HomeMy WebLinkAbout23B - PROJ - SANTA CLARA AVE SEWER AND WATER MAINREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
MARCH 21, 2011
TITLE:
CONTRACT AWARD FOR SANTA
CLARA AVENUE SEWER AND WATER
MAIN IMPROVEMENTS
(PROJECT NOS. 106600 & 116409)
C/tom
CIT MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
? As Recommended
? As Amended
? Ordinance on 1 s` Reading
? Ordinance on 2nd Reading
? Implementing Resolution
? Set Public Hearing For
CONTINUED TO
FILE NUMBER
1. Award a contract to Garcia Juarez Construction, Inc., the lowest responsible bidder, in
accordance with unit bid prices in the estimated amount of $1,196,325 for construction of
Santa Clara Avenue sewer and water main improvements.
2. Approve a funding analysis with a total estimated construction cost of $1,495,400.
DISCUSSION
This project provides for the replacement of deteriorated and undersized sewer and water pipes
(Exhibit 1). The improvements include installation of new sewer and water mains, fire hydrants,
main gate valves, and water services. Once completed, water main breaks and leaks associated
with the older and deteriorated water mains will be eliminated. In addition, sewer capacity will be
increased, and water service capacity and fire protection will be enhanced.
The Notice Inviting Bids was advertised on December 13 and 15, 2010, and bids were opened on
January 6, 2011. A summary of the bid invitations mailed, the bids received, and the bid results
follows.
Santa Ana Contractors receiving notices:
Contractors requesting bidding documents:
Bids received:
Bids received from Santa Ana Contractors:
8
28
13
0
23B-1
Contract Award For
Santa Clara Avenue Sewer and
Water Main Improvements
March 21, 2011
Page 2
NAME OF RESPONSIVE BIDDER CITY BID AMOUNT
1. Garcia Juarez Construction, Inc. Brea $1,196
325.00
2. Mike Bubalo Construction Company Baldwin Park ,
$1,241,900.00
3. Nikola Corporation Irvine $1,311,370.00
4. Dominguez General Engineering, Inc. Rosemead $1,311,645.00
5. Kana Pipeline, Inc. Placentia $1,370,000.00
6. J. De Sigio Construction, Inc. Baldwin Park $1,374,575.00
7. T.E. Roberts, Inc. Tustin $1,404
072.50
8. Vido Artukovich & Son, Inc. S. El Monte ,
$1,422
800.00
9. T. B. U., Inc. Beaumont ,
$1,532
985.00
10. MNR Construction, Inc. San Dimas ,
$1,537
400.00
11. J. A. Salazar Construction & Supply La Habra ,
$1,594
605.00
12. Savala Construction Irvine ,
$1,740
692.15
13. Blois Construction, Inc. Oxnard ,
$1,861,130.00
While the City made outreach efforts to Santa Ana contractors regarding the Notice Inviting Bids,
no contractors from Santa Ana submitted bids. The eight Santa Ana contractors did not submit a
bid either because they are not capable of performing this type of work, unable to obtain insurance
because the project is too large, or they work as a subcontractor only for certain prime contractors.
A total of 13 bids were received and all were responsive. The lowest bid was submitted by Garcia
Juarez Constriction, Inc., for $1,196,325 which is below the Engineer's estimate of $1,497,500.
BID PROTEST
The Public Works Agency issued a Notice Inviting Bids for the above project. After bids were
opened on January 6, 2011, the City received a bid protest from Mike Bubalo Construction Co.,
Inc., alleging that the low bidder submitted a late bid, and should have been disqualified. The
contractor asserted that the late filing cannot be waived because it is a material irregularity which
affects the amount of the bid and/or gives the late bidder an advantage over other bidders.
The protesting party has the burden of proof to demonstrate that the staff's determination of
proposed low bidder is arbitrary and capricious, or unsupported by substantial evidence in the
record.
