HomeMy WebLinkAbout05 - Coop Agmt - Parking Lot 3rd-Bush
AGENCY DOARD MEETING DATE:
MAY 16, 2011
TITLE:
COOPERATIVE AGREEMENT -
PARKING LOT IMPROVEMENTS AT 3Ro
AND BUSH STREETS METERED
PARKING LOT
IIVTERI EXECUTIVE DIRECTOR
C ENDED ACTION
AGENCY SECRETARY USE 0(dLY:
APPROVED
^ As Recommended
^ As Amended
^ Ordinance on 15t Reading
^ Ordinance on 2"d Reading
^ Implementing Resolution
^ Set Public Hearing For
CONTINUED TO
FILE NUMBER
Authorize the Executive Director and Agency Secretary to execute the attached Cooperative
Agreement with the City of Santa Ana in the amount of $262,725, subject to non-substantive
changes approved by the Executive Director and Agency General Counsel.
DISCUSSION
The Community Redevelopment Agency (Agency) owns the public metered surface parking lot
located at the northeast corner of 3rd and Bush Streets. The parking lot holds a total of 63
parking spaces and services the general downtown area and the Artist Lofts. With years of
continuous use, the parking lot is in need of capital repairs that include resurfacing, new
landscaping, upgrading the irrigation system, enhancing the operational equipment and
upgrading the lighting. The Agency is proposing improvements to the parking lot in efforts to
make the parking lot more inviting and to provide a safer environment by upgrading the existing
lighting to comply with current codes. Once completed, these improvements will enhance the
surface quality and visual appearance of the parking lot.
At the same time the improvements are done at the 3rd and Bush Streets parking lot, the Agency
is seeking to upgrade the equipment by removing the individual parking meters and installing a
single pay station that will service the entire parking lot. The pay station will allow patrons the
capability of paying the parking meter fees via coin or credit card. Neither the new equipment
nor landscape and irrigation upgrades are included as part of the City's Parking Lot and Parks
Improvement Project. Therefore, the landscape and irrigation upgrades will be contracted for
separately. The upgraded equipment will be purchased and maintained by Parking Concepts
Inc., the current contract administrator for the City's parking structures in the Downtown.
5-1
Cooperative Agreement -
Parking Lot Improvements
May 16, 2011
Page 2
The City is in the process of renovating several parking lots at various park site locations. For
cost efficiencies, this project was bid as part of the City's Parking Lot and Parks Improvement
Project. The cooperative agreement provides for the Agency to fund the cost of the
improvements to the public parkng lot located at the northeast corner of 3~d and Bush Streets.
Based on the terms of the cooperative agreement, the Redevelopment Agency will reimburse the
City for all improvements including the future landscaping and upgraded irrigation of the parking
lot. The public parking lot is located within the Merged Project Area.
FISCAL IMPACT
Funds are available in the Merged Capital Projects (accounting unit 57018830-66220).
APPROVED AS TO FUNDS AND ACCOUNTS:
~~
.~
`~ ~` r
, ~
.. '. ~az ~ .~
,
Gab~iela P. Lomeli
Redevelopment Project Manager 1
Community Development Agency
Francisco Gutierrez `
Executive Director
Finance & Mgmt. Services Agency
NTE/GPL/mlr
Exhibit: 1. Cooperative Agreement
5-2
COOPERATIVE AGREEMENT BETWEEN THE
COMMiJNITY REDEVELOPMENT AGENCY
AND THE CITY OF SANTA ANA FOR
CONSTRUCTION IMPROVEMENTS AT THE THIRD AND
BUSH SURFACE PARKING LOT
THIS COOPERATIVE AGREEMENT is entered into this 16t~ day of May, 2011, by and
between the COMIVIUN][TY REDEVELOPMENT AGENCY OF THE CITY OF SANTA ANA, a
public body corporate and politic (the "Agency"), and the CITY OF SANTA ANA, a charter city
and municipal corporation duly organized and existing under the Constitution and laws of the State
of California (the "City").
WITNESSETH
A. The Agency is undertaking certain activities necessary for the execution of the City
of Santa Ana redevelopment projects (the "Projects") under the provisions of the California
Community Redevelopment Law (Health and Safety Code Section 33000 et seq.) and pursuant to
the redevelopment plans for the Projects.
B. The Agency desires to contract with the City for the City to provide for the
construction of public improvement projects which, in this case, will consist of the capital
improvements to the Agency-owned parking lot at Third and Bush Street ("Parking Lot") located
within the Merged Project Area (Central City Project Area). Such work will be referred to
hereinafter as "Publicly Owned Improvements" in connection with the Agency's redevelopment
activities within the Merged Project Area
C. The Agency is willing in connection with the provision of such Publicly Owned
Improvements by the City, to pay for a portion of the total construction costs of such Publicly
Owned Improvements.
D. The City has initially paid or will initially pay for said Publicly Owned
Improvements on the condition that the Agency contribute to the costs of such construction work on
the Publicly Owned Improvements.
E. The City and Agency by resolution have each found that the use of Agency
redevelopment funding for the Publicly Owned Improvements included herein is in accordance
with Section 33445 and 33445.1 of the Community Redevelopment Law ("CRL") and other
applicable law. Such Council and Agency resolutions dated March 1, 2011, are each based on the
authority, with the consent of the Council, to pay all or part of the cost of the installation and
construction of any building, facility, structure, or other improvement which is publicly owned,
either within or outside a Project Area, if the City Council makes certain determinations.
