contingencies, and all other costs associated with completion of the Work. The GMP proposal shall include a detailed Schedule of Values (SOV) identifying and itemizing construction costs by major project components. The Schedule of Values shall be organized in sufficient detail to allow the City to evaluate the cost of individual work elements and monitor construction progress. Upon approval of the GMP by the City, payments for Phase 2 construction services shall be made on a monthly progress payment basis, based on the percentage of work completed for each item in the approved Schedule of Values. The City shall retain statutory retention from each progress payment in accordance with applicable California Public Contract Code requirements. CITY RESPONSIBILITIES: The City will provide information in its possession relevant to the preparation of the required information in the RFP. The City will provide only the staff assistance and the documentation specifically in referred to herein. • Provide city standard plans and specifications • Provide access to existing building,as requested by consultant. • Furnish scope of work and provide general direction as needed for the assigned project. • All plan check coordination within the City • Facilitate meeting space and coordination and City facilities CONSULTANT RESPONSIBILITIES: CITY OF SANTA ANA • All work as described under Consultant Services(Section A-K), General Requirements and Payment& Invoicing. • Provide Bonds and Insurance as outlined in Attachment of this RFP. • Submit renewal of Certificate of Insurance 30 days before expiring. • Ensure Certificate of Insurance is current when submitting invoices. EXHIBIT B _ Addendum No. Two CITY OF SANTA ANA PRICE PROPOSAL FORM CABRILLO PARK IMPROVEMENTS PROPOSAL TO: City of Santa Ana 20 Civic Center Plaza Santa Ana, CA 92701 Proposal from: DESIGN-BUILDER A's Construction (Name of Firm Submitting Proposal) 1662 W. McFadden Avenue, Santa Ana, CA 92704 (Street Address, City, State, Zip Code) (714) 656-7421 (Telephone) Andres Aguilar, President/Owner/ Licensed Qualifier (Design-Builder Project Executive Name &Title) andres&asconst.org (Design-Builder Project Executive Email Address) (714) 656-7421 (Design-Builder Project Executive Telephone) May 21, 2026 (Date Submitted) ,. Addendum No. Two CITY OF SANTA ANA 1.0 PROPOSER'S REPRESENTATIONS Proposer, represents that a) it has the appropriate active Contractor's license required by the State of California; b) it has carefully read and examined the Proposal Documents for the proposed Work on this Project; c) it has examined the site of the proposed Work and all Reference Documents; d) it has become familiar with all the conditions related to the proposed Work, including the availability of labor, materials, and equipment; e)that all information and submittals provided as part of the prequalification process are accurate and correct; and f) Proposer and all Subcontractors, regardless of tier, are currently registered with the California Department of Industrial Relations pursuant to California Labor Code Section 1725.5 and 1771.1. Proposer hereby offers to furnish all labor, materials, equipment, tools,transportation, and services necessary to complete the proposed Work on this Project in accordance with the Contract Documents for the sums quoted. Proposer further agrees that it will not withdraw its Proposal within 180 days after the Proposal Deadline, and that, if it is selected as the apparent lowest responsive and responsible Proposer,that it will, after receipt of notice of selection, sign and deliver to City of Santa Ana the Design-Build Agreement in triplicate and furnish to City of Santa all items required by the Proposal Documents. If awarded the Contract, Proposer agrees to complete the proposed Work within the number of days specified in the Design-Build Agreement. 2.0 ADDENDA Proposer acknowledges that it is Proposer's responsibility to ascertain whether any Addenda have been issued and if so,to obtain copies of such Addenda from City of Santa Ana at the appropriate address stated. Proposer therefore agrees to be bound by all Addenda that have been issued for this Proposal. 