HomeMy WebLinkAbout23A - BRISTOL WIDENING - MCFADDEN TO PINE REQUEST FOR COUNCIL ACTION* CITY COUNCIL MEETING DATE: CLERK OF COUNCIL USE ONLY: NOVEMBER 15, 2010 TITLE: APPROVED INCREASE CONTINGENCY FOR ? As Recommended BRISTOL STREET WIDENING FROM ? As Amended MCFADDEN AVENUE TO PINE 171 Ordinance on Reading El Ordinance on 2 n d Reading STREET (PROJECT NO. 061500) ? Implementing Resolution ? Set Public Hearing For CONTINUED TO l FILE NUMBER CITY MANAGER RECOMMENDED ACTION Increase the contingency for the contract with All American Asphalt for the Bristol Street Widening Project by $200,000 to a total estimated contract amount of $10,178,904 and authorize the City Manager to execute change orders up to the contingency amount. DISCUSSION On May 4, 2009, the City Council awarded a contract for the Bristol Street Widening Project to All American Asphalt in the estimated amount of $8,315,754 plus a contingency of $1,663,150 totaling $9,978,904. While constructing Bristol Street, several unforeseen conditions have exhausted the approved contingency; consequently, additional funds are required to complete the work. The work includes revising the striping plan to include a bike lane on Bristol Street between Cubbon and Walnut Streets, adding new conduit to preserve the link between the traffic signals in the area and the traffic management center, constructing new sidewalk at intersecting streets and retaining curb, and repairing existing block wall to match the new adjacent improvements and street asphalt sections. ENVIRONMENTAL IMPACT This is no environmental impact associated with this action. 23A-1 Increased Contingency for Bristol Street Widening for McFadden Avenue to Pine Street November 15, 2010 Page 2 FISCAL IMPACT The contingency increase and additional contract amount are estimated at $200,000. Funds are available in the Select Street Construction Fund (accounting unit 05917661-66220) and the Measure M Street Construction Fund (accounting unit 03217660-66220). APPROVED AS TO FUNDS AND ACCOUNTS: Raul Godi z II Francisco Gutierrez G Executive Director Executive Director I Public Works Agency Finance & Management Services Agency RG/DI 23A-2