HomeMy WebLinkAbout2026-047 - Walnut Pump Station PFAS Treatment System Funding RESOLUTION NO. 2026-047
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SANTAANA SUPPORTING AND ADOPTING THE FINDINGS
THAT THE CITY OF SANTA ANA WALNUT PUMP STATION
PFAS TREATMENT PROJECT IS EXEMPT FROM CEQA
PURSUANT TO SECTION 15303 OF THE CEQA
GUIDELINES
WHEREAS, the City of Santa Ana staff determined that a treatment plant for per-
and polyfluoroalkyl substances ("PFAS") is required to reduce concentrations in drinking
water extracted from the groundwater basin at existing and future well connections; and
WHEREAS, the City of Santa Ana, in its capacity under the California
Environmental Quality Act (CEQA), has conducted an evaluation of the potential for
environmental impacts associated with the City of Santa Ana Walnut Pump Station PFAS
Treatment Project (including wells 16, 29, 33 and 41); and
WHEREAS, such evaluation determined that the City of Santa Ana Walnut Pump
Station PFAS Treatment Project is consistent with the applicable Categorical Exemption
(Class 3, Section 15303) under CEQA as it consists of the construction and operation of
a treatment plant at Walnut Pump Station for the treatment of PFAS contaminants from
several existing groundwater production well sites. The treatment plant will use ion
exchange (IX) treatment protocol through the use of IX vessels along with associated
water conveyance facilities. The sites have been disturbed by the development of the
existing groundwater production wells, and the Project would not require any new ground
disturbances. The facility would treat groundwater pumped from the production wells and
convey it to existing water distribution pipelines for potable water consumption. The
Project would not require any vegetation removal and occurs within an area that is highly
urbanized.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Santa
,Ana, that:
Section 1. Adopts the finding that the City of Santa Ana Walnut Pump Station
PFAS Treatment Project is exempt from CEQA pursuant to Section 15303 of the CEQA
Guidelines because it consists of the construction and operation of small treatment plant
and associated connection facilities at previously disturbed sites representing the
development of limited numbers of new, small facilities or structures and it would not result
in any significant impacts to the environment.
Section 2. This Resolution shall take effect immediately upon its adoption by the
City Council, and the City Clerk shall attest to and certify the vote adopting this Resolution.
Resolution No. 2026-047
Page 1 of 2
ADOPTED this 6t" day of October, 2026.
Valtr
ie Am cua
Ma
APPROVED AS TO FORM:
Sonia R. Carvalho, City Attorney
By:
-Z114 lka��
Ky ellesen
Assistant City Attorney
AYES: Councilmembers Amezcua Bacerra Hernandez Penaloza
Phan Vazquez 6
NOES: Councilmembers None (0)
ABSTAIN: Councilmembers None 0
ABSENT: Councilmembers Lopez (1)
CERTIFICATE OF ATTESTATION AND ORIGINALITY
1, JENNIFER L. HALL, City Clerk, do hereby attest to and certify the attached Resolution
No. 2026-047 to be the original resolution adopted by the City Council of the City of Santa
Ana on October 6, 2026. ,• l,
{{
Date:
ennifer all
Ci r
C ity a
Resolution No. 2026-047
Page 2 of 2