3.0 DESIGN-BUILD ENTITY'S PRICE PROPOSAL $ 5 9 1 , 0 0 0 Addendum No. Two Price Proposal Spreadsheet DESIGN BUILDER/CONTRACTOR NAME: LUMP SUM BASE REF NO. TRADE DESCRIPTION PRICE TOTAL($) 00 GENERAL CONDITIONS,OH& FEE 00.1 General Expenses $ 12,000.00 _ 00.2 Supervision,Fringes,Taxes&Surcharges 00.3 Performance&Payment Bond 5,904.45 _ 00.4 Insurance 7,872.60 _ 00.5 All-Risk Builder's Risk Insurance 00.6 Fee 39,650.80 _ 00.7 Other: Subtotal: $ 77,396.00 01 GENERAL REQUIREMENTS 01.1 Design Fee(Phase 1) $ 01.2 Testing and Inspection 4,000.00 01.3 Allowances 01.4 Commissioning 01.5 Water Quality Management Plan 2,000.00 01.6 Mobilization 5,000.00 01.7 Temporary Facilities/Fencing 6,000.00 01.8 Off Site Staging 0.00 01.9 Hoist Facilities 01.10 Temporary Utilities 2,000.00 01.11 Cleaning 01.12 Protection&Safety 5,000.00 01.13 Demobilization 1,500.00 01.14 Other: 32,000.00 _ Subtotal: $ 191,655.00 03.1 Cast in Place Concrete $ 26,000.00 _ 03.2 Architectural Concrete 3,500.00 _ 03.3 Precast Architectural Concrete 03.4 Other: 0.00 Subtotal: $ 29,500.00 04 MASONRY 04.1 Unit Masonry $ 15,000.00 _ 04.2 Brick Veneer Masonry Subtotal: $ 15,000.00 1 of 6 Price Proposal Spreadsheet Addendum No. Two Price Proposal Spreadsheet 06 WOOD,PLASTICS,AND COMPOSITES 06.1 Miscellaneous Carpentry $ 5,000.00 _ 06.2 Sheathing 2,500.00 06.3 Other: Subtotal: $ 7,500.00 THERMAL AND MOISTURE PROTECTION 07.1 Thermal Insulation $ 3,000.00 _ 07.2 Roofing 13,500.00 _ 07.3 Sheet Metal Flashing and Trim 2,500.00 _ 07.4 Roof Accessories 07.5 Joint Sealants 1,500.00 07.6 Other: 0.00 _ Subtotal: $ 22,000.00 08.1 Doors Frames and Hardware $ 7,500.00 08.2 Windows 6,500.00 08.3 Other: Subtotal: $ 14,000.00 2 of 6 Price Proposal Spreadsheet Addendum No. Two Price Proposal Spreadsheet 09 FINISHES 09.1 Gypsum Board Assemblies $ 4,500.00 _ 09.2 Non-Structural Metal Framing 3,500.00 09.3 Portland Cement Plastering 4,000.00 09.4 Tiling 11,000.00 _ 09.5 Acoustical Panel Ceilings 09.6 Flooring 4,000.00 _ 09.7 Interior Painting 3,500.00 09.8 High-Performance Coatings 3,000.00 09.9 Other: Subtotal: $ 35,000.00 SPECIALTIES 10.1 Signage $ 2,000.00 10.2 Toilet Compartments 7,000.00 10.3 Operable Partitions 10.4 Wall and Door Protection 10.5 Toilet Accessories 3,500.00 _ 10.6 Fire Protection Specialties 10.7 Other: 0.00 _ Subtotal: $ 15,000.00 11 FURNISHINGS 11.1 Casework $ 11,000.00 Subtotal: $ 11,000,00 _ 22 PLUMBING - 22.1 Plumbing $ 34,000.00 Subtotal: $ 34,000.00 _ 23 IL HEATING VENTILATING AND AIR CONDITIONING 23.1 Common Work Resultsfor HVAC $ 12,000.00 _ 23.2 Testing,Adjusting,and Balancing for HVAC 23.3 Commissioning of HVAC 23.4 Instrumentation and Controls 2,000.00 Subtotal: $ 17,500.00 26 ELECTRICAL 26.1 General Electrical $ 19,000.00 _ 26.2 Solar panels inverters transfer switches 26.3 Interior Lighting 5,500.00 26.4 Exterior Lighting 4,500.00 _ 26.5 Other: Subtotal: $ 29,000.00 3 of 6 Price Proposal Spreadsheet Addendum No. Two Price Proposal Spreadsheet 32 . EXTERIOR IMPROVEMENTS 32.1 Concrete walkway $ 69.949.00 32.2 Concrete Planter improvements 32.3 North CMU Wall Renovation 4,000.00 32.8 Other: 5,000.00 Subtotal: $ 82,449.00 . 33 UTILITIES J 33.1 Utility Connections $ 10,000,00 33.6 Other: Subtotal: $ 10.000_00 Total: $ 591,000.00 Notes: The purpose of Allowance line items is to accommodate scope beyond the minimum requirements described in the RFP.As all Respondents are asked to carry the same allowance values,the inclusion of allowances will have no impact on price competitiveness among the Respondents.Allowances are to be implemented using the following concepts: • During project execution,the expenditure of Allowances is solely at city's discretion; • As established,Allowances are intended as"not-to-exceed"budgets for each scope item; • Additional funds required for unanticipated or expanded scope forAllowance-related items may be covered under Change Order provisions,at city's discretion; • Once scope is better defined,the DBE will be required to estimate for and then document actual costs incurred for Allowance items; • Only actual cost expended,including fee for overhead and profit,for Allowances will be reimbursed to the DBE; • At the completion of the project,any remaining allowances belongs to city of Santa Ana. 4 of 6 Price Proposal Spreadsheet EXHIBIT C w � CITY OF SANTA ANA EXHIBIT 3 - INSURANCE REQUIREMENTS Contractor shall procure and maintain for the duration of the contract, and for 5 years thereafter, insurance against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the work hereunder by the Contractor, its agents, representatives, employees, and sub- contractors. MINIMUM SCOPE AND LIMIT OF INSURANCE Coverage shall be at least as broad as: 1. Commercial General Liability (CGL). Insurance Services Office (ISO) Form CG 0001 covering CGL on an "occurrence" basis, including products and completed operations, property damage, bodily injury and personal & advertising injury with limits no less than $2,000,000 per occurrence and $4,000,000 in the aggregate. Umbrella and excess insurance policies can be used to meet the required limits. 