The parties agree to the following facts:
The Notice Inviting Bids provides that the City will receive sealed bids "on or before the hour of
2:00 p.m." Additionally, the Instructions to Bidders warns that it is the bidder's responsibility to
ensure delivery of the proposal to "...the Public Works Agency, Fourth Floor Receptionist, prior
to the bid opening hour stipulated in the Notice Inviting Bids. Late proposals will not be
considered."
23B-2
Contract Award For
Santa Clara Avenue Sewer and
Water Main Improvements
March 21, 2011
Page 3
• The low bid, submitted by Garcia Juarez Construction, Inc., was handed to the City at
approximately 2:00:10. The envelope was returned to the bidder as it was not properly sealed,
whereupon, the low bidder's representative sealed the envelope and returned it to the Public
Works representative at 2:00:40.
• The bid was accepted by a representative from the Public Works Agency and was eventually
determined to be the low bidder.
• The second low bidder timely submitted a protest asserting that the delivery of the bid at
2:00:40 did not conform to the bid specifications and the bid should not have been accepted.
• Both state law and the City's bid documents and policies prohibit the consideration of late bids.
Cal. Government Code §53068, Cal Public Contract Code §10168.
The dispute rests on each party's interpretation of "on or before" the hour of 2:00 p.m.
The protesting party contends that any bid submitted after 2:00:00 is late. In support of its
contention, the protesting party stated that it has submitted bids in many cities and the majority of
those cities close their bid at the beginning of the hour. However, some cities utilizing a time clock
without a second hand do allow bids until 2:01. Other cities' language regarding bid closure time
was not provided.
Santa Ana normally utilizes a time stamp that is accurate to the minute. Therefore, City policy has
been that any bid submitted until 2:01 will be accepted. At 2:01 p.m., the bid would be deemed
late.
On the date the subject bid was closed, the time stamp was not working and interested bidders
were watching the digital clock located behind the clerk's desk, which registers seconds. In
compliance with the City's practice of accepting bids at 2:00, which includes the 59 seconds
between 2:00:00 and 2:01, the City accepted bids until the digital clock registered 2:01.
The parties agree that if the bid was submitted late, the City could not accept it. However, the
protesting party did not demonstrate that the City's policy of including the 59 seconds between
2:00:00 and 2:01:00, in its interpretation of "on or before 2:00 p.m." is arbitrary or capricious.
Therefore, the bid submitted by Garcia Juarez Construction, Inc., was determined to be filed on
time and should be accepted by the City of Santa Ana.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended action is exempt
from further review. Categorical Exemption Environmental Review No. 2011-03 has been filed.
23B-3
Contract Award For
Santa Clara Avenue Sewer and
Water Main Improvements
March 21, 2011
Page 4
FISCAL IMPACT
The funding analysis shows a total estimated construction cost of $1,495,400 for the project
(Exhibit 2). Funds are available in the Water Utility Capital Projects Fund (accounting unit
06617647-66301) and the Sewer Services Capital Projects Fund (accounting unit 05517660-
66220).
Raul Godinez I
Executive Director,,
Public Works Agency
APPROVED AS TO FUNDS AND ACCOUNTS:
Francisco Gutierrez
Executive Director
Finance & Management Services Agency
RG/WA
Exhibit 1: Project Location Map
2: Funding Analysis
23B-4
EXHIBIT 1
VICINITY MAP
NOT TO SCALE
SANTA ANA r tG?
M ¦?? City Council Title: ,oP-- -•._?,
P W A ¦ SANTA CLARA AVE
Agenda Date SEWER AND WATER MAIN IMPROVEMENTS
PUBLIC WORKS AGENCY March 21, 2011 PROJECT NO. 10-6600 AND 11-6409
23B-5
23B-6
FUNDING ANALYSIS
PROJECT NOS. 106600 AND 116409
SANTA CLARA AVENUE SEWER AND WATER MAIN IMPROVEMENTS
Construction Contract
Contract Administration
Inspection and Testing
Survey Staking
Contingencies
TOTAL ESTIMATED CONSTRUCTION COSTS
Exhibit 2
$1,196,325
$34,443
$90,000
$55,000
$119,632
$1.495,400
23B-7
23B-8