TOPIC: Annual Public Financing Authority Update
AGENDA TITLE
Annual Public Financing Authority Update
RECOMMENDED ACTION
Receive and file the annual Public Financing Authority Update.
GOVERNMENT CODE §84308 APPLIES: No
DISCUSSION
The Santa Ana Public Financing Authority(Financing Authority) is required to hold at least
one regular meeting each calendar year. This report provides the 2026 annual update,
including background on the Financing Authority, the use of Water Revenue Bond
proceeds, required annual debt reporting, and an update on the credit rating for the 2024
Water Revenue Bonds. All required FY 2024-25 debt reports were submitted on time.
On May 7, 2024, the City Council authorized the establishment of the Financing Authority
through a Joint Exercise of Powers Agreement (JEPA). The Financing Authority is a
separate legal entity established to issue bonds to finance City projects. The Financing
Authority's bylaws provide that:
• The governing body, the Board of Directors of the Financing Authority, consists of
the Mayor and the members of the City Council.
• Any regular meeting of the Board of Directors is held at the same time and location
as the regular meetings of the City Council.
• The Board of Directors conducts a regular meeting at least once each calendar
year, on the first Tuesday of December.
Because no regular meeting is scheduled for the first Tuesday of December 2026, staff
is providing this update in November.
2024 Water Revenue Bonds
On June 4, 2024, the City Council authorized the issuance and sale of Water Revenue
Bonds to fund improvements to the City's aging water infrastructure. The Financing
City Council 3 - 1 11/17/2026
Annual Public Financing Authority Update
November 17, 2026
Page 2
Authority issued the bonds on June 11, 2024, and the transaction closed on June 27,
2024.
The bonds have a principal amount of$44.16 million and generated approximately $49.4
million in total proceeds, including a $5.21 million premium paid by investors. Of the total
proceeds, the City allocated $40 million to water infrastructure projects, $9.03 million to
refinance the 2014 Water Bonds, and $0.34 million for issuance costs. The City will repay
the bonds through 2049. On November 4, 2025, the City Council approved reallocating
project funds to align bond proceeds with current infrastructure priorities. The revised
project allocations are summarized below.
Project Project Name Original Bond Updated Bond
No. Allocation Allocation
16-6460 Advanced Water Meters $ 15,000,000 $ 13,310,000
NIA Walnut Pump Station PFAS $ 5,000,000 $ 0
Improvements
NIA Garthe Pump Station Improvements $ 5,000,000 $ 0
26-6424 Large Water Services Vault & Meter $ 8,000,000 $ 2,400,000
Apparatus Improvements
26-6425 Washington Well Improvements— $ 6,000,000 $ 2,430,000
Phase II
NIA Citywide Facilities Electrical $ 1,000,000 $ 0
Improvements
13-6433 Well 32 Rehabilitation $ 0 $ 4,850,000
15-6445 Bristol Street Water Main $ 0 $ 1,000,000
Im rovements Phase 3A
18-6491 Well 29 Improvements $ 0 $ 3,000,000
19-6499 Bristol Street Water Main $ 0 $ 2,300,000
Improvements Phase 4
26-6426 Citywide Facilities PFAS $ 0 $ 6,000,000
Im rovements
19-6428 Lacy Neighborhood Water Main $ 0 $ 1,000,000
Im rovements
26-6427 Citywide Water Improvements $ 0 $ 3,110,000
26-6428 Fire Hydrant Improvements $ 0 $ 600,000
Total $ 40,000,000 $ 40,000,000
Annual Reporting Requirements
The City is required to submit annual debt reports to federal and state agencies to provide
transparency regarding its outstanding debt and the use of bond proceeds.
• Federal Reporting: Under Securities and Exchange Commission (SEC) Rule
15c2-12 and the City's continuing disclosure agreements, the City must submit
annual financial and operating information and report certain events through the
Municipal Securities Rulemaking Board's (MSRB) Electronic Municipal Market
Access (EMMA) system.
City Council 3 - 2 11/17/2026
Annual Public Financing Authority Update
November 17, 2026
Page 3
• State Reporting: California Government Code Section 8855(k) requires state and
local debt issuers to submit an Annual Debt Transparency Report to the California
Debt and Investment Advisory Commission (CDIAC) within the State Treasurer's
Office. The report documents debt authorized, debt outstanding, and the use of
debt proceeds during the reporting period. Reports are due by January 31 for the
fiscal year ending the preceding June 30.
All required FY 2024-25 annual debt reporting filings were submitted on time.
Credit Ratings Update
In October 2025, Standard & Poor's (S&P) Global Ratings revised its outlook on the 2024
Water Revenue Bonds from stable to negative while affirming the bonds' AA long-term
rating. The negative outlook reflects declining cash reserves in the Water Enterprise as
operating costs have increased without corresponding water rate adjustments.
S&P indicated that it could downgrade the credit rating if the Water Enterprise's financial
position does not improve over the next couple of years. Staff is proposing water and
sewer rate adjustments for City Council consideration in February 2027 to help improve
the Water Enterprise's financial position. Staff will continue monitoring the Water
Enterprise's financial performance and its ability to meet future debt payments.
ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.
FISCAL IMPACT
There is no fiscal impact associated with this action.