NOW, THEREFORE, the parties hereto do mutually agree as follows:
EXHIBIT 1
G 1
1. SCOPE OF WORK
A. The City will be contracting with the lowest and best bidder to perform the Parking Lot
construction improvements pursuant to plans and specifications to be prepared by the City. The
work consists of capital improvements to the parking lot that includes resurfacing, new landscaping,
upgrading the irrigation system, enhancing the parking equipment and upgrading the lighting to
comply with current codes. The Agency is also seeking to upgrade the equipment by removing the
individual parking meters and installing a single pay station that will service the entire Parking Lot.
B. It is the responsibility of the City to pay all development and construction costs in
connection with these Publicly Owned Improvements from funds paid to the City by the Agency
under this Agreement.
C. The Agency authorized the City to collect all parking revenues from said Parking Lot on
behalf of the Agency and all money deposited in said parking meters/pay station shall be
deposited in a special fund, to be known as the "Parking Meter Fund," and shall be used
exclusively for the purchase, installation, maintenance, repair, servicing and policing of said
parking meters and pavement markings in the traffic zones wherein parking is regulated or
controlled by parking meters for the proper regulation of traffic, the elimination of traffic
violations upon the public streets of the city, for the elimination of traffic hazards, the
realignment, improvement and widening of streets to expedite orderly traffic movement, the
purchase, installation and maintenance of mechanical traffic-control devices, and the purchase or
lease and operation of land for off-street parking within
the City, or any of them, as the council may determine.
D. The City shall perform its obligations hereunder in accordance with all applicable
provisions of federal, state and local laws, including its obligation to comply with environmental
laws such as CEQA, and shall timely complete the work required for the Publicly Owned
Improvements referenced herein.
2. COMPENSATION AND METHOD OF PAYMENT
The Agency shall contribute to the construction of the Publicly Owned Improvements in an
amount not to exceed Two Hundred Sixty Two Thousand Seven Hundred Twenty Five Dollars
($262,725.00), with the breakdown of project costs as shown in Exhibit A attached hereto and
incorporated herein. The Agency shall pay the City the actual cost incurred by the City for the
Publicly Owned Improvement construction work set forth in Section 1. The amount to be paid by
the Agency hereunder shall be paid in the same fiscal year as the year in which the debts are
incurred by the City.
3. LIABILITY AND INDEMNIFICATION
In contemplation of the provisions of Section 895.2 of the Government Code of the State of
EXHIBIT 1
G 2 A
California imposing certain tort liability jointly upon public entities solely by reason of such entities
being parties to an agreement as defined by Section 895 of said Code, the parties hereto, as between
themselves, pursuant to the authorization contained in Section 895.4 and 895.6 of said Code, will
each assume the full liability imposed upon it, or any of its officers, agents or employees bylaw for
injury caused by negligent or wrongful act or omission occurring in the performance of this
Agreement to the same extent that such liability would be imposed in the absence of Section 895.2
of said Code. To achieve the above-stated purpose each party indemnifies and holds harmless the
other party for any loss, costs or expense that may be imposed upon such other party solely by
virtue of said Section 895.2. The provisions of Section 2778 of the California Civil Code are made
apart hereof as if fully set forth herein.
4. SEVERABILITY
If any term, provision, covenant or condition of this Agreement is held by a court of
competent jurisdiction to be invalid, void or unenforceable, the remainder of the provisions shall
continue in full force and effect unless the rights and obligations of the parties have been materially
altered or abridged by such invalidation, voiding or unenforceability.
5. TERMINATION
This Agreement maybe terminated by the Agency upon sixty (60) days written notice of
termination. In such event, City shall be entitled to receive and the Agency shall pay City
compensation for all services performed by City prior to receipt of such notice of termination.
However, as a condition of such payment, the Executive Director may require City to deliver to the
Agency all work product completed as of such date, and in such case such work product shall be the
property of the Agency unless prohibited by law, and City consents to the Agency's use thereof for
such purposes as the Agency deems appropriate.
6. EFFECTIVE DATE OF AGREEMENT
This Agreement shall take effect from and after the date of adoption and approval by the
City and the Agency pursuant to official action of the governing bodies thereof and shall be
effective for a duration not to exceed the time necessary for the City to complete the work and for
the Agency to pay the City in full, unless terminated as set forth hereinabove. This Agreement shall
apply to all activities carried out by the City as set forth in Section 1 hereto.
7. BINDING ON SUCCESSORS
Unless terminated pursuant to section 5, this Agreement shall be binding on and shall inure
to the benefit of all successors and assigns of the parties, whether by agreement or operation of law.
EXHIBIT 1
535
IN WITNESS WHEREOF, the parties hereto have executed this Cooperative Agreement the date
and year first above written.
ATTEST:
Maria D. Huizar
Clerk of the Council
CITY OF SANTA ANA
By
David N. Ream
City Manager
ATTEST;
Maria D. Huizar
Secretary
APPROVED AS TO FORM:
Joseph Straka
Interim City Attorney/Agency General
Counsel
By: Lisa E. Storck
Assistant City Attorney/Assistant Counsel
COMMUNITY REDEVELOPMENT
AGENCY OF THE CITY OF SANTA ANA
By:
Nancy T. Edwards
Interim Executive Director
EXHIBIT 1
546
EXHIBIT A
3RD AND BUSH SURFACE LOT IMPROVEMENTS
PROJECT COSTS
Parking Lot Improvements $232,725 (includes upgraded lighting)
Landscape and Irrigation 30 000
$262,725
5-7
THIS PAGE LEFT BLANK INTENTIONALLY
5