2. Automobile Liability(AL). Insurance Services Office Form CA 0001 covering Code 1(any auto), with combined single limit no less than $2,000,000. 3. Workers'Compensation (WC). As required by the State of California,with statutory limits, and Employers' Liability insurance with a limit of no less than $1,000,000 per accident, policy, employee for bodily injury or disease. 4. Pollution Legal Liability (PILL). With limits no less than $1,000,000 per occurrence or claim, and $2,000,000 policy aggregate. 5. Professional Liability (Errors& Omissions)(PL). With limits no less than $1,000,000 per occurrence or claim, and $2,000,000 aggregate. These insurance requirements shall not in any way act to reduce coverage that is broader or includes higher limits than the minimums shown above. If Contractor maintains broader coverage and/or higher limits than the minimums shown above, City shall be entitled to the broader coverage and/or the higher limits maintained by Contractor. Insurance provided under this contract shall not contain any restrictions or limitations which are inconsistent with City's rights under this contract. Other Insurance Provisions The insurance policies are to contain, or be endorsed to contain,the following provisions: 1. City of Santa Ana, its City Council, officers, officials, employees, agents, and volunteers are to be covered as additional insureds on Contractor's CGL and AL policies with respect to liability arising out of work operations performed by or on behalf of Contractor including materials, parts, and equipment furnished in connection with such work or operations and automobiles owned, leased, hired, or borrowed by or on behalf of Contractor. Additional insured status can be provided in the form of an endorsement to Contractor's insurance. 2. For any claims related to this project, Contractor's insurance coverage shall be primary insurance coverage as respects City of Santa Ana, its City Council, officers,officials, employees, agents, and volunteers.Any insurance (9) CITY OF SANTA ANA or self-insurance maintained by City of Santa Ana, its City Council, officers, officials, employees, agents, or volunteers shall not contribute with it. 3. A severability of interest provision must apply for all the additional insureds, ensuring that Contractor's insurance shall apply separately to each insured against whom a claim is made or suit is brought, except with respect to the insurer's limits of liability. 4. Contractor hereby grants to City a waiver of subrogation which any insurer of said Contractor may acquire against City of Santa Ana, its City Council,officers, officials, employees, agents and volunteers by virtue of the payment of any loss under Contractor's CGL, AL, WC, PLL, and PL policies. Contractor agrees to obtain any endorsement(s)that may be necessary to affect this waiver of subrogation, but this provision applies regardless of whether or not City has received a waiver of subrogation endorsement from any insurer(s). S. Each insurance policy required by this clause shall provide that coverage shall not be canceled, suspended, voided, reduced in scope or in limits, non-renewed by the carrier, or materially changed except after thirty (30) days prior written notice has been given to City and ten (10) days prior written notice of policy cancellation or non-renewal due to non-payment. 6. Certificate Holder on each Evidence of Insurance certificate shall be: City of Santa Ana,Attention: (Name of Department Staff Responsible for Agreement),Address of Department Responsible for Agreement, M-XX, Santa Ana, CA 92701.The name and location of the project must be indicated in the Description of Operations section of each certificate. Claims Made Policies If any coverage required is written on a claims-made coverage form: 1. The retroactive date must be shown, and this date must be before the execution date of the contract. 2. Insurance must be maintained and evidence of insurance must be provided for at least five (5)years after completion of work. 3. If coverage is cancelled or non-renewed, and not replaced with another claims-made policy form with a retroactive date prior to the contract effective, or start of work date, Contractor must purchase extended reporting period coverage for a minimum of five (5)years after completion of work. 4. A copy of the claims reporting requirements must be submitted to City. Acceptability of Insurers Insurance is to be placed with insurers authorized to conduct business in the state of California with a current A.M. Best rating of no less than A:VII, unless otherwise acceptable to CITY. Waiver of Subrogation Contractor hereby agrees to waive