HomeMy WebLinkAbout23B - PROJ - REHAB BROADWAY AND WASHINGTON WATER MAIN IMPROVEMENTSREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
AUGUST 5, 2013
TITLE:
CONTRACT AWARD FOR BROADWAY
REHABILITATION FROM CIVIC CENTER
TO SANTA CLARA (PROJECT 11-6743)
AND BROADWAY AND WASHINGTON
AVENUE WATER MAIN IMPROVEMENTS
(PROJECT 11-6415)
f'
CI GER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
? As Recommended
? As Amended
? Ordinance on 1" Reading
? Ordinance on 2nd Reading
? Implementing Resolution
? Set Public Hearing For
CONTINUED TO
FILE NUMBER
1. Award a contract to the lowest responsible bidder, Christensen Brothers General
Engineering, Inc., in accordance with the Base Bid totaling $4,302,858.65 for the construction
of the Broadway Rehabilitation and Broadway and Washington Avenue Water Main
Improvements.
2. Approve the Cost Analysis for a total estimated project delivery cost of $5,163,430.65.
DISCUSSION
This project has received Council budget and funding approval as part of the City's Capital
Improvement Program. Project design is complete and the next step is to construct the
improvements. Procurement procedures have been followed as established by the City's
Municipal Code and in adherence to the Public Contracts Code. The project was advertised for
solicitation of bids, and the recommended action will allow construction to proceed.
The City's Pavement Management System identified Broadway from Civic Center Drive to Santa
Clara Avenue (Exhibit 1) as a high priority for rehabilitation. The pavement has deteriorated due
to weather, age, heavy usage, and poor drainage. Portions of the adjacent curb and gutter,
driveway approaches, curb ramps, and sidewalks are either missing or in disrepair and require
replacement. Improvements include reconstructing the roadway pavement; replacing damaged
concrete curb and gutter, driveway approaches, sidewalk; and constructing new cross gutters.
Once completed, these improvements will extend the life of the pavement and enhance the ride
quality, surface drainage, and appearance of the street.
Other project improvements include replacing deteriorated and undersized water mains on
Broadway and Washington Avenue. This work involves installing new water mains, fire hydrants,
main gate valves, and water services. Once this project is completed, breaks and leaks
23B-1
Contract Award for Broadway Rehabilitation (Pr. 11-6743) and
Broadway and Washington Water Main Improvements (Pr. 11-6415)
August 5, 2013
Page 2
associated with the older and deteriorated water mains will be eliminated, and water service
capacity and fire protection will be enhanced.
The Notice Inviting Bids was advertised on June 10 & 11, 2013, and bids were opened on July 8,
2013. A summary of the bid invitations mailed, bids received, and bid results are as follows:
Contractor Participation Data
Santa Ana Contractors receiving notices: 15
Contractors requesting bidding documents: 14
Bids received: 6
Bids received from Santa Ana Contractors: 0
Bid Results Summary
RANK BIDDER'S NAME LOCATION BASE BID
1 Christensen Brothers General Engineering, Inc. Apple Valley $4,302,858.65
2 Lonerock, Inc. Irvine $4,569,883.00
3 Sally-Miller Contracting, Inc. Brea $4,771,000.00
4 All American Asphalt Corona $5,030,974.00
5 Los Angeles Engineering, Inc. Covina $5,214,016.00
6 Excel Paving Company Long Beach $5,329,910.40
A total of six bids were received and all were deemed responsive, with Christensen Brothers
General Engineering, Inc. submitting the lowest responsive bid. Their $4,302,858.65 bid is 9.5
percent higher than the $3,930,100 Engineer's Estimate. A subsequent review of the Engineer's
Estimate concluded that night work, which may be required due to the potential impact on traffic,
was not accounted for and resulted in a lower estimate. Staff has also begun to notice
construction costs trending up associated with greater construction activity. Nonetheless, staff is
confident that the current bids are very competitive and that the low bid represents a very good
price.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, this project is exempt from further
review. Categorical Exemptions Environmental Review No. 2012-24 was filed for this project.
FISCAL IMPACT
The Project Cost Analysis (Exhibit 2) determined that the total funds needed to deliver the project
are $5,163,430.65. The total cost includes construction administration, testing, and
contingencies.
23B-2
Contract Award for Broadway Rehabilitation (Pr. 11-6743) and
Broadway and Washington Water Main Improvements (Pr. 11-6415)
August 5, 2013
Page 3
Funding for the Broadway Rehabilitation (Pr. 11-6743) is available in the Proposition 1B - State
Local Partnership Program (SLPP) Fund (Account 03017660-66220), Measure M2 Local
Fairshare Fund (Account 03217662-66220) and Traffic Congestion Relief HUT Fund (Account
05917663-66220). Funding for the Broadway and Washington Water Main Improvements
(Project 11-6415) is available in the Water Utility Capital Projects Fund (Account 06617647-
66301).
APPROVED AS TO FUNDS AND ACCOUNTS:
Edwin "William" GaT ; P.E.
Acting Executive iD ror
Public Works Agency
RG/CC
Exhibit 1: Project Location Map
2: Cost Analysis
Francisco Gutierrez
Executive Director
Finance & Management Services Agency
23B-3
23B-4
I
I
WA8FNOTON ST
BUFFALO AVE
EXHIBIT 1
AVE
SANTA ANA PROJECT NO. *W43 BROADWAY ORATION
CRY FROM CIVIC CENTER DR TO SANTA CLARA AVEW E
p AGENDA DATE: PROJECT NO. U-6415 BROADWAY AND WABFNGION
AUGUST 05, 2013 AVENA= WATER MAN UTME MENTS
K. WASHINGTON U'ROVEIWENTS FROM
SYCAMORE TO MAN STREET
/ N OR4N 1
tiOi N/ `eC
?O
iaw-
23B-5
23B-6
COST ANALYSIS
PROJECT NO. 116743 AND 116415
BROADWAY REHABILITATION AND BROADWAY AND WASHINGTON AVENUE
WATER MAIN IMPROVEMENTS
Construction Contract $4,302,858.65
Contract Administration $172,114
Inspection and Testing $129,086
Survey $129,086
Contingencies $430,286
TOTAL ESTIMATED PROJECT DELIVERY COSTS $5.163.430.65
EXHIBIT 2
23B-7
23B-8