rights of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss. Contractor agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation. The Workers' Compensation policy shall be endorsed with a waiver of subrogation in favor of City for all work performed by Contractor, its employees, agents and sub- contractors. Verification of Coverage (9) CITY OF SANTA ANA Contractor shall furnish City with original Certificates of Insurance including all required amendatory endorsements (or copies of the applicable policy language effecting coverage required by this clause).A statement on a Certificates)/Evidence of Insurance will not be accepted in lieu of the actual endorsements required herein. Failure to obtain the required documents prior to the work beginning shall not waive Contractor's obligation to provide them. City reserves the right to require complete, certified copies of all required insurance policies, including endorsements, required by these specifications, at any time. Sub-Contractors Contractor shall require and verify that all sub-contractors maintain insurance meeting all requirements stated herein, and Contractor shall ensure that City is an additional insured on insurance required from sub- contractors. For CGL coverage, sub-contractors shall provide coverage with a form at least as broad as CG 20 38 0413. Failure to Maintain Insurance Coverage If Contractor,for any reason,fails to maintain insurance coverage which is required pursuant to this contract, the same shall be deemed a material breach of contract. City, at its sole option, may terminate this contract at any time and obtain damages from Contractor resulting from said breach. Special Risks or Circumstances City reserves the right to modify these requirements, including limits, based on the nature of the risk, prior experience, insurer, coverage, or other circumstances. PWA 06_Exh 1 Agreement (27-6004) - A's Construction (CAO 8.26.26)(2223720. 1 ) Final Audit Report 2026-08-31 Created: 2026-08-31 By: Skylar Wilk(swilk@santa-ana.org) Status: Signed Transaction ID: CBJCHBCAABAAnQOmj02Bxggs74rMohEEKUB5eqx34lqW TWA 06_Exh 1 Agreement (27-6004) - A's Construction (CAO 8 .26.26)(2223720. 1 )" History Document created by Skylar Wilk (swilk@santa-ana.org) 2026-08-31 -8:47:58 PM GMT Document emailed to Rudy Rosas (rrosas@santa-ana.org) for signature 2026-08-31 -8:48:06 PM GMT Email viewed by Rudy Rosas (rrosas@santa-ana.org) 2026-08-31 -8:54:41 PM GMT Signer Rudy Rosas (rrosas@santa-ana.org) entered name at signing as Rodolfo Rosas 2026-08-31 -9:04:27 PM GMT Document e-signed by Rodolfo Rosas (rrosas@santa-ana.org) Signature Date:2026-08-31 -9:04:29 PM GMT-Time Source:server-Signature Appearance Selected:TYPE Agreement completed. 2026-08-31 -9:04:29 PM GMT Adobe Acrobat Sign MAYOR CITY MANAGER Valerie Amezcua Alvaro Nunez MAYOR PRO TEMP CITY ATTORNEY David Penaloza i Sonia R. Carvalho COUNCIL MEMBERS CLERK OF THE COUNCIL Thal Viet Phan x"k` . Jennifer L. Hall Benjamin Vazquez Jessie Lopez Phil Bacerra CITY OF SANTA ANA Johnathan Ryan Hernandez PUBLIC WORKS AGENCY 20 Civic Center Plaza M-11 P.O. Box 1988 Santa Ana, CA 92702 (714)647-5690. Fax(714)647-5823 https://www.santa-ana.org/ NOTICE OF EXEMPTION From the Requirements of the California Environmental Quality Act(CEQA) Fee Exemption per California Government Code Section 6103 To: COUNTY CLERK From: City of Santa Ana County of Orange Public Works Agency P.O. Box 238 20 Civic Center Plaza M-11 Santa Ana, CA 92702 Santa Ana, CA 92702 Project Title: Cabrillo Park Restroom and Concession Building Improvements Project Number(s): 27-6004 Project Location: 1820 E Fruit Street, Santa Ana CA 92703 City: Santa Ana County: Orange ER Number: ER-2026-053 Date of Approval: 09/15/2026 Project Description: Restroom and building improvements Applicant Name: City of Santa Ana Public Works Agency Applicant Address: 20 Civic Center Plaza SANTA ANA, CA 92701 Name of Public Agency Approving Project: City Council Name of Agency Carrying Out Project: Public Works Agency Exempt Status: Categorical Exemption 15301(b) Reason(s)Why Project is Exempt From CEQA: 15301 (b) consists of repair/maintenance of existing public facilities. City Contact: Robert Aguirre Title: Senior Civil Engineer Telephone: (714)647-5652 Signature: Date: City of Santa Ana City Council Valerie Amezcua David Penaloza Thal Viet Phan Benjamin Vazquez Jessie Lopez Phil Bacerra Johnathan Ryan Hernandez Mayor Mayor Pro Tem,Ward 6 Ward 1 Ward 2 Ward 3 Ward 4 Ward 5 tphan@santa-ana.org byazquez@santa-ana.org tphan@santa-ana.org byazquez@santa-aua.org jessielopez@santa-ana.org Pbacerra@santa-ana.org jryanhernandez@santa